ReraGenieLog inGet a buyer report

Home / Browse projects / Udupi, Karnataka / TRANQUIL ABODE

Registration approved Residential/Group Housing project

TRANQUIL ABODE

By ANIKA ASSOCIATES

RG-KA-08105 · RERA PRM/KA/RERA/1273/318/PR/131224/007293 · Last updated on RERA Karnataka portal: Not stated

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2029Possession promisedno revision filed
0 of 14Construction stages donefurthest along: Earth work and other leveling..., 0%
Jump to the 10 documents Report an error

TRANQUIL ABODE is a Residential/Group Housing project by ANIKA ASSOCIATES in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/131224/007293 on 13 Dec 2024. Possession is promised by 31 Dec 2029.

At a glance

Project

  • NameTRANQUIL ABODE
  • TypeResidential/Group Housing
  • Location
    • Udupi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1273/318/PR/131224/007293
  • ReraGenie IDRG-KA-08105

Builder

  • NameANIKA ASSOCIATES
  • Entity typePartnership Firm
  • GSTIN29ABRFA2603H1ZE
  • Authorized SignatoryVINAYA KUMAR BHANDARY

Key dates

this monthRegisteredDec 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Dec 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed10 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRANQUIL ABODE---16016

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on Not stated, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 14 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 0%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on Not stated, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasYes-
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
AJITHA S SHETTY--
NANDISH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHALINI SURESH
EngineerNAGRAJ ACHARYA
Chartered AccountantMALTHESHA

Documents filed10

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/131224/007293 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Registration CertificateFile: firm regsiatrtion certificate.pdf-
Partnership DeedFile: partnership deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1 ca report.pdf-
Certificate issued by Architect Form 2File: architect certificate.pdf-
Certificate issued by Engineer Form 3File: engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-

How this compares with Udupi

22%of Udupi projects moved their completion datethis one has not
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep TRANQUIL ABODE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

Builder: ANIKA ASSOCIATES

ANIKA ASSOCIATES has 1 registration on RERA Karnataka, including TRANQUIL ABODE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if TRANQUIL ABODE is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of TRANQUIL ABODE?

The registered promoter entity is ANIKA ASSOCIATES, a partnership firm as per the filing. Its GSTIN 29ABRFA2603H1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in TRANQUIL ABODE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TRANQUIL ABODE?

The professionals named in the filing: Architect: SHALINI SURESH; Engineer: NAGRAJ ACHARYA; Chartered Accountant: MALTHESHA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRANQUIL ABODE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRANQUIL ABODE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRANQUIL ABODE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.