Home / Browse projects / Thane, Maharashtra / TRINITY MOKSH

Registered No litigation declared Others project

TRINITY MOKSH

By RATTANRAJ LIFESPACES

RG-MH-30685 · RERA P51700031260 · Last updated on MahaRERA portal: 3 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 24 months from the original
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 96%
102 of 149Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

TRINITY MOKSH is a Others project by RATTANRAJ LIFESPACES in Thane, Maharashtra, registered with MahaRERA as P51700031260 on 15 Oct 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 24 months from the original filing. 47 of the 149 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameTRINITY MOKSH
  • TypeOthers
  • Location
    • NXT TO SHIV MANDIR ROAD
    • PALEGAON
    • Ambarnath(M Cl)
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700031260
  • ReraGenie IDRG-MH-30685

Builder

  • NameRATTANRAJ LIFESPACES
  • Entity typePartnership
  • PartnersDHIRAJ RATANLAL JAGIASI, SURESH RATANLAL JAGIASI, GURBUX RATANLAL JAGIASI
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredOct 2021First promiseMar 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Oct 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2025)
  • Buildings2 building records
  • Documents filed105 files

Current status

32%47 of 149 units booked
76.2%Work done, per cost certificate

Figures as on 3 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRINITY MOKSH-WING ANA1814532275
TRINITY MOKSH-WING BNA1814522274

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 96%.

TRINITY MOKSH-WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.96%
TRINITY MOKSH-WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.96%

Progress on shared amenities15

As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered2
Open Space37
BuildingClosed/CoveredOpen SpaceTotal
TRINITY MOKSH-WING A13738
TRINITY MOKSH-WING B101

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,210 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Aug 2025

Approvals and building plan

Sanctioning authorityAmbernath Municipal Corporation
Permissible FSI14894.0
Proposed, not sanctioned14,894 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSTATION ROAD
Estimated costRs 53.13 cr
Cost incurredRs 40.51 cr
Work done76.24%
BuildingWingEstimatedIncurred
TRINITY MOKSH-WING ANARs 24.25 crRs 20.25 cr
TRINITY MOKSH-WING BNARs 24.25 crRs 20.25 cr
-NARs 4.62 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPIYUSH N BANSAL
EngineerATUL KUDTARKAR
EngineerMahesh Bhoir
Chartered AccountantVIJAY KAVRANI
Chartered AccountantMamta Watwani
PartnerRole in project
RATTANRAJ LIFESPACES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025231Mar 2025 → Mar 2026

Reason as filed by the promoterThe date of completion of the project was given as 31.03.2025 at the time of registration. However, we couldn’t complete said project within the stipulated period due to the finishing work, fire-fighting NOC, electricity main line connection and solar work are yet to be completed. We request to kindly accept our application and grant us the extension till 31.03.2026.

EA02032620070Mar 2025 → Mar 2027

Reason as filed by the promoterWe, RATTANRAJ LIFESPACES ("RATTANRAJ"), and we are writing you with regards to our application for extension of time till 31st March, 2027; 1. As you are aware that the company is engaged in the constructing a real estate project at Ambernath, Maharashtra on its plot of land comprising of 2 Building Wings having 16 floors.” [hereinafter collectively referred to as "the Proiect"). 2. We say that we obtained the Rera registration number for Project TRINITY MOKSH at Ambernath, Thane bearing number P51700031260. 3. We say that our project 84% completed in March-2026. However, due to bad market con

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 17th Form 1 of Moksh 30062026_11zon.pdf3 Aug 2026
Withdrawal Update Form 2File: 17th Form 2 of Moksh 30062026_11zon.pdf3 Aug 2026
Withdrawal Update Form 3File: 17th Form 3 of Moksh 30062026.pdf3 Aug 2026
Withdrawal Update Form 1File: 15th Form 1 of Moksh 31032026_11zon.pdf25 Apr 2026
Withdrawal Update Form 2File: 15th Form 2 of Moksh 31032026_11zon.pdf25 Apr 2026
Withdrawal Update Form 3File: 16th Form 3 of Moksh 31032026_11zon.pdf25 Apr 2026
Form 2A (FY 2025-2026)File: 2A For FY 2025-26_11zon (1).pdf25 Apr 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25_11zon.pdf14 Mar 2026
Withdrawal Update Form 1File: 14th Form 1 of Moksh 31122025_11zon.pdf20 Jan 2026
Withdrawal Update Form 2File: 14th Form 2 of Moksh 31122025_11zon.pdf20 Jan 2026
Withdrawal Update Form 3File: 14th Form 3 of Moksh 31122025.pdf20 Jan 2026
Withdrawal Update Form 1File: 13th Form 1 of Moksh 30092025_compressed.pdf19 Nov 2025
Withdrawal Update Form 2File: 13th Form 2 of Moksh 30092025.pdf19 Nov 2025
Withdrawal Update Form 3File: 13th Form 3 of Moksh 30092025.pdf19 Nov 2025
Form 5 (FY 2024-2025)File: FY 2024-25 Rattan raj lifespaces.pdf12 Nov 2025
Form 1File: 12th Form 1 of Moksh 30062025_11zon.pdf5 Aug 2025
Form 2File: 12th Form 2 of Moksh 30062025_11zon.pdf5 Aug 2025
Form 3File: 12th Form 3 of Moksh 30062025_11zon.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Jun-2025_11zon.pdf5 Aug 2025
Form 1File: 11th Form 1 of Moksh 31032025_11zon.pdf2 Jun 2025
Form 2File: 11th Form 2 of Moksh 31032025_11zon.pdf2 Jun 2025
Form 3File: 11th Form 3 of Moksh 31032025_11zon.pdf2 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar-2025_11zon.pdf2 Jun 2025
OthersFile: 2A for FY 2024-25.pdf2 Jun 2025
Other - TechnicalFile: P51700031260_FileName_2.pdf9 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Mar-2025_11zon.pdf8 Apr 2025
Other - TechnicalFile: PERT Chart.pdf3 Apr 2025
Declaration in FORM BFile: Form-B Developers.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10th Form 3 Revised of Moksh 31122024_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec-2022_4_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Jun-2022_7_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Sep-2022_12_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Mar-2023_10_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Jun-2023_8_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Sep-2023_13_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec-2023_5_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Mar-2024_11_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Jun-2024_9_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Sep-2024_14_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec-2024_6_11zon.pdf27 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A for FY 2021-22_11zon.pdf27 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A for FY 2022-23_11zon.pdf27 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 31122024_11zon.pdf11 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 6th 31122024_11zon.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10th Form 1 of Moksh 31122024_11zon.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10th Form 3 of Moksh 31122024_11zon.pdf14 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10th Form 2 of Moksh 31122024_11zon.pdf14 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 Trinity Moksh FY 2022-23.pdf16 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-5 of Trinity Moksh FY 2023-24_compressed.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold_11zon.pdf28 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 3rd 31032024_11zon.pdf28 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 4th 30062024_11zon.pdf28 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A 5th 30092024_11zon.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9th Form 1 of Moksh 306092024_11zon.pdf7 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9th Form 3 of Moksh 306092024_11zon.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9th Form 2 of Moksh 306092024_11zon.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8th Form 1 of Moksh 306062024.pdf16 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8th Form 2 of Moksh 306062024_11zon.pdf16 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8th Form 3 of Moksh 306062024_11zon.pdf16 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7th Form 1 of Moksh 31032024_11zon.pdf20 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7th Form 2 of Moksh 31032024_11zon.pdf20 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7th Form 3 of Moksh 31032024_11zon.pdf20 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6th Form 1 of Moksh 31122023_11zon.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6th Form 2 of Moksh 31122023_11zon.pdf12 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6th Form 3 of Moksh 31122023_11zon.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5th Form 1 of Moksh 30092023.pdf13 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5th Form 2 of Moksh 30092023.pdf13 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5th Form 3 of Moksh 30092023.pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: From 5 Trinity Mkosh FY 2022-23.pdf21 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4th Form 3 of Moksh 30062023_11zon.pdf4 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2nd Form 1 of Moksh 15122022.pdf3 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3rd Form 1 of Moksh 31032023_11zon.pdf3 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4th Form 1 of Moksh 30062023_11zon.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2nd Form 2 of Moksh 22122022.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3rd Form 2 of Moksh 31032023_11zon.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4th Form 2 of Moksh 30062023_11zon.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2nd Form 3 of Moksh 23012023_11zon.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3rd Form 3 of Moksh 31032023_11zon.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4th Form 3 of Moksh 30062023_11zon.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4th Form 3 of Moksh 30062023_11zon.pdf3 Oct 2023

How this compares with Thane

32%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRINITY MOKSH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALEGAON7,600+ in Thane

2 kmTRINITY MOKSHCompleted 175Lapsed / revoked 64Other 155Dot size: filed unitsN

Filed coordinates, straight-line distance. 394 registered projects within 2 km.

Builder: RATTANRAJ LIFESPACES

RATTANRAJ LIFESPACES has 2 registrations on MahaRERA, including TRINITY - RUDRA and TRINITY MOKSH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if TRINITY MOKSH is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRINITY MOKSH?

The registered promoter entity is RATTANRAJ LIFESPACES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRINITY MOKSH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRINITY MOKSH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRINITY MOKSH?

The professionals named in the filing: Architect: PIYUSH N BANSAL; Engineer: ATUL KUDTARKAR; Engineer: Mahesh Bhoir; Chartered Accountant: VIJAY KAVRANI; Chartered Accountant: Mamta Watwani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRINITY MOKSH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRINITY MOKSH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRINITY MOKSH to a free account