Home / Browse projects / Pune, Maharashtra / TRIO ALPHA

Registered No litigation declared Residential / Group Housing project

TRIO ALPHA

By TRIO SPACES

RG-MH-57280 · RERA P52100051396 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 2 extensions taken
  • Rs 15.00 crore secured on the land, in favour of ADITYA BIRLA HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
21 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 98%
16 of 116Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 153 documents Report an error

TRIO ALPHA is a Residential / Group Housing project by TRIO SPACES in Pune, Maharashtra, registered with MahaRERA as P52100051396 on 8 Jun 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 100 of the 116 units on this registration are recorded sold or booked, and 21 of 33 construction stages are filed complete.

At a glance

Project

  • NameTRIO ALPHA
  • TypeResidential / Group Housing
  • Location
    • AUNDH RAVET BRTS ROAD
    • TATHWADE
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051396
  • ReraGenie IDRG-MH-57280

Builder

  • NameTRIO SPACES
  • Entity typePartnership
  • PartnersBIPIN ASHOK DAKHNEJA, HARSHITA SUNIL SUKHWANI

Key dates

this monthRegisteredJun 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jun 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings3 building records
  • Documents filed153 files

Current status

86%100 of 116 units booked
88.1%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A wingNA141248048
B wingNA141248048
C WingNA131020020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.

A wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.97%
B wing91%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
C Wing40%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises47%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks16%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes64%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes59%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed217

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots217
Closed/Covered217
BuildingClosed/CoveredTotal
A wing7373
B wing7373
C Wing7171

Land and ownership16

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,188 sq m
Land owned byNot the promoter
Named landowners16
Encumbrance on the landDeclared present
Charge in favour ofADITYA BIRLA HOUSING FINANCE LIMITED
Secured amountRs 15.00 crore
CERSAI search filedYes
Declared on18 Sep 2025
LandownerVillageDistrict
Durva AssociatesTathwadePune
Tanaji Rambhau PawarTathwadePune
Surekha Tanaji PawarTathwadePune
Sagar Tanaji PawarTathwadePune
Swapna Mahindra PadaleTathwadePune
Reshma Rahul RaksheTathwadePune
Mansi Kiran JadhavTathwadePune
Sambhaji Rambhau PawarTathwadePune
Manisha Sambhaji PawarTathwadePune
Vaibhav Sambhaji PawarTathwadePune
Saurabh Sambhaji PawarTathwadePune
Vimal Hanumant PawarTathwadePune
Shrikant Hanumant PawarTathwadePune
Deepali Ravindra SakhreTathwadePune
Jyotsna Sachin MalageTathwadePune
Shilpa Suraj KadTathwadePune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI14077.02
Proposed, not sanctioned10,282 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGRD AND MEZZANINE FLR P W D 24 9 10 NR ASHOK THEATRE SHASTRI GARDEN PIMPRI PUNE MAHARASHTRA 411017
Estimated costRs 56.00 cr
Cost incurredRs 49.35 cr
Work done88.13%
BuildingWingEstimatedIncurred
A wingNARs 20.62 crRs 20.01 cr
B wingNARs 20.62 crRs 20.01 cr
C WingNARs 9.75 crRs 6.34 cr
-NARs 5.00 crRs 3.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSangram Salunkhe Salunkhe
EngineerArvind Jadhav Hanumant Jadhav
EngineerKAMESH R PAMNANI
Chartered AccountantMasulkar and Associates
Chartered AccountantCA Trilok Ahuja and Company
Chartered AccountantCA ANKIT TALREJA
PartnerRole in project
TRIO SPACES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA01082502284Dec 2025 → Jun 2026

Reason as filed by the promoterI, Shri Chahat Ratan Pamnani, Partner of Trio Spaces, having our office at Survey No. 6/2B, 6/11, 6/12, 6/13, 6/14, 6/15, 6/16, Village: Tathwade, Taluka: Mulshi, District: Pune - 411033, respectfully submit this application as follows. Trio Spaces is the Promoter of the real estate project titled “Trio Alpha”, bearing MahaRERA Registration No. P52100051396, which is currently valid up to 31st December 2025. Due to certain unforeseen and unavoidable circumstances beyond our control, such as delays in obtaining statutory approvals, disruptions in material procurement, and shortages of both skil

EA30072621939Dec 2025 → Dec 2026

Reason as filed by the promoterRespected Sir/Madam, We, TRIO SPACES, the Promoter of the real estate project "TRIO ALPHA", bearing MahaRERA Registration No. P52100051396, most respectfully submit this application seeking an extension of the project registration up to 31ST DECEMBER 2026. The project could not be completed within the stipulated period due to certain genuine and unavoidable circumstances beyond the control of the Promoter. The progress of the project was affected due to delay in obtaining statutory approvals, permissions and revalidations from the concerned authorities, which impacted the construction schedule

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed153

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 JUNE 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM-2 TRIO ALPHA JUN-2026.pdf30 Jul 2026
Withdrawal Update Form 3File: FORM 3 TRIO ALPHA JUNE 2026.pdf30 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A TRIO ALPHA MARCH 2026.pdf30 Jul 2026
Withdrawal Update Form 1File: FORM 1 JUNE 2026.pdf25 Jul 2026
Withdrawal Update Form 2File: FORM-2 TRIO ALPHA JUN-2026.pdf25 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 apr-jun 2026 final scan.pdf25 Jul 2026
Withdrawal Update Form 1File: FORM 1 MARCH 2026.pdf24 Jul 2026
Withdrawal Update Form 2File: FORM 2 MARCH 2026.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 RERA Jan-Mar 2026 Final Scan.pdf24 Jul 2026
Withdrawal Update Form 1File: FORM-1.pdf9 Feb 2026
Withdrawal Update Form 2File: FORM-2.pdf9 Feb 2026
Withdrawal Update Form 3File: FORM-3 SEPTEMBER -2025 CORRECTION COMPRESSED.pdf9 Feb 2026
Withdrawal Update Form 1File: FORM-1.pdf5 Feb 2026
Withdrawal Update Form 2File: FORM-2.pdf5 Feb 2026
Withdrawal Update Form 3File: FORM-3 DEC-2025 AMENDED SCANNED COMPRESSED.pdf5 Feb 2026
Withdrawal Update Form 1File: FORM-1.pdf31 Jan 2026
Withdrawal Update Form 2File: FORM-2.pdf31 Jan 2026
Withdrawal Update Form 3File: FORM-3.pdf31 Jan 2026
Withdrawal Update Form 1File: FORM-1.pdf30 Jan 2026
Withdrawal Update Form 2File: FORM-2.pdf30 Jan 2026
Withdrawal Update Form 3File: FORM-3_COMPRESS.pdf30 Jan 2026
Withdrawal Update Form 1File: Q2 Form 1.pdf3 Jan 2026
Withdrawal Update Form 2File: Q2 Form 2 .pdf3 Jan 2026
Withdrawal Update Form 3File: Q2 Form 3 July-sept 2025 Final scan.pdf3 Jan 2026
Withdrawal Update Form 1File: FORM-1_JUNE-2025.pdf26 Nov 2025
Withdrawal Update Form 2File: FORM-2_JUNE-2025.pdf26 Nov 2025
Withdrawal Update Form 3File: FORM-3_JUNE-2025.pdf26 Nov 2025
Withdrawal Update Form 1File: Q2 Form 1.pdf6 Nov 2025
Withdrawal Update Form 2File: Q2 Form 2 NEW.pdf6 Nov 2025
Withdrawal Update Form 3File: Q2 Form 3 July-sept 2025 Final scan.pdf6 Nov 2025
Withdrawal Update Form 1File: Q2 Form 1.pdf3 Nov 2025
Withdrawal Update Form 1File: Q2 Form 1.pdf3 Nov 2025
Withdrawal Update Form 2File: Q2 Form 2 NEW.pdf3 Nov 2025
Withdrawal Update Form 2File: Q2 Form 2 NEW.pdf3 Nov 2025
Withdrawal Update Form 3File: Q2 Form 3 July-sept 2025 Final scan.pdf3 Nov 2025
Withdrawal Update Form 3File: Q2 Form 3 July-sept 2025 Final scan.pdf3 Nov 2025
Withdrawal Update Form 1File: Q2 Form 1.pdf30 Oct 2025
Withdrawal Update Form 2File: Q2 Form 2 NEW.pdf30 Oct 2025
Withdrawal Update Form 3File: Q2 Form 3 July-sept 2025 Final scan.pdf30 Oct 2025
Form 2A (FY 2023-2024)File: Engineer certificate for Quality Assurance 2023 - 2024.pdf8 Jul 2025
Form 2A (FY 2024-2025)File: Engineer certificate for Quality Assurance 2024 - 2025.pdf8 Jul 2025
Form 1File: April to June 2023.pdf3 Jul 2025
Form 2File: Q1.pdf3 Jul 2025
Form 3File: Form 3 Final Apr - Jun 2023-24.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: April to June 2023.pdf3 Jul 2025
Form 1File: July to September 2023.pdf3 Jul 2025
Form 2File: Q2.pdf3 Jul 2025
Form 3File: Form 3 Final July - Sept 2023-24.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: July to September 2023.pdf3 Jul 2025
Form 1File: October to December 2023.pdf3 Jul 2025
Form 2File: Q3.pdf3 Jul 2025
Form 3File: Form 3 Final Oct - dec.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: October to December 2023.pdf3 Jul 2025
Form 1File: First Quarter (April to June 2024).pdf3 Jul 2025
Form 2File: April to June 2024.pdf3 Jul 2025
Form 3File: Form 3 Apr-Jun 2024.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: April to June 2024.pdf3 Jul 2025
Form 1File: Second Quarter (July to September 2024).pdf3 Jul 2025
Form 2File: July to September 2024.pdf3 Jul 2025
Form 3File: Form 3 July-Sept 2024.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: July to September 2024.pdf3 Jul 2025
Form 1File: Third Quarter (October to December 2024).pdf3 Jul 2025
Form 2File: October to December 2024.pdf3 Jul 2025
Form 3File: Form 3 Oct-Dec 2024.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: October to December 2024.pdf3 Jul 2025
Form 1File: Fourth Quarter (January to March 2025).pdf3 Jul 2025
Form 2File: January to March 2025.pdf3 Jul 2025
Form 3File: Form 3 Jan-mar 2025 .pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: January to March 2025.pdf3 Jul 2025
Form 1File: January to March 2024.pdf3 Jul 2025
Form 2File: Q4.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: January to March 2024.pdf3 Jul 2025
Form 3File: Form 3 Final jan - Mar 23-24.pdf3 Jul 2025
Form 5 (FY 2024-2025)File: FORM-5 MAR-25.pdf3 Jul 2025
Form 5 (FY 2023-2024)File: From 5 - Trio Spaces.pdf3 Jul 2025
Building plan approvalFile: C-Building Plan.pdf24 Jan 2025
Building plan approvalFile: C-Building Plan.pdf24 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: C-Building Plan.pdf24 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: C-Building Plan.pdf24 Jan 2025

How this compares with Pune

86%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIO ALPHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TATHWADE13,700+ in Pune

2 kmTRIO ALPHACompleted 67Lapsed / revoked 28Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 173 registered projects within 2 km.

Builder: TRIO SPACES

TRIO SPACES has 1 registration on MahaRERA, including TRIO ALPHA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TRIO ALPHA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIO ALPHA?

The registered promoter entity is TRIO SPACES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIO ALPHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRIO ALPHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIO ALPHA?

The professionals named in the filing: Architect: Sangram Salunkhe Salunkhe; Engineer: Arvind Jadhav Hanumant Jadhav; Engineer: KAMESH R PAMNANI; Chartered Accountant: Masulkar and Associates; Chartered Accountant: CA Trilok Ahuja and Company; Chartered Accountant: CA ANKIT TALREJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIO ALPHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIO ALPHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIO ALPHA to a free account