ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai City, Maharashtra / Tridhaatu Aaroha

Registration lapsed Litigation declared Residential / Group Housing project

Tridhaatu Aaroha

By Tridhaatu Vishnu Kunj Developers LLP

RG-MH-92362 · RERA P51900010312 · Last updated on MahaRERA portal: 5 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 63 months
  • 4 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 95%
1Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Tridhaatu Aaroha is a Residential / Group Housing project by Tridhaatu Vishnu Kunj Developers LLP in Mumbai City, Maharashtra, registered with MahaRERA as P51900010312 on 24 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 63 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTridhaatu Aaroha
  • TypeResidential / Group Housing
  • Location
    • KA Subramaniyam Road
    • Matunga
    • Mumbai City
    • 400019
  • Pincode400019
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900010312
  • ReraGenie IDRG-MH-92362

Builder

  • NameTridhaatu Vishnu Kunj Developers LLP
  • Entity typeOthers
  • GSTIN27AAGFT7483C1ZY
  • Named personRrajesh Survey

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseSep 2018Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Sep 2018)
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIDHAATU AAROHANA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

TRIDHAATU AAROHA: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 5 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area373 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2024

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai (MCGM)
Permissible FSI1495.31
Proposed, not sanctioned1,495 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNew Vijay V N Purav Marg Sion Trombay Road 400071

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAakar Architect & Consultants
ArchitectMadhuri Khandekar
EngineerMilind Kulkarni Consulting Engineers
Chartered AccountantS R Shelke & Associates
Chartered AccountantDMJ & Company
PartnerRole in project
Tridhaatu Vishnu Kunj Developers LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900012733Sep 2018 → Dec 2023

Reason as filed by the promoterSeeking Extension under 7(3) of the RERA Act and basis majority consent received from Allottees as attached with this Application

EXT51900009760Sep 2018 → Mar 2022

Reason as filed by the promoterThe Project Building Tridhaatu Aaroha comprises of Ground plus 18 (Eighteen) slabs i.e., 17 (seventeen) floors. The RCC Structure of the Project Building is 100% complete, the Building Finishes are in progress. In March 2020, due to the unprecedented COVID-19 pandemic the GoI declared a nation-wide lockdown, resulting into reverse migration of construction workers to their hometowns and also impacted the supply chain of raw materials. Thereby, due to the unavailability of in-situ labour, delayed approvals and required raw materials, all construction activities on the Project Building were stal

EXT51900002596Sep 2018 → Sep 2020

Reason as filed by the promoterThe Project Building Tridhaatu Aaroha comprises of Ground plus 18 (Eighteen) slabs i.e., 17 (seventeen) floors. The initial changes brought about by the advent of the Goods and Service tax (GST) followed by the changing market situation has led to certain delays in procurement of material as well as retention/ engaging contractors for Building Construction and Finishes which has resulted in an overall delay in finishing of the project Tridhaatu Aaroha. Nonetheless, the RCC Structure of the Project Building is 100% complete and the Building Finishes are in progress. Post completion of the same,

EXT51900000678Sep 2018 → Sep 2020

Reason as filed by the promoterThe Project Building Tridhaatu Aaroha comprises of 16 (Sixteen) Flats inclusive of 1 (One) Duplex Flat spread across 17 (Seventeen) floors on the Project Building. The Goods and Services Tax Act, 2017 (“GST”) was implemented to replace the Service Tax and Value Added Tax, resulting in manifold changes to the processes and policies required to be followed for selling a real estate product and for engaging contractors for Building Construction and Finishes. However, the RCC Structure of the Tridhaatu Aaroha Project is 100% complete and finishing work is in progress. Due to the GST having impacte

Litigation declared1

CaseCourtStatus
CC006000000395818/2024Maharashtra Real Estate Regulatory AuthorityOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000395818Arun Sitaram MaheshwariTridhaatu Vishnu Kunj Developers17/05/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: CERSAI Declaration.pdf5 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A-Aaroha.pdf5 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Aaroha - RS.pdf5 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Tridhaatu Aaroha 2023.pdf5 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked Inventory -Aaroha-2024.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Cert 2024.pdf7 Oct 2024
Declaration in FORM BFile: Form B.pdf17 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Vishnu Kunj Mar 24.pdf9 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Invetory 2024.pdf9 Aug 2024
Certificates of CA (Form 3)File: Form 3 31032024.pdf9 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 310324.pdf9 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Tridhaatu Aaroha 2023-24.pdf30 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu Kunj Mar - 21.pdf19 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu Kunj Mar - 22.pdf19 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Vishnu Kunj Mar - 23.pdf19 Dec 2023
Certificates of CA (Form 3)File: Form 3- VishnuKunj Aaroha- Mar 23.pdf2 Dec 2023
Certificates of CA (Form 3)File: Form 3- Vishnukunj Aroha- Mar 19_.pdf25 Oct 2023
Certificates of CA (Form 3)File: Form 3- Vishnukunj Aroha- Mar 21.pdf25 Oct 2023
Certificates of CA (Form 3)File: Form 3- Vishnukunj Aroha- Mar 22.pdf25 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Vishnu kunj form 5 signed 31032023.pdf5 Oct 2023
Certificates of CA (Form 3)File: Tridhaatu Aaroha Form 3 31032021.pdf11 Jan 2023
Certificates of CA (Form 3)File: Tridhaatu Aaroha Form 3 31032022.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA FORM 5 Aaroha 31032021.pdf11 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Form 5 Aaroha 31032022.pdf11 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aaroha - Form 1.pdf17 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - October 2022.pdf8 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked Inventory -Aaroha-2022.pdf8 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Aaroha 2022.pdf19 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A-Aaroha 2020.pdf4 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A-Aaroha 2021.pdf4 Dec 2021
Disclosure of sold/ booked inventoryFile: Disclosure of Sold- Booked Inventory -Aaroha.pdf29 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Vishnu kunj.pdf29 Jun 2021
Declaration about Commencement CertificateFile: Fortmat D- Vishnu Kunj- Aaroha.pdf22 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Fortmat D- Vishnu Kunj- Aaroha.pdf15 Jun 2021
Details of Restarting of Construction work post lockdownFile: Construction Status Post Lockdown-Tridhaatu Aaroha.pdf2 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5 Vishnukunj.pdf12 Dec 2019
Certificates of CA (Form 5)File: Form-5 Vishnukunj.pdf27 Sep 2019
Certificates of CA (Form 5)File: Form 5 - AAROHA 17-18.pdf1 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Tridhaatu Aaroha Architect Certificate 31 Mar 18.PDF11 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I Architect Certificate Vishnu Kunj 31 Dec 17.pdf28 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VISHNUKUNJ FORM 1 Architect 16 10 17.pdf4 Dec 2017
Building plan approvalFile: Approved Plan 4.pdf31 Jul 2017
Building plan approvalFile: Approved Plan 3.pdf31 Jul 2017
Building plan approvalFile: IOD-Vishnukunj.pdf31 Jul 2017
Building plan approvalFile: Approved Plan 1.pdf31 Jul 2017
Building plan approvalFile: Approved Plan 2.pdf31 Jul 2017
Layout approvalFile: Approved Plan 1.pdf31 Jul 2017
PAN CardFile: PAN-Tridhaatu Vishnukunj Developers LLP.PDF31 Jul 2017
Copy of the legal title reportFile: Title Certificate-Vishnu Kunj.pdf31 Jul 2017
Details of encumbrancesFile: TRIDHAATU AAROHA-ENCUMBRANCE CERTIFICATE.PDF31 Jul 2017
Copy of Layout Approval (in case of layout)File: Approved Plan 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD-Vishnukunj.pdf31 Jul 2017
Building Plan Approval (IOD)File: Approved Plan 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: Approved Plan 2.pdf31 Jul 2017
Building Plan Approval (IOD)File: Approved Plan 3.pdf31 Jul 2017
Building Plan Approval (IOD)File: Approved Plan 4.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate-Vishnukunj.pdf31 Jul 2017
Declaration in FORM BFile: Declaration Form B.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect cerificate - Vishnu Kunj.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Aaroha - Engineer Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Merged-AFS and Allotment Letter.pdf31 Jul 2017

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 63 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tridhaatu Aaroha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Matunga780+ in Mumbai City

2 kmTridhaatu AarohaCompleted 79Lapsed / revoked 51Other 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 205 registered projects within 2 km.

Builder: Tridhaatu Vishnu Kunj Developers LLP

Tridhaatu Vishnu Kunj Developers LLP has 1 registration on MahaRERA, including Tridhaatu Aaroha. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Tridhaatu Aaroha shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Tridhaatu Aaroha is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tridhaatu Aaroha?

The registered promoter entity is Tridhaatu Vishnu Kunj Developers LLP, an others as per the filing. Its GSTIN 27AAGFT7483C1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tridhaatu Aaroha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Tridhaatu Aaroha?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Tridhaatu Aaroha?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tridhaatu Aaroha?

The professionals named in the filing: Architect: Aakar Architect & Consultants; Architect: Madhuri Khandekar; Engineer: Milind Kulkarni Consulting Engineers; Chartered Accountant: S R Shelke & Associates; Chartered Accountant: DMJ & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tridhaatu Aaroha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tridhaatu Aaroha. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tridhaatu Aaroha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.