Home / Browse projects / Satara, Maharashtra / Quadra Town

Registered No litigation declared Residential / Group Housing project

Quadra Town

By Bhujbal Brothers Properties

RG-MH-24925 · RERA P52700026490 · Last updated on MahaRERA portal: 3 Oct 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 70 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Jul 2028Possession promisedmoved 70 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 75%
99 of 112Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Quadra Town is a Residential / Group Housing project by Bhujbal Brothers Properties in Satara, Maharashtra, registered with MahaRERA as P52700026490 on 26 Sep 2020. Possession is promised by 31 Jul 2028. The completion date has moved by 70 months from the original filing. 13 of the 112 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameQuadra Town
  • TypeResidential / Group Housing
  • Location
    • Khandala
    • Shindewadi
    • Satara
    • 412801
  • Pincode412801
  • RERA no.P52700026490
  • ReraGenie IDRG-MH-24925

Builder

  • NameBhujbal Brothers Properties
  • Entity typePartnership
  • PartnersSaroj Jagannath Bhujbal, Dhiraj Raman Bhujbal

Key dates

this monthRegisteredSep 2020First promiseSep 2022Revised toJul 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2020
  • Promised completion31 Jul 2028
  • Revised completionRevised to 31 Jul 2028 (originally 30 Sep 2022)
  • Buildings2 building records
  • Documents filed58 files

Current status

12%13 of 112 units booked

Figures as on 3 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1NA8756056
CNA8756056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 75%.

B170%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes75%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes75%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityTown Planning and Valuation Department, Satara Branch
Permissible FSI11624.0
Proposed, not sanctioned11,624 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch421, 422, Shaniwar Peth, Pune - 411030

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANS Architects and interior Designers Mr Sumit S Bagade
Engineerdnyanewshwar d khilare
Chartered AccountantDivekar Rairikar & Company
Chartered AccountantAgarwal Dayma & Co. LLP
PartnerRole in project
Bhujbal Brothers Properties-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24072502178Sep 2022 → Jul 2028

Reason as filed by the promoterRespected Authority, We, the Promoter/Developer of the project, have undertaken this development with utmost dedication and integrity, ensuring every aspect is crafted to high standards. Despite comprehensive planning and sustained marketing efforts, unforeseen financial setbacks and adverse market conditions have severely impacted the sales process in the said RERA project which consist of 2 buildings i.e. “B1” & “C”. Despite these challenges, we have persevered and nearly completed the construction work of “B1” building up to 4th floor and “C” building up to 3rd floor, demonstrating our comm

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000085281Madhuri Sunil TambeM/s. Bhujbal Brothers Properties27/03/2021
CC12503323Kawaljit Gur SinghBhujbal Brothers Properties17/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2028

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2020-2021)File: Scanned Document 5.pdf3 Oct 2025
Form 2A (FY 2021-2022)File: Scanned Document 8.pdf3 Oct 2025
Form 2A (FY 2022-2023)File: Scanned Document 9.pdf3 Oct 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q2.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q4.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2021-22 Q1.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q2.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q3.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q4.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2021-22 Q1.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Form 1File: Form1 .pdf23 Jul 2025
Form 2File: FORM 2.pdf23 Jul 2025
Form 3File: Form 3 2020-21 Q2.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold book inventry.pdf23 Jul 2025
Commencement Certificates / NA Order for plotted developmentFile: NA Qua_merged file.pdf29 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: SDO Permission QT 1.pdf4 Jun 2019
Declaration in FORM BFile: Form B.pdf4 Jun 2019
Layout approvalFile: Layout.pdf8 Aug 2017
Building plan approvalFile: 4-5.pdf8 Aug 2017
Building plan approvalFile: 5-5.pdf8 Aug 2017
Building plan approvalFile: Layout.pdf8 Aug 2017
Copy of the legal title reportFile: Search Title Report.PDF8 Aug 2017
Details of encumbrancesFile: DOC002.PDF8 Aug 2017
Details of encumbrancesFile: DOC003.PDF8 Aug 2017
Details of encumbrancesFile: DOC004.PDF8 Aug 2017
Details of encumbrancesFile: DOC005.PDF8 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf8 Aug 2017
Building Plan Approval (IOD)File: 4-5.pdf8 Aug 2017
Building Plan Approval (IOD)File: 5-5.pdf8 Aug 2017
Building Plan Approval (IOD)File: Layout.pdf8 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Quadra Town Eng Cert.pdf8 Aug 2017
Certificates of CA (Form 3)File: CA Certificate.pdf8 Aug 2017
Proforma of Allotment letterFile: Articles of Agreement.pdf8 Aug 2017

How this compares with Satara

12%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 70 months
35%of Satara registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep Quadra Town on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shindewadi1,100+ in Satara

Builder: Bhujbal Brothers Properties

Bhujbal Brothers Properties has 1 registration on MahaRERA, including Quadra Town. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What are my rights if Quadra Town is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Quadra Town?

The registered promoter entity is Bhujbal Brothers Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Quadra Town?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Quadra Town?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Quadra Town?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Quadra Town?

The professionals named in the filing: Architect: SANS Architects and interior Designers Mr Sumit S Bagade; Engineer: dnyanewshwar d khilare; Chartered Accountant: Divekar Rairikar & Company; Chartered Accountant: Agarwal Dayma & Co. LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Quadra Town?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Quadra Town. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Quadra Town to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.