Home / Browse projects / Raigarh, Maharashtra / TULSI V CITY - TULSI VIVAAN
TULSI V CITY - TULSI VIVAAN
By RAJ REALTORS (A project by Raj Group)
RG-MH-77367 · RERA P52000015825 · Last updated on MahaRERA portal: 15 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 19 months past the filed date
- Completion date moved by 42 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TULSI V CITY - TULSI VIVAAN is a Others project by RAJ REALTORS (A project by Raj Group) in Raigarh, Maharashtra, registered with MahaRERA as P52000015825 on 27 Mar 2018. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 42 months from the original filing.
At a glance
Project
- NameTULSI V CITY - TULSI VIVAAN
- TypeOthers
- Location
- NA
- WANGANI-PASHANE
- Pashane
- Karjat
- Raigarh
- 421503
- Pincode421503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000015825
- ReraGenie IDRG-MH-77367
Builder
- NameRAJ REALTORS (A project by Raj Group)
- Entity typePartnership
- PartnersPRAVIN RAVJIBHAI PATEL, MADANLAL RATANLAL CHAPLOT, YASH PRAVIN PATEL, BHAVAN RAVJIBHAI PATEL, TRUPESH BHAVAN PATEL, BHARAT GANGARAM PATEL, KANUBHAI GANGARAM PATEL, GARIMA PANKAJ CHAPLOT, PISTA RAJENDRA CHAPLOT, SWEETY SUMIT CHAPLOT, NEHAL PRATEEK CHAPLOT
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Mar 2018
- Promised completion31 Mar 2025
- Revised completionRevised to 31 Mar 2025 (originally 30 Sep 2021)
- Buildings3 building records
- Documents filed138 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 5 - A, B, C, D | NA | 9 | 0 | 0 | 0 | 0 |
| Building No 6 - A, B, C, D | NA | 9 | 0 | 0 | 0 | 0 |
| Building 7 - A and B | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 15 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
Building No 5 - A, B, C, D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 6 - A, B, C, D91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building 7 - A and B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities16
As on 15 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 20% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 40% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Club House Facility | Yes | 75% |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building No 5 - A, B, C, D | 1 | 1 |
| Building No 6 - A, B, C, D | 1 | 1 |
| Building 7 - A and B | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGNO ARCHITECT (Partner CHINTAMANI PURANDARE) |
| Engineer | Kamleshkumar Ratilal Patel Prop of KR PATEL & ASSOCIATES |
| Partner | Role in project |
|---|---|
| RAJ REALTORS (A project by Raj Group) | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe date of completion as per RERA record is 30/09/2021 (i.e. after the Suomoto Extension given by RERA Authorities).However the construction work is delayed due to less booking / sale of units and cancellations of bookings higher than the normal on account of non-approval home loan by the Banks & Financial Institutions as the home buyers are from very lower income group. Since our project is being carried out at Vangani an under developed area, due above reasons we have been facing shortage of funds from the beginning.Hence we could not complete the project development and construction work a
Reason as filed by the promoterThat we have already obtained consent/NOC from more than 51% allotees at the time of applying last extention and our project is also completed in all respect, Now it is not possible for us to again obtain NOC from 51% or more allotees as required by MahaRERA authorities to apply for extension in obtaining Occupancy certificate. 8. That we request Maharera Authorities to grant us Necessary extension up to 31/03/2025 for obtaining Occupancy Certificate under section 7(3) of the Real Estate (Regulation and Development) Act,2017 with reference to MahaRERA order No.40/2022 dated 27/12/2022 (without
Reason as filed by the promoterWe have completed the construction and development work of all the buildings viz., (Building No.5,6 & 7 consisting 10 Wings) of our project Tulsi Vivaan in all respect. We have obtained Architect Certificate for progress of the work in respect of all 10 wings of building No.5,6 &7. We are collecting various documents and NOC’s required for submission of application for occupancy certificate to Town Planning Department, Alibaug which will take some time and the said competent authority will take some time for verifying the documents, Constructed project and issue occupancy certificate. Hence we
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Feb 2025
Documents filed138
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TULSI V CITY _ Form 4.pdf | 15 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: TULSI V CITY _ Form 4.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q1_compressed.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q2_compressed.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form -1 Q3_compressed.pdf | 1 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Raj Realtors Form-05.pdf | 16 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_June 2018_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 2018_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 2018_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 2019_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 2021_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Sep 2022_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 2019_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 2020_compressed.pdf | 7 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Dec 2021_compressed.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 18.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 19.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 20.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 21.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Dec 22.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 18.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 19.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_June 21.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sep 18.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sep 19.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sep 21.pdf | 7 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Sep 22.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_Dec 22.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_June 19.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_June 20.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_June 21.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3_Sep 20.pdf | 7 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3-Dec 20_compressed.pdf | 7 Apr 2024 |
| Declaration in FORM BFile: From B Raj Realtors .pdf | 21 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A DATED-18-03-24.pdf | 21 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold-Booked Inventory_11zon.pdf | 21 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 MARCH-2023.pdf | 21 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2.pdf | 2 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Q3.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 JUN-23.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 SEP-23.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 DEC-23.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3-Q1_compressed.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3-Q2_compressed.pdf | 2 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3-Q3_compressed.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec-18.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar-19.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar-20.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar-21.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar-22.pdf | 23 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar-23.pdf | 23 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2023 done.pdf | 23 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-22.pdf | 23 May 2023 |
| Declaration about Commencement CertificateFile: From-D.pdf | 20 May 2023 |
| Declaration in FORM BFile: FORM-B.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 23102020.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2021_compressed.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2021_compressed.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2022.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-3062022.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 2023.pdf | 20 May 2023 |
| Other - LegalFile: Covering letter.pdf | 20 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2019.pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2022.pdf | 19 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30062022.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122018.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032019.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032021.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122021.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032022.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30062022.pdf | 19 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032023.pdf | 19 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2020.pdf | 19 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2022.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: Form 3 2019.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: Form 3 2021_compressed.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: Form 3 2022_compressed.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: Form 3 062022_compressed.pdf | 19 May 2023 |
| Certificates of CA (Form 3)File: Form 3 2023_compressed.pdf | 19 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 138 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep TULSI V CITY - TULSI VIVAAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near WANGANI-PASHANE5,900+ in Raigarh
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Mohan Alcoves I
MOHAN LIFESPACES LLP
MANOHAR VIKAS SHREEJI PARAISO PHASE - 2
DEEPLAXMI DEVELOPERS
SHREEJI MILESTONE
DEEP LAXMI ASSOCIATES
Mohan Willows III
MOHAN LIFESPACES LLP
SHREEJI SQUARE PHASE I
SHREEJI DEVELOPERS
See every Raigarh project, with the district possession charts
Builder: RAJ REALTORS (A project by Raj Group)
RAJ REALTORS (A project by Raj Group) has 1 registration on MahaRERA, including TULSI V CITY - TULSI VIVAAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that TULSI V CITY - TULSI VIVAAN shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TULSI V CITY - TULSI VIVAAN is delayed beyond 31 Mar 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TULSI V CITY - TULSI VIVAAN?
The registered promoter entity is RAJ REALTORS (A project by Raj Group), a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TULSI V CITY - TULSI VIVAAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TULSI V CITY - TULSI VIVAAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TULSI V CITY - TULSI VIVAAN?
The professionals named in the filing: Architect: DESIGNO ARCHITECT (Partner CHINTAMANI PURANDARE); Engineer: Kamleshkumar Ratilal Patel Prop of KR PATEL & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TULSI V CITY - TULSI VIVAAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback