Completed No litigation declared Residential / Group Housing project

Triaa Aashray

By EBPL HOMES LLP

RG-MH-25693 · RERA P52700013128 · Last updated on MahaRERA portal: 2 Nov 2023

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 84 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Sep 2025Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
1Complaints at MahaRERAon this registration
Jump to the 52 documents Report an error

Triaa Aashray is a Residential / Group Housing project by EBPL HOMES LLP in Satara, Maharashtra, registered with MahaRERA as P52700013128 on 14 Sep 2017. The registration is recorded completed; possession was promised by 30 Sep 2025. The completion date has moved by 84 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTriaa Aashray
  • TypeResidential / Group Housing
  • Location
    • Shindewadi
    • Khandala
    • Satara
    • 412801
  • Pincode412801
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700013128
  • ReraGenie IDRG-MH-25693

Builder

  • NameEBPL HOMES LLP
  • Entity typePartnership
  • GSTIN27AAEFE1604Q3Z9
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersARUN JAGDISH AGARWAL, SHEKHAR RAJKUMAR GUPTA, ARUNITABUILDCONPRIVATELIMITED THROUGHDIRECTOR
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredSep 2017First promiseSep 2018Revised toSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Sep 2017
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Sep 2018)
  • Buildings1 building record
  • Documents filed52 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building CNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Building C: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 2 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes65%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes75%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes45%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes40%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Shivsai DevelopersDhanakwadiSatara

Approvals and building plan

Permissible FSI3047.38
Proposed, not sanctioned1,533 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSrishti Chambers,C Wing,Pune Nagar Road,Pune-411014

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA DESIGN STUDIO ASSOCIATES
PartnerRole in project
EBPL HOMES LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700002364Sep 2018 → Sep 2020

Reason as filed by the promoterDelay on account of slow sales, Cash flow issue.

EXT52700002554Sep 2018 → Sep 2020

Reason as filed by the promoterDue to lack of bookings, we are out of funds. Due to market slack and location of the project, we could sell only 5 flats which is not even 50% of total flats. Inspite of shortage in funds, we have completed 85% of the site out of own funds. Kindly provide us extension in order to complete the remaining 15% work.

EXT52700011280Sep 2018 → Mar 2023

Reason as filed by the promoterProject delayed due to Covid Restrictions and un availability of labor and material

EXT52700017769Sep 2018 → Sep 2025

Reason as filed by the promoterWe had completed 90% Project as per current approvals. However due to change in development policy we can get further potential development. We need time to complete project as per current approvals and utilize further additional potential

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501814Raviraj Dattatray KulkarniEBPL HOMES LLP02/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed52

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventorynew .pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf23 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEER - FORM2 A.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 EBPL Homes LLP CA 22-23.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 EBPL Homes LLP CA 21-22.pdf18 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate 22 09 23.pdf13 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- engineer's certificate.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEER - FORM2 A.pdf13 Oct 2023
Certificates of CA (Form 3)File: Form 3 EBPL Homes LLP CA_compressed.pdf13 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 EBPL Homes LLP CA 21-22.pdf13 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 EBPL Homes LLP CA 22-23.pdf13 Oct 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf7 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECTS CERT.pdf7 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2 A ENGINEERS CERT.pdf7 Jan 2022
Disclosure of sold/ booked inventoryFile: sold unsold declaration 7 1 22.pdf7 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227649485_For_Asset_Based_Search_07_01_2022_13_07_23_697.pdf7 Jan 2022
Certificates of CA (Form 3)File: CA form 3 Q2 21 22_compressed.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2018-2019.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 2019-2020.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-2021.pdf7 Jan 2022
Architect’s Certificate on Completion of Project (Form 4)File: form 4.pdf14 Oct 2019
OtherFile: 7 NEW Partnership Deed 29 APRIL 2019.pdf25 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf7 Sep 2019
Building plan approvalFile: Total Land Plan Copy.pdf6 Sep 2019
Layout approvalFile: Total Land Plan Copy.pdf6 Sep 2019
Building plan approvalFile: PLAN C D.pdf6 Sep 2019
Building plan approvalFile: Plan C D 1.pdf6 Sep 2019
Copy of Layout Approval (in case of layout)File: Total Land Plan Copy.pdf6 Sep 2019
Building Plan Approval (IOD)File: Total Land Plan Copy.pdf6 Sep 2019
Building Plan Approval (IOD)File: PLAN C D.pdf6 Sep 2019
Building Plan Approval (IOD)File: Plan C D 1.pdf6 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Cert.pdf6 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Cert.pdf6 Sep 2019
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2 Engineer Cert.pdf6 Sep 2019
Certificates of CA (Form 3)File: Form -3 EBPL Homes LLP.pdf6 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 CA CERTIFICATE 2018.pdf6 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 CA CERTIFICATE 2019.pdf6 Sep 2019
OtherFile: 1 Mortgage Deed.pdf19 Dec 2017
Building plan approvalFile: Layout.pdf31 Aug 2017
Layout approvalFile: Layout.pdf31 Aug 2017
PAN CardFile: 3 Pan Card.pdf31 Aug 2017
Copy of the legal title reportFile: 8 Legal Title.pdf31 Aug 2017
Details of encumbrancesFile: 5 Encumburances.pdf31 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf31 Aug 2017
Building Plan Approval (IOD)File: Layout.pdf31 Aug 2017
Declaration in FORM BFile: Form B.pdf31 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf31 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginner Cert.pdf31 Aug 2017
Certificates of CA (Form 3)File: CA-ilovepdf-compressed.pdf31 Aug 2017
Proforma of Allotment letterFile: Allottment letter.pdf31 Aug 2017
Proforma of Allotment letterFile: RERA Draft Agreement.pdf31 Aug 2017

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 84 months
35%of Satara registrations have lapsed or been cancelledthis one is completed

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep Triaa Aashray on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shindewadi1,100+ in Satara

2 kmTriaa AashrayCompleted 2Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: EBPL HOMES LLP

EBPL HOMES LLP has 2 registrations on MahaRERA, including Triaa Aashray and TRIAA AASHRAY WING D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if Triaa Aashray is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Triaa Aashray?

The registered promoter entity is EBPL HOMES LLP, a partnership as per the filing. Its GSTIN 27AAEFE1604Q3Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Triaa Aashray?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Triaa Aashray?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Triaa Aashray?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Triaa Aashray?

The professionals named in the filing: Architect: A DESIGN STUDIO ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Triaa Aashray?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Triaa Aashray. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Triaa Aashray to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.