TRIDHAATU VIHAAN
By TRIDHAATU SURAJ VILLA DEVELOPERS LLP
RG-MH-66046 · RERA P51900009421 · Last updated on MahaRERA portal: 2 Dec 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 60 months past the filed date
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TRIDHAATU VIHAAN is a Residential / Group Housing project by TRIDHAATU SURAJ VILLA DEVELOPERS LLP in Mumbai City, Maharashtra, registered with MahaRERA as P51900009421 on 22 Aug 2017. Possession was promised by 30 Oct 2021 and is now 60 months past that date. The completion date has moved by 36 months from the original filing.
At a glance
Project
- NameTRIDHAATU VIHAAN
- TypeResidential / Group Housing
- Location
- Bhaudaji Road
- Matunga
- Mumbai City
- 400019
- Pincode400019
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900009421
- ReraGenie IDRG-MH-66046
Builder
- NameTRIDHAATU SURAJ VILLA DEVELOPERS LLP
- Entity typeOthers
- GSTIN27AAHFT0455D1ZD
- Named personKRISHNAN MUTHUKUMAR
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Aug 2017
- Promised completion30 Oct 2021
- Revised completionRevised to 30 Oct 2021 (originally 31 Oct 2018)
- Buildings1 building record
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TRIDHAATU VIHAAN | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
TRIDHAATU VIHAAN: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architectural Consultancy Services |
| Architect | YMS Consultants Limited |
| Engineer | SACPL |
| Partner | Role in project |
|---|---|
| TRIDHAATU SURAJ VILLA DEVELOPERS LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRCC Structure and Building Finishes of the said Project is 100% complete. Post completion, we have commenced the process for obtaining Occupation Certificate (OC) for the Project. Accordingly, we had sought time upto 31st October 2019 on the MAHARERA Website to procure the said OC. However, due to certain unforeseen circumstances the application for and procurement of Occupation Certificate (OC) has been delayed. Nonetheless we are trying to expedite and obtain the OC at the earliest.
Reason as filed by the promoterThe Project Building Tridhaatu Vihaan comprises of 18 (Eighteen) Flats inclusive of 2 (Two) Duplex Flat spread across 19 (Nineteen) floors on the Project Building. The Goods and Services Tax Act, 2017 (“GST”) was implemented to replace the Service Tax and Value Added Tax, resulting in manifold changes to the processes and policies required to be followed for engaging contractors and procurement of material for Building Construction and Finishes which resulted in delay in finishing of the project Tridhaatu Vihaan. Nonetheless, the RCC Structure is 100% complete and the Building Finishes are nea
Reason as filed by the promoterThe Project Building Tridhaatu Vihaan comprises of 16 (Sixteen) Flats and 2 (Two) Duplex Flats spread across 19 (Nineteen) floors on the Project Building. Out of the same, 9 (Nine) Flats are allotted to the Tenants of the Old Building vide Agreements for Permanent Alternate Accommodation which includes specifications as demanded by the Tenants in respect of amenities, fittings and fixtures to be provided in their individual flats. The raw materials required for providing the amenities, fittings and fixtures as assured in the aforesaid Agreements for Permanent Alternate Accommodation were not a
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 2463/2012 | Bombay City Civil Court | Pending |
| 34591 Stamp Number/2016 | Bombay High Court | Preadmission |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Form 3- Vihaan Suraj Villa- Mar 23.pdf | 2 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-Vihaan-Suraj Villa-FY 20-21.pdf | 1 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-Vihaan-Suraj Villa-FY 21-22.pdf | 1 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Vihaan-Suraj Villa-FY 22-23.pdf | 1 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3- Tridhaatu Vihaan- Mar 19.pdf | 6 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Tridhaatu Vihaan- Mar 22.pdf | 6 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Surajvilla Form 5-signed 31032023.pdf | 5 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Tridhaatu Vihaan FY 20 21.pdf | 2 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Tridhaatu vihaan 2021 22.pdf | 2 May 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Vihaan.pdf | 14 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - suraj Villa.pdf | 29 Jun 2021 |
| Declaration about Commencement CertificateFile: Fortmat D- Surajvilla- Vihaan.pdf | 22 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Fortmat D- Surajvilla- Vihaan.pdf | 15 Jun 2021 |
| Details of Restarting of Construction work post lockdownFile: Construction Status Post Lockdown-Vihaan .pdf | 2 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5 Surajvilla.pdf | 16 Dec 2019 |
| Certificates of CA (Form 5)File: Form-5 Surajvilla.pdf | 27 Sep 2019 |
| Certificates of CA (Form 5)File: Form 5 - VIHAAN 17-18.pdf | 1 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tridhaatu Vihaan Form I 31 Mar 18.pdf | 11 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I Architect Certificate Vihaan.pdf | 21 Feb 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Vihaan Form 1 16 10 17.pdf | 4 Dec 2017 |
| Building plan approvalFile: Amended Plan 1.pdf | 31 Jul 2017 |
| Building plan approvalFile: IOD-Suraj Villa.PDF | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 2.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 3.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 5.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 4.pdf | 31 Jul 2017 |
| Layout approvalFile: Amended Plan 1.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 6.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan Letter.pdf | 31 Jul 2017 |
| PAN CardFile: PAN-Tridhaatu Suraj Villa Developers LLP.PDF | 31 Jul 2017 |
| Copy of the legal title reportFile: Suraj Villa - Title Certificate - Solicitor-RS Raymond.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Details of Encumbrances.PDF | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Amended Plan 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: IOD-Suraj Villa.PDF | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 2.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 3.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 4.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 5.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 6.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan Letter.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Suraj Villa Full CC.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Declaration Form B.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate - Suraj Villa .pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Vihaan - Engineer Certificate.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Suraj Villa.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Merged-AFS and Allotment Letter.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep TRIDHAATU VIHAAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Matunga780+ in Mumbai City
Filed coordinates, straight-line distance. 216 registered projects within 2 km.
CODENAME MATUNGA ORIGINS
J. P. INFRA (MUMBAI) PRIVATE LIMITED
SHANTI HEIGHTS
Vipul Shantilal Nagda HUF
Balkrishna Hills
Oriental Contractors Private Limited
VERVE MANSION
SHANTI SIDDHI INFRA LLP
PRINCECARE AMARAA
PRINCECARE AMARAA LLP
Godrej Five Gardens
Godrej Projects Development Ltd.
See every Mumbai City project, with the district possession charts
Builder: TRIDHAATU SURAJ VILLA DEVELOPERS LLP
TRIDHAATU SURAJ VILLA DEVELOPERS LLP has 1 registration on MahaRERA, including TRIDHAATU VIHAAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that TRIDHAATU VIHAAN shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TRIDHAATU VIHAAN is delayed beyond 30 Oct 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TRIDHAATU VIHAAN?
The registered promoter entity is TRIDHAATU SURAJ VILLA DEVELOPERS LLP, an others as per the filing. Its GSTIN 27AAHFT0455D1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TRIDHAATU VIHAAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TRIDHAATU VIHAAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TRIDHAATU VIHAAN?
The professionals named in the filing: Architect: Architectural Consultancy Services; Architect: YMS Consultants Limited; Engineer: SACPL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TRIDHAATU VIHAAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback