ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / TRIDHAATU ARANYA - A DREAM

Registered No litigation declared Residential / Group Housing project

TRIDHAATU ARANYA - A DREAM

By TRIDHAATU ARANYA DEVELOPERS LLP

RG-MH-30411 · RERA P51800031547 · Last updated on MahaRERA portal: 13 Jan 2025

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
3Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

TRIDHAATU ARANYA - A DREAM is a Residential / Group Housing project by TRIDHAATU ARANYA DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031547 on 25 Oct 2021. Possession is promised by 31 Dec 2027. 3 complaints are on record with the regulator.

At a glance

Project

  • NameTRIDHAATU ARANYA - A DREAM
  • TypeResidential / Group Housing
  • Location
    • Deonar
    • Kurla
    • Mumbai Suburban
    • 400088
  • Pincode400088
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800031547
  • ReraGenie IDRG-MH-30411

Builder

  • NameTRIDHAATU ARANYA DEVELOPERS LLP
  • Entity typeOthers
  • Named personDhananjay Sandu
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2021PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2021
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIDHAATU ARANYA - A DREAMNA290000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

TRIDHAATU ARANYA - A DREAM: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed320

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots320
Closed/Covered320

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,445 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI25000.0
Proposed, not sanctioned4,718 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVijay Cinema, Near Diamond Garden, Chembur, 71

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAakar Architects and Consultants
ArchitectAakar Architects & Consultants
ArchitectBhalchandra Walanju
EngineerMilind Kulkarni Consulting Engineers
EngineerArun Surve
Chartered AccountantSHETH DOSHI AND ASSOCIATES
Chartered AccountantS.R. Shelke & Associates
Chartered AccountantDMJ & Company
PartnerRole in project
TRIDHAATU ARANYA DEVELOPERS LLP-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000408151PRAKASH KRISHNA SHETTYTRIDHAATU ARANYA DEVELOPERS LLP14/11/2023
CC006000000429609PRAKASH KRISHNA SHETTYTRIDHAATU ARANYA DEVELOPERS LLP13/03/2024
CC12503356Simon AbrahamTRIDHAATU ARANYA DEVELOPERS LLP20/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2025

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: RERA Certificate Form 4 06012025.pdf13 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC signed Aranya dt 1102024.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A March 2023 -2024.pdf30 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aranya A Dream 310721.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aranya A Dream 310323.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aranya A Dream 310323.pdf23 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Aranya A Dream 300623.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aranya A Dream Form 3 31032023.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aranya A Dream Form 3 30062023.pdf23 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March 2021-2022.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A March 2022 2023.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tridhaatu Aranya -A dream-Form 5-31032023.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Aranya - A Dream FY 21-22.pdf9 May 2023
Building plan approvalFile: PAGE 1.pdf23 Feb 2022
Building plan approvalFile: PAGE 2.pdf23 Feb 2022
Building plan approvalFile: PAGE 3.pdf23 Feb 2022
Building plan approvalFile: PAGE 4.pdf23 Feb 2022
Building plan approvalFile: PAGE 5.pdf23 Feb 2022
Building plan approvalFile: PAGE 6.pdf23 Feb 2022
Building plan approvalFile: PAGE 7.pdf23 Feb 2022
Building plan approvalFile: PAGE 8.pdf23 Feb 2022
Building plan approvalFile: PAGE 9.pdf23 Feb 2022
Building plan approvalFile: PAGE 10.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 1.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 2.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 3.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 4.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 5.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 6.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 7.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 8.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 9.pdf23 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PAGE 10.pdf23 Feb 2022
Layout approvalFile: Drawing Aranya.pdf16 Aug 2021
Copy of Layout Approval (in case of layout)File: Drawing Aranya.pdf16 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tridhaatu Aranya A Dream Form 3.pdf13 Aug 2021
Building plan approvalFile: IOD Letter.pdf11 Aug 2021
Building plan approvalFile: Drawing 1.PDF11 Aug 2021
Building plan approvalFile: Drawing 2.pdf11 Aug 2021
Building plan approvalFile: Drawing 3.PDF11 Aug 2021
PAN CardFile: TRIDHAATU ARANYA DEVELOPERS LLP-PAN Card.PDF11 Aug 2021
Copy of the legal title reportFile: Title-Aranya Supplementary -Compresed.pdf11 Aug 2021
Copy of the legal title reportFile: Aranya II Title Certificate Hariani and Co Pages 13 to 26.pdf11 Aug 2021
Copy of the legal title reportFile: Aranya Title Report.PDF11 Aug 2021
Details of encumbrancesFile: Details of encumbrances.pdf11 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD Letter.pdf11 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Drawing 1.PDF11 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Drawing 2.pdf11 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Drawing 3.PDF11 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf11 Aug 2021
Declaration about Commencement CertificateFile: Format- D- DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf11 Aug 2021
Declaration in FORM BFile: FORM B- Declaration.pdf11 Aug 2021
Proforma of Allotment letterFile: RERA Allotment Letter-Tridhaatu Aranya-A Dream.pdf11 Aug 2021
Proforma of Allotment letterFile: Draft AFS-Tridhaatu Aranya A Dream.pdf11 Aug 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIDHAATU ARANYA - A DREAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Deonar6,700+ in Mumbai Suburban

2 kmTRIDHAATU ARANYA - A DRECompleted 88Lapsed / revoked 53Other 73Dot size: filed unitsN

Filed coordinates, straight-line distance. 214 registered projects within 2 km.

Builder: TRIDHAATU ARANYA DEVELOPERS LLP

TRIDHAATU ARANYA DEVELOPERS LLP has 2 registrations on MahaRERA, including Tridhaatu Aranya and TRIDHAATU ARANYA - A DREAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if TRIDHAATU ARANYA - A DREAM is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIDHAATU ARANYA - A DREAM?

The registered promoter entity is TRIDHAATU ARANYA DEVELOPERS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIDHAATU ARANYA - A DREAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TRIDHAATU ARANYA - A DREAM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TRIDHAATU ARANYA - A DREAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIDHAATU ARANYA - A DREAM?

The professionals named in the filing: Architect: Aakar Architects and Consultants; Architect: Aakar Architects & Consultants; Architect: Bhalchandra Walanju; Engineer: Milind Kulkarni Consulting Engineers; Engineer: Arun Surve; Chartered Accountant: SHETH DOSHI AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIDHAATU ARANYA - A DREAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIDHAATU ARANYA - A DREAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIDHAATU ARANYA - A DREAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.