ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Tycoons Square Avenue I Tower D

Registration lapsed No litigation declared Others project

Tycoons Square Avenue I Tower D

By Tycoons Avanti Projects LLP

RG-MH-21710 · RERA P51700023614 · Last updated on MahaRERA portal: 23 Aug 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 12 months past the filed date
  • 19 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Oct 2025Possession promised12 months past this date
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 23%
19Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

Tycoons Square Avenue I Tower D is a Others project by Tycoons Avanti Projects LLP in Thane, Maharashtra, registered with MahaRERA as P51700023614 on 20 Dec 2019. Possession was promised by 30 Oct 2025 and is now 12 months past that date. 19 complaints are on record with the regulator.

At a glance

Project

  • NameTycoons Square Avenue I Tower D
  • TypeOthers
  • Location
    • Birla College Road
    • Chikanghar
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • RERA no.P51700023614
  • ReraGenie IDRG-MH-21710

Builder

  • NameTycoons Avanti Projects LLP
  • Entity typeOthers
  • PartnerShrikant D Shitole Digambar Shitole
  • Other registrations6 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

12 months past promisethis monthRegisteredDec 2019PromisedOct 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Dec 2019
  • Promised completion30 Oct 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tycoons Goldmine Avenue I DNA340000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 23%.

Tycoons Goldmine Avenue I D: 48% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure23%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 23 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Club House only for residential unitsYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,939 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
Chikanghar Tiranga Co-operative Housing SocietiesKalyanThane
Chikanghar Trilok Co-operative Housing SocietiesKalyanThane
Gajanan Co-operative Housing SocietyKalyanThane
Chikanghar Tiranga CHSLChikangharThane
Chikanghar Trilok CHSLChikangharThane
Gajanan CHSLChikangharThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Muncipal Corporation
Permissible FSI11887.96
Proposed, not sanctioned9,866 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Consortium
ArchitectLokhandwalla F T
EngineerVastech Consultants & Engineers LLP
Chartered AccountantAmrrita Jagnaani
Chartered AccountantTausif Shaikh
Chartered AccountantVenkat Raghunath chari
Chartered AccountantMOK & ASSOCIATES
PartnerRole in project
Tycoons Avanti Projects Pvt. Ltd.-

Complaints filed with MahaRERA19

Case no.ComplainantRespondentFiled
CC006000000220697ASHISH CHANDRAKANT BARHATESHRIKANT SHITOLE OF TYCOONS AVANTI PROJECTS LLP15/04/2022
CC006000000439621AMRUTA PRAMOD PASHTETYCOONS AVANTI PROJECT LLP07/04/2024
CC12504272Jaywant KulkarniTycoons Avanti Projects LLP03/12/2025
CC12504273Hemalata MaratheTycoons Avanti Projects LLP03/12/2025
CC12504301Ankush BanubakodeTycoons Avanti Projects LLP05/12/2025
CC12504355Nitin BhangareTycoons Avanti Projects LLP08/12/2025
CC12504356Swapnil JawaleTycoons Avanti Projects LLP08/12/2025
CC12504459Kundan NannavareTycoons Avanti Projects LLP14/12/2025
CC12504464Rohit ShakyaTycoons Avanti Projects LLP14/12/2025
CC12504465Prashant WaniTycoons Avanti Projects LLP14/12/2025
CC12504466Prashant ThombeTycoons Avanti Projects LLP14/12/2025
CC12600456Sumeetee SinhaTycoons Avanti Projects LLP25/01/2026
CC12602898Mandar JoshiTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602899Sameer JoshiTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602900Vivek ChaudhariTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602901Prakash PansareTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602902Indrajit BorikarTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602904Mrityunjay SinghTycoons Avanti Projects Pvt. Ltd.17/05/2026
CC12602905Shridhar KadamTycoons Avanti Projects Pvt. Ltd.17/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 1File: ARCH CERT ZONE 1 D 18-10-2019.pdf23 Aug 2025
Form 2File: Tower D Engg Certificate sale _compressed 05-11-2019.pdf23 Aug 2025
Form 3File: Form 3 30-09-2019.pdf23 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld-Booked Inventory dtd 16-06-2021.pdf23 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration for QPR I D.pdf23 Aug 2025
Form 5 (FY 2019-2020)File: Form 5 (1).pdf4 Aug 2025
Form 5 (FY 2020-2021)File: Form 5 (2).pdf4 Aug 2025
Form 5 (FY 2021-2022)File: Form 5 (3).pdf4 Aug 2025
Form 5 (FY 2022-2023)File: Form 5 (4).pdf4 Aug 2025
Form 5 (FY 2023-2024)File: Form 5 (5).pdf4 Aug 2025
Form 5 (FY 2024-2025)File: Form 5 (6).pdf4 Aug 2025
Form 2A (FY 2019-2020)File: Form 2A.pdf1 Aug 2025
Form 2A (FY 2020-2021)File: Form 2A (1).pdf1 Aug 2025
Form 2A (FY 2021-2022)File: Form 2A (2).pdf1 Aug 2025
Form 2A (FY 2022-2023)File: Form 2A (3).pdf1 Aug 2025
Form 2A (FY 2023-2024)File: Form 2A (4).pdf1 Aug 2025
Form 2A (FY 2024-2025)1 Aug 2025
Form 2A (FY 2024-2025)File: Form 2A (5).pdf1 Aug 2025
Form 2A (FY 2025-2026)File: Form 2A (6).pdf1 Aug 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Avenue I Tower D 21-22.PDF23 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Aveune I Tower D 21-22 New.PDF4 Nov 2022
Layout approvalFile: 4 Mhada Layout 1988.pdf19 Apr 2022
Layout approvalFile: MHADA Layout 2014.pdf19 Apr 2022
Copy of Layout Approval (in case of layout)File: 4 Mhada Layout 1988.pdf19 Apr 2022
Copy of Layout Approval (in case of layout)File: MHADA Layout 2014.pdf19 Apr 2022
Building plan approvalFile: Layout dtd 24-9-21.pdf29 Dec 2021
Layout approvalFile: 21-02-2019.pdf29 Dec 2021
Layout approvalFile: Layout dtd 24-9-21.pdf29 Dec 2021
Copy of Layout Approval (in case of layout)File: 21-02-2019.pdf29 Dec 2021
Copy of Layout Approval (in case of layout)File: Layout dtd 24-9-21.pdf29 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Layout dtd 24-9-21.pdf29 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 ID 20-21.pdf3 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Avenue-I Tower D 2019-2020_compressed.pdf16 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Avenue-I Tower D 2020-2021_compressed.pdf16 Nov 2021
Declaration about Commencement CertificateFile: Declaration abt CC - ID.PDF15 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencemnet Certificate.pdf28 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: TAPL Form 5 Avenue I D 19-20.pdf25 Sep 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold-booked inventory-AvenueI Tower D_compressed.pdf16 Jun 2021
Declaration in FORM BFile: Form B.pdf7 Dec 2019
Building plan approvalFile: Layout 06-08-2019.pdf6 Dec 2019
Copy of the legal title reportFile: Title Report 1.pdf6 Dec 2019
Copy of the legal title reportFile: Title Report 2.pdf6 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Layout 06-08-2019.pdf6 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: Revised CC 06-08-2019.pdf6 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf6 Dec 2019
Proforma of Allotment letterFile: Declaration for FSA.pdf6 Dec 2019
OtherFile: ANWAR.pdf6 Dec 2019
Layout approvalFile: Layout 06-08-2019.pdf30 Nov 2019
PAN CardFile: TAPL Pan card.pdf30 Nov 2019
Details of encumbrancesFile: Encumbrance Certificate Avenue I D.pdf30 Nov 2019
Copy of Layout Approval (in case of layout)File: Layout 06-08-2019.pdf30 Nov 2019

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Tycoons Solitaire Phase-IKalyan-West103CompletedJul 2017Jul 2017
Spring avenuekalyan-west14CompletedSep 2011Sep 2011
Tycoons Residencykalyan -west48CompletedJul 2011Jul 2011

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tycoons Square Avenue I Tower D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikanghar7,600+ in Thane

Builder: Tycoons Avanti Projects LLP

Tycoons Avanti Projects LLP has 7 registrations on MahaRERA, including Tycoons Square Avenue I Tower B and Tycoons Square Avenue I Tower C. Its filings disclose 7 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Tycoons Square Avenue I Tower D shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Tycoons Square Avenue I Tower D is delayed beyond 30 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tycoons Square Avenue I Tower D?

The registered promoter entity is Tycoons Avanti Projects LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tycoons Square Avenue I Tower D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Tycoons Square Avenue I Tower D?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Tycoons Square Avenue I Tower D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tycoons Square Avenue I Tower D?

The professionals named in the filing: Architect: Design Consortium; Architect: Lokhandwalla F T; Engineer: Vastech Consultants & Engineers LLP; Chartered Accountant: Amrrita Jagnaani; Chartered Accountant: Tausif Shaikh; Chartered Accountant: Venkat Raghunath chari. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tycoons Square Avenue I Tower D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tycoons Square Avenue I Tower D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tycoons Square Avenue I Tower D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.