Home / Browse projects / Pune, Maharashtra / TREASURE TROVES

Registered Litigation declared Others project

TREASURE TROVES

By REALCON HOMES LLP

RG-MH-56395 · RERA P52100052582 · Last updated on MahaRERA portal: 8 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 5 cases
  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2031Possession promisedmoved 4 months from the original
15 of 55Construction stages doneacross 5 buildings; furthest along: Slabs of Super Structure, 96%
130 of 490Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

TREASURE TROVES is a Others project by REALCON HOMES LLP in Pune, Maharashtra, registered with MahaRERA as P52100052582 on 11 Sep 2023. Possession is promised by 30 Apr 2031. The completion date has moved by 4 months from the original filing. 360 of the 490 units on this registration are recorded sold or booked, and 15 of 55 construction stages are filed complete.

At a glance

Project

  • NameTREASURE TROVES
  • TypeOthers
  • Location
    • 113/1 PART. BHUMKAR DAS GUGRE ROAD
    • BHAGVAN NAGAR
    • OPP SUKHAWANI SKYLINES
    • WAKAD
    • PUNE
    • Wakad
    • Mulshi
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052582
  • ReraGenie IDRG-MH-56395

Builder

  • NameREALCON HOMES LLP
  • Entity typePartnership
  • GSTIN27ABBFR5242F1ZC
  • PartnersPritam Vilas Rathod, Vilas Chaganlal Rathod, Kanhaiyalal Hotchand Matani, Vashu Hotchand Matani, Rajesh Krishnakumar Goyal, Jaideep Dhananjay Modak

Key dates

this monthRegisteredSep 2023First promiseDec 2030Revised toApr 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion30 Apr 2031
  • Revised completionRevised to 30 Apr 2031 (originally 31 Dec 2030)
  • Buildings5 building records
  • Documents filed113 files

Current status

73%360 of 490 units booked
32.2%Work done, per cost certificate

Figures as on 8 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-BUILDING - AMBERNA272388694
B-BUILDING - SAPPHIRENA272388593
C-BUILDING - EMERALDNA13131126118
D-BUILDING - PEARLNA212188593
E-BUILDING - RUBYNA212188492

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 8 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Slabs of Super Structure, at 96%.

A-BUILDING - AMBER56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises61%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks41%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.47%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
B-BUILDING - SAPPHIRE56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises61%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks41%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.47%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
C-BUILDING - EMERALD45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises26%
Sanitary Fittings within the flats / premises24%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.18%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.13%
D-BUILDING - PEARL29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%
E-BUILDING - RUBY29%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure7%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.1%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.12%

Progress on shared amenities15

As on 8 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes33%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes7%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25
BuildingClosed/CoveredTotal
A-BUILDING - AMBER22
B-BUILDING - SAPPHIRE55
C-BUILDING - EMERALD66
D-BUILDING - PEARL55
E-BUILDING - RUBY77

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area13,647 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Apr 2026

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI51972.44
Proposed, not sanctioned51,972 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD, PUNE
Estimated costRs 172.64 cr
Cost incurredRs 55.67 cr
Work done32.25%
BuildingWingEstimatedIncurred
C-BUILDING - EMERALDNARs 39.47 crRs 22.41 cr
B-BUILDING - SAPPHIRENARs 30.07 crRs 10.26 cr
A-BUILDING - AMBERNARs 29.95 crRs 10.36 cr
E-BUILDING - RUBYNARs 29.11 crRs 4.48 cr
D-BUILDING - PEARLNARs 28.97 crRs 4.41 cr
-NARs 15.06 crRs 3.77 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMilind Patil
EngineerSudhir Kulkarni
Chartered AccountantMadhusudan Jhanwar
Chartered AccountantRushabh Dugad
PartnerRole in project
REALCON HOMES LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100052582/WarDec 2030 → Apr 2031

Reason as filed by the promoterNA

Litigation declared5

CaseCourtStatus
341/2016Civil Judge Junior Division Pimpri PuneOngoing
37/2026District Judge and Additional Sessions Judge Pimpri ChinchwadOngoing
732/2020Civil Judge Senior Division PuneClosed
773/2021Civil Judge Senior Division PuneOngoing
11445/2018High Court BombayClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2031

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Form 2 A F y 2023-2024.pdf8 Aug 2026
Form 2A (FY 2024-2025)File: Form 2 A F y 2024-2025.pdf8 Aug 2026
Form 2A (FY 2025-2026)File: Form 2 A F y 2025-2026.pdf8 Aug 2026
Form 5 (FY 2023-2024)File: Form 5 F y 2023-2024.pdf5 Aug 2026
Form 5 (FY 2024-2025)File: Form 5 F y 2024-2025.pdf5 Aug 2026
Withdrawal Update Form 1File: REALCON HOMES LLP FORM 1 JUNE 2026.pdf18 Jul 2026
Withdrawal Update Form 2File: REALCON HOMES LLP FORM 2 JUNE 2026.pdf18 Jul 2026
Withdrawal Update Form 3File: REALCON HOMES LLP FORM 3 JUNE 2026 (1)_11zon.pdf18 Jul 2026
Withdrawal Update Form 1File: Final ARCHITECT CERTIFICATE TT.pdf28 May 2026
Withdrawal Update Form 2File: Realcon Homes LLP - Form - 2 (1) (1).pdf28 May 2026
Withdrawal Update Form 3File: Final Realcon Homes LLP - Form - 3_compressed.pdf28 May 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 1File: Form 1.pdf5 May 2026
Withdrawal Update Form 1File: Form 1.pdf5 May 2026
Withdrawal Update Form 1File: Form 1.pdf5 May 2026
Withdrawal Update Form 2File: Form 2.pdf5 May 2026
Withdrawal Update Form 2File: Form 2.pdf5 May 2026
Withdrawal Update Form 2File: Form 2.pdf5 May 2026
Withdrawal Update Form 3File: Form 3.pdf5 May 2026
Withdrawal Update Form 3File: Form 3.pdf5 May 2026
Withdrawal Update Form 3File: Form 3.pdf5 May 2026
Withdrawal Update Form 1File: Treasure Trove - form 1 S.pdf2 May 2026
Withdrawal Update Form 1File: Treasure Trove - form 1 S.pdf2 May 2026
Withdrawal Update Form 2File: REALCON HOMES LLP FORM 2 s.pdf2 May 2026
Withdrawal Update Form 2File: REALCON HOMES LLP FORM 2 s.pdf2 May 2026
Withdrawal Update Form 3File: REALCON HOMES LLP FORM 3 s_compressed.pdf2 May 2026
Withdrawal Update Form 3File: REALCON HOMES LLP FORM 3 s_compressed.pdf2 May 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_TT_Q1 25-26.pdf16 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_TT_Q1 25-26.pdf16 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_TT_Q1 25-26.pdf16 Jul 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory_TT_Jun-25.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_TT_Q4_24-25.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_TT_Q4_24-25.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_TT_Q4_24-25.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory_TT_March-25.pdf14 Apr 2025
Proforma of Agreement for saleFile: SD_Treasure_Troves_Wakad_113_Flat_Agreement_Draft For A and B Building Rera Purpose March 25 Mar 2025
Proforma of Agreement for saleFile: SD_Treasure_Troves_Wakad_113_Flat_Agreement_Draft For C Building Rera Purpose March 25.pdf25 Mar 2025
Proforma of Agreement for saleFile: SD_Treasure_Troves_Wakad_113_Flat_Agreement_Draft For D and E Building Rera Purpose March 25 Mar 2025
Proforma of Agreement for saleFile: Treasure Troves Draft Agreement For A and B Building Rera Purpose.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Treasure Troves_Q3 24-25.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Treasure Troves_Q3 24-25.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Treasure Troves_Q3 24-25.pdf21 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory_TT_Dec-24.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TT_Form-1_Sep-24.pdf26 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: TT_Form 3_Sep-24.pdf26 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TT_Form-2_Sep-24.pdf26 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: TT_Form 2A_Sep-24.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: TT_Form 5.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: TT_Disclosure of Sold booked Inventory_Sep-24.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Treasure Troves.pdf12 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Treasure Troves.pdf12 Jul 2024
Disclosure of sold/ booked inventoryFile: Treasure Troves_compressed.pdf12 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Treasure Troves_compressed.pdf12 Jul 2024
Copy of the legal title reportFile: Title Report Treasure Troves Part I.pdf20 Jun 2024
Copy of the legal title reportFile: Title Report Treasure Troves Part II.pdf20 Jun 2024
Proforma of Agreement for saleFile: Treasure Troves Revised Agreement draft 20062024 (1).pdf20 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrances of Bajab Finance.pdf6 Jun 2024
Details of encumbrances concerned to LegalFile: Encumbrances of Bajab Finance.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Treasure Troves_compressed.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Treasure Troves.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Treasure Troves 31-3-2024.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Treasure Troves 16-4-2024-C.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: TreasureTroves.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 of Treasure Troves 6th Jan 2024.pdf8 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Treasure Troves 5-1-2024.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Treasure Toves 1-1-2024.pdf6 Jan 2024
Disclosure of sold/ booked inventoryFile: Treasure Troves.pdf12 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form - 1 Treasure Troves.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Treasure Troves.pdf11 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Treasure Troves.pdf11 Oct 2023
CERSAI detailsFile: Non - Encumbrance Letter.pdf31 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A Pritam Rathod.pdf7 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A Vilas Rathod.pdf7 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A Jaydeep Modak.pdf7 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A Kanhaiyalal Matani.pdf7 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure-A Vashu Matani.pdf7 Jul 2023
Layout approvalFile: IOD.pdf6 Jul 2023
Details of encumbrances concerned to FinanceFile: ilovepdf_merged.pdf6 Jul 2023

How this compares with Pune

73%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 4 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TREASURE TROVES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

2 kmTREASURE TROVESCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: REALCON HOMES LLP

REALCON HOMES LLP has 1 registration on MahaRERA, including TREASURE TROVES. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TREASURE TROVES is delayed beyond 30 Apr 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TREASURE TROVES?

The registered promoter entity is REALCON HOMES LLP, a partnership as per the filing. Its GSTIN 27ABBFR5242F1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TREASURE TROVES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TREASURE TROVES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TREASURE TROVES?

The professionals named in the filing: Architect: Milind Patil; Engineer: Sudhir Kulkarni; Chartered Accountant: Madhusudan Jhanwar; Chartered Accountant: Rushabh Dugad. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TREASURE TROVES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TREASURE TROVES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TREASURE TROVES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.