Red flags

  • Possession 2 months past the filed date
  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 70%
31 of 40Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

TUNGABHADRA CO OP HSG SOC is a Residential / Group Housing project by PRAVIN KESHAV BADHEKAR in Pune, Maharashtra, registered with MahaRERA as P52100046370 on 22 Jun 2022. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 16 months from the original filing. 9 of the 40 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameTUNGABHADRA CO OP HSG SOC
  • TypeResidential / Group Housing
  • Location
    • LOKMANYA COLONY
    • VANAZ
    • Kothrud
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046370
  • ReraGenie IDRG-MH-27504

Builder

  • NamePRAVIN KESHAV BADHEKAR
  • Entity typeIndividual
  • GSTIN27AEPPB8899F1ZU
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations14 more →
  • Completed2 of 15
  • No longer live4 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

2 months past promisethis monthRegisteredJun 2022First promiseApr 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 30 Apr 2025)
  • Buildings1 building record
  • Documents filed149 files

Current status

22%9 of 40 units booked
65.8%Work done, per cost certificate

Figures as on 14 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TUNGABHADRANA111140040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 70%.

TUNGABHADRA: 56% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered24
Open Space26

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,130 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on6 Nov 2025
LandownerVillageDistrict
TUNGABHADRAKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2441.78
Proposed, not sanctioned2,442 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAYUR COLONY ROAD
Estimated costRs 14.60 cr
Cost incurredRs 9.61 cr
Work done65.82%
BuildingWingEstimatedIncurred
TUNGABHADRANARs 13.00 crRs 9.16 cr
-NARs 1.61 crRs 45.48 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParas Netragaonkar
EngineerDipali Kulkarni
EngineerStructus Consultantss Pvt Ltd
Chartered AccountantShrikant Mantri
Chartered AccountantDinesh Gandhi
Chartered AccountantSHRIKANT MANTRI AND CO.
PartnerRole in project
BADHEKAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028124Apr 2025 → Aug 2026

Reason as filed by the promoterAs per revised rules of Corporation, FSI got increased due to which we have to add 2 additional floors. For all the revised sanctioning process and execution of the project, we need extension. Please grant us the Extension as per above mentioned date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 1 5 DATED 15 10 2025.pdf14 Apr 2026
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 2 5 DATED 15 10 2025.pdf14 Apr 2026
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 3 5 DATED 15 10 2025.pdf14 Apr 2026
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 4 5 DATED 15 10 2025.pdf14 Apr 2026
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 5 5 DATED 15 10 2025.pdf14 Apr 2026
Commencement certificateFile: TUNGBHADRA REVISE SANCTION CC DATED 15 10 2025.pdf14 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Tungabhadra Jun 25.pdf14 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect certificate Tungbhadra Sep-25..pdf14 Apr 2026
Withdrawal Update Form 2File: Form 2 Tungabhadra Jun 25.pdf14 Apr 2026
Withdrawal Update Form 2File: Form 2 Tungabhadra Sep 25.pdf14 Apr 2026
Withdrawal Update Form 3File: Tungbhadra RERA Form 3 CA Certificate Jun-25 Scan_compressed.pdf14 Apr 2026
Withdrawal Update Form 3File: Tungbhadra RERA Form 3 up to Sep-25 scan_compressed.pdf14 Apr 2026
Form 5 (FY 2024-2025)File: Tungbhadra FY 24-25 RERA 5 Scan.pdf26 Mar 2026
Form 2A (FY 2025-2026)File: Form 2A Tungabhadra 25-26.pdf22 Jan 2026
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 1 5 DATED 15 10 2025.pdf25 Nov 2025
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 2 5 DATED 15 10 2025.pdf25 Nov 2025
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 3 5 DATED 15 10 2025.pdf25 Nov 2025
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 4 5 DATED 15 10 2025.pdf25 Nov 2025
Building plan approvalFile: TUNGBHADRA REVISE SANCTION PLAN 5 5 DATED 15 10 2025.pdf25 Nov 2025
Form 1File: Architect Certificate Tungabhadra Mar 25.pdf24 Nov 2025
Form 2File: Architect Certificate Tungabhadra Mar 25.pdf24 Nov 2025
Form 3File: Architect Certificate Tungabhadra Mar 25.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Architect Certificate Tungabhadra Mar 25.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Sep 2024.pdf24 Nov 2025
Form 2File: Architect’s Certificate - Tungabhadra Sep 2024.pdf24 Nov 2025
Form 3File: Architect’s Certificate - Tungabhadra Sep 2024.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sep 24.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Jun 2024.pdf24 Nov 2025
Form 2File: Architect’s Certificate - Tungabhadra Jun 2024.pdf24 Nov 2025
Form 3File: Architect’s Certificate - Tungabhadra Jun 2024.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Jun 24.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Mar 2024.pdf24 Nov 2025
Form 2File: Engineer’s Certificate - Tungabhadra Mar 2024.pdf24 Nov 2025
Form 3File: CA Certificate - Tungabhadra Mar 2024.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Architect’s Certificate - Tungabhadra Mar 2024.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Dec 2023.pdf24 Nov 2025
Form 2File: Architect’s Certificate - Tungabhadra Dec 2023.pdf24 Nov 2025
Form 3File: Architect’s Certificate - Tungabhadra Dec 2023.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory Dec 23.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Sep 2023.pdf24 Nov 2025
Form 2File: Architect’s Certificate - Tungabhadra Sep 2023.pdf24 Nov 2025
Form 3File: Architect’s Certificate - Tungabhadra Sep 2023.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Sep 23.pdf24 Nov 2025
Form 1File: Engineer’s Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 2File: Engineer’s Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 3File: CA Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: CA Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 1File: CA Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 2File: Engineer’s Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 3File: CA Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: CA Certificate - Tungabhadra Mar 2023.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Dec22.pdf24 Nov 2025
Form 2File: Architect’s Certificate - Tungabhadra Dec22.pdf24 Nov 2025
Form 3File: Architect’s Certificate - Tungabhadra Dec22.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Architect’s Certificate - Tungabhadra Dec22.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Jun 2022.pdf24 Nov 2025
Form 2File: Engineer’s Certificate - Tungabhadra May 2022.pdf24 Nov 2025
Form 3File: CA Certificate - Tungabhadra May 2022.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory Jun 22.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Jun 2022.pdf24 Nov 2025
Form 2File: Engineer’s Certificate - Tungabhadra May 2022.pdf24 Nov 2025
Form 3File: CA Certificate - Tungabhadra May 2022.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory Jun 22.pdf24 Nov 2025
Form 1File: Architect’s Certificate - Tungabhadra Dec 2024.pdf5 Aug 2025
Form 2File: Engineer’s Certificate - Tungabhadra Dec 2024.pdf5 Aug 2025
Form 3File: CA Certificate - Tungabhadra Dec 2024.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory Dec 24.pdf5 Aug 2025
Form 5 (FY 2022-2023)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf15 Jul 2025
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf15 Jul 2025
Form 2A (FY 2022-2023)File: Form 2 A QAC Tungbhadra site 22-23..pdf10 Jul 2025
Form 2A (FY 2023-2024)File: Form 2 A QAC Tungbhadra site 23-24..pdf10 Jul 2025
Form 2A (FY 2024-2025)File: Form 2 A QAC Tungbhadra site 24-25..pdf10 Jul 2025
Declaration in FORM BFile: Tungabhadra Form B 310826.pdf5 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory Tungabhadra Dec -24.pdf5 Apr 2025
CERSAI detailsFile: CERSAI Report Tungabhadra 050425.pdf5 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 QAC Tungabhadra 23-24.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tungbhadra RERA Form 3 CA Certificate Dec-24 Scan.pdf2 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate Tungbhadra site Dec-24.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tungbhadra RERA Form 3 CA Certificate Mar-24 Scan.pdf28 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate Tungbhadra site.pdf28 Mar 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SAMRUDDHI RESIDENCYP52100006236Warje, Pune15Aug 2017CompletedFeb 2023Registered original: Jul 2019Late, Feb 2024
VINAYAK15P52100007478Rambaug Colony, Pune14Aug 2017CompletedNov 2021Dec 2019

How this compares with Pune

22%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 16 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TUNGABHADRA CO OP HSG SOC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VANAZ13,700+ in Pune

2 kmTUNGABHADRA CO OP HSG SOCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: PRAVIN KESHAV BADHEKAR

PRAVIN KESHAV BADHEKAR has 15 registrations on MahaRERA, including SAMRUDDHI RESIDENCY and VINAYAK15. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TUNGABHADRA CO OP HSG SOC is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TUNGABHADRA CO OP HSG SOC?

The registered promoter entity is PRAVIN KESHAV BADHEKAR, an individual as per the filing. Its GSTIN 27AEPPB8899F1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TUNGABHADRA CO OP HSG SOC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TUNGABHADRA CO OP HSG SOC?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TUNGABHADRA CO OP HSG SOC?

The professionals named in the filing: Architect: Paras Netragaonkar; Engineer: Dipali Kulkarni; Engineer: Structus Consultantss Pvt Ltd; Chartered Accountant: Shrikant Mantri; Chartered Accountant: Dinesh Gandhi; Chartered Accountant: SHRIKANT MANTRI AND CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TUNGABHADRA CO OP HSG SOC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TUNGABHADRA CO OP HSG SOC. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TUNGABHADRA CO OP HSG SOC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.