Home / Browse projects / Thane, Maharashtra / Tulsi Aaradhana

Registration lapsed No litigation declared Residential / Group Housing project

Tulsi Aaradhana

By RAJ GROUP

RG-MH-75357 · RERA P51700047616 · Last updated on MahaRERA portal: 3 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
0 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

Tulsi Aaradhana is a Residential / Group Housing project by RAJ GROUP in Thane, Maharashtra, registered with MahaRERA as P51700047616 on 14 Nov 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameTulsi Aaradhana
  • TypeResidential / Group Housing
  • Location
    • Kharvai
    • Badlapur
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700047616
  • ReraGenie IDRG-MH-75357

Builder

  • NameRAJ GROUP
  • Entity typePartnership
  • PartnersPRAVIN RAVJIBHAI PATEL, SANJAY ATMARAM PATEL, PANKAJ MANIBHAI PATEL, DINESH RAVJIBHAI PATEL, KIRITBHAI RAVJI PATEL, BHAVAN RAVJI PATEL, SANKET SHANTILAL PATEL, BHARAT GANGARAM PATEL, RAMAN JIVRAJ PATEL, PANKAJ SURESHBHAI PATEL, VALLABH KARSAN PATEL, KHIMJI NARSHI BERA
  • Other registrations6 more →
  • Completed5 of 7
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

10 months past promisethis monthRegisteredNov 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on14 Nov 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed90 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA1412000
Wing BNA1513000
Wing CNA1513000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 3 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Wing A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
Wing A11
Wing B11
Wing C11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,980 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKulgaon Badlapur Muncipal Corporation
Permissible FSI18390.15
Proposed, not sanctioned18,390 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKharvai,Badlapur

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaj Associates (Ar. S R Khambayat)
ArchitectS R Khambayat Partner of RAJ ASSOCIATES
EngineerER. Kamlesh R Patel
EngineerSmit Velani Partner of Aadhar Engineering
EngineerK R Patel & Associates
Chartered AccountantCA Rajendra Chaplot
Chartered AccountantCA Ganapath Jain
PartnerRole in project
RAJ GROUP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1.pdf3 Feb 2026
Form 2File: FORM 2.pdf3 Feb 2026
Form 3File: Form3_compressed.pdf3 Feb 2026
Disclosure of Sold and Booked InventoryFile: Raj Group Tulsi Aaradhana Q3 Sold_Unsold Unit.pdf3 Feb 2026
Form 1File: FORM-1 Q1 Aaradhana.pdf15 Jan 2026
Form 2File: FORM-2 Q1 Aaradhana.pdf15 Jan 2026
Form 3File: Form 3_Tulsi Aradhana_Q1_compressed.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: Tulsi Aradhana Q1 Disclosure of Sold_Unsold Unit.pdf15 Jan 2026
Form 1File: FORM-1 Q2-2025 Aaradhana.pdf15 Jan 2026
Form 2File: FORM-2 Q2- 2025 Aaradhana.pdf15 Jan 2026
Form 3File: Form 3_Tulsi Aradhana_Q2_compressed.pdf15 Jan 2026
Disclosure of Sold and Booked InventoryFile: Tulsi Aaradhana Q2 Disclosure of Sold_Unsold Unit.pdf15 Jan 2026
Disclosure of sold/ booked inventoryFile: Disclosure of sold-unsold inventory 31_03_2025 (Aaradhana)_11zon.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 31_03_2025 Aaradhana_11zon.pdf5 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31_03_2025 Tulsi Aaradhana.pdf2 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31_03_2025 Aaradhana.pdf2 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q3 Aaradhana.pdf7 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 Aaradhana Q3.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM- 3 Aaradhana Q3.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold inventory Q3 Aaradhna.pdf31 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A Aaradhana.pdf26 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory Aaradhana_11zon.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Tulsi Aaradhana.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf23 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf22 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 30062024 Aaradhana.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 30062024 Aaradhana.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 30062024_ Compressed.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-unsold inventory 30062024 (Aaradhana) Compressed.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 30062024 Aaradhana.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 30062024_ Compressed.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 30062024 Aaradhana.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold-unsold inventory 30062024 (Aaradhana) Compressed.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Aadradhna.pdf23 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Aaradhana.pdf23 May 2024
Disclosure of sold/ booked inventoryFile: Signed Disclosure of Sold_Unsold Inventory Tulsi Aaradhana PH 9_compressed.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Q4 Tulsi Aaradhna_compressed.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Tulsi Aananda-Q3_compressed.pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Tulsi Aaradhana-Q3_compressed.pdf29 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q3- Aaradhana.pdf25 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5- 31 MARCH 2023 Aaradhana.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 DEC-2023 Aaradhana.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-Tulsi Aaradhana PH 9_Apr23 To Jun23-Compressed.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form-Tulsi Aaradhana PH 9_Jul23 To Sep23_Compressed.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Tulsi Aaradhana June 23.pdf1 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tulsi Aaradhana - Form 2-Sep23.pdf1 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-Mar 23_Tulsi Aaradhna.pdf1 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1- 30092023 Aaradhana_compressed.pdf1 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 JUN -2023 (Aaradhana)_compressed.pdf16 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 PHASE-9 TULSI AARADHANA.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 DATED 31-03-2023.pdf3 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-1 DATED 31-03-2023.pdf3 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 31-03-2023_compressed.pdf3 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A 31-03-2023.pdf3 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 PHASE-9 TULSI AARADHANA.pdf27 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Tulsi Aaradhana.pdf27 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 PHASE-9 TULSI AARADHANA.pdf24 Feb 2023
Other - LegalFile: Revised AFS Tulsi Aaradhana.pdf4 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Revised CC.pdf19 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report of RajGroup.pdf19 Sep 2022
Building plan approvalFile: P-09 Layout Plan 1 of 3.pdf24 Aug 2022
Building plan approvalFile: P-09 Layout Plan 2 of 3.pdf24 Aug 2022
Building plan approvalFile: P-09 Layout Plan 3 of 3.pdf24 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: P-09 Layout Plan 1 of 3.pdf24 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: P-09 Layout Plan 2 of 3.pdf24 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: P-09 Layout Plan 3 of 3.pdf24 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Plinth Completion Certificate_compressed.pdf24 Aug 2022
Proforma of Allotment letterFile: Allotment Letter - Tulsi Aaradhana.pdf24 Aug 2022
Proforma of Agreement for saleFile: Revised AFS Tulsi Aaradhana.pdf24 Aug 2022
PAN CardFile: Pan Card.pdf2 Aug 2022
Details of encumbrances concerned to LegalFile: Certificate Tulsi Aaradhana.pdf2 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Bank.pdf2 Aug 2022
Deviation Report with respect to Allotment letterFile: Declaration Allotment deviation.pdf2 Aug 2022
Building plan approvalFile: P-09 Layout Plan 1 of 3_compressed_compressed.pdf5 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: P-09 Layout Plan 1 of 3_compressed_compressed.pdf5 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Phase-09 CC.pdf5 Jul 2022
Layout approvalFile: P-09 Layout Plan 1 of 3_compressed_compressed.pdf18 Jun 2022

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Tulsi AadvikKharvai Badlapur east 421503377CompletedSep 2021Sep 2021
Tulsi AahanGuru Ashray Katrap Badlapur 421503449CompletedDec 2019Jun 2019
Tulsi Aarambh - P to USurvey No 48 Hissa No. A B2 B1 AND Survey No 45 Hissa No 1A 2 3 1B 5 KHARWAI BADLAPUR.144CompletedMar 2017Late, Apr 2017
Tulsi Aarambh - L to OSurvey No 48 Hissa No. A B2 B1 AND Survey No 45 Hissa No 1A 2 3 1B 5 KHARWAI BADLAPUR.112CompletedMar 2017Oct 2016
Tulsi Aarambh - A to KSurvey No 48 Hissa No. A B2 B1 AND Survey No 45 Hissa No 1A 2 3 1B 5 KHARWAI BADLAPUR.271CompletedDec 2015Late, Feb 2016

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tulsi Aaradhana on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Badlapur7,600+ in Thane

2 kmTulsi AaradhanaCompleted 77Lapsed / revoked 30Other 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 175 registered projects within 2 km.

Builder: RAJ GROUP

RAJ GROUP has 7 registrations on MahaRERA, including TULSI AAHAN and Tulsi Aadvik. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 5 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Tulsi Aaradhana shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Tulsi Aaradhana is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tulsi Aaradhana?

The registered promoter entity is RAJ GROUP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tulsi Aaradhana?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Tulsi Aaradhana?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tulsi Aaradhana?

The professionals named in the filing: Architect: Raj Associates (Ar. S R Khambayat); Architect: S R Khambayat Partner of RAJ ASSOCIATES; Engineer: ER. Kamlesh R Patel; Engineer: Smit Velani Partner of Aadhar Engineering; Engineer: K R Patel & Associates; Chartered Accountant: CA Rajendra Chaplot. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tulsi Aaradhana?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tulsi Aaradhana. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tulsi Aaradhana to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.