Home / Browse projects / Udupi, Karnataka / KIRTHI PALMVILLE PHASE II

Registration approved No litigation declared Residential/Group Housing project

KIRTHI PALMVILLE PHASE II

By KIRTHI CONSTRUCTION

RG-KA-17870 · RERA PRM/KA/RERA/1273/318/PR/210422/004842 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
5 of 16Construction stages donefurthest along: RCC or MS Framed structure, 80%
144 of 330Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 146 documents Report an error

KIRTHI PALMVILLE PHASE II is a Residential/Group Housing project by KIRTHI CONSTRUCTION in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/210422/004842 on 21 Apr 2022. Possession is promised by 31 Dec 2029. 186 of the 330 units on this registration are recorded sold or booked, and 5 of 16 construction stages are filed complete.

At a glance

Project

  • NameKIRTHI PALMVILLE PHASE II
  • TypeResidential/Group Housing
  • Location
    • Udupi
    • 576101
  • Pincode576101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1273/318/PR/210422/004842
  • ReraGenie IDRG-KA-17870

Builder

  • NameKIRTHI CONSTRUCTION
  • Entity typePartnership Firm
  • GSTIN29AAGFK6781Q1ZB
  • Authorized SignatorySUDHIR SHETTY
  • Other registrations2 more →
  • Past their filed date2
  • Declared earlier projects4 →

Key dates

this monthRegisteredApr 2022PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Apr 2022
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings4 building records
  • Documents filed146 files

Current status

56%186 of 330 units booked
33.8%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KIRTHI PALMVILLE-BLOCK B---1050105
KIRTHI PALMVILLE-BLOCK C---1060106
KIRTHI PALMVILLE-BLOCK D---1190119
INDOOR GAMES AND GYM---202

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 80%.

Building: 82% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure80%
Masonry Construction80%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)70%
Railing and Grill fixing70%
Electrification, Water supply and Sanitary Finishing70%
Painting70%
Fire prevention and fire fighting fitting and fixture with network70%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings70%

Progress on shared amenities40

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes80%
Energy managementYes80%
Fire protection and fire safety requirementsYes80%
Solid waste management and disposalYes80%
Emergency Evacuation servicesYes80%
Internal Roads & FootpathsYes80%
Electricity supply transformer and substationYes80%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes80%
Street LightingYes80%
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes80%
Corridor/LobbiesYes80%
Fire escapesYes80%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes80%
TerraceNoNot applicable
Outer WallYes80%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes80%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,515 sq m
Land owned byNot the promoter
Named landowners6
LandownerVillageDistrict
KIRTHI CONSTRUCTION--
KIRTHI CONSTRUCTION--
KIRTHI CONSTRUCTION--
KIRTHI CONSTRUCTION--
KIRTHI CONSTRUCTION--
KIRTHI CONSTRUCTION--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 140.00 cr
Cost incurredRs 47.36 cr
Spent of the estimate33.83%
BuildingWingEstimatedIncurred
-NARs 113.00 crRs 5.24 cr
-NARs 25.50 crRs 7.70 lakh
-NARs 1.50 cr-
-NA-Rs 6.60 lakh
-NA-Rs 41.98 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMANI HANDE
EngineerRAJENDRA MAIYA
Chartered AccountantSRINIDHI RAO

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed146

As listed on the registration, under the names the promoter filed them with; the newest 80 of 146 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/210422/004842 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 I.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Rera architect cert I.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Rera Engineer Cert I.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Labour and Education Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA form 4.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Labour and Education Department14 Apr 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: RERA Architecht Cert.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: RERA Engineers Cert.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Labour and Education Department15 Jan 2026
WATER NOCFile: WATER NOC.pdf8 Apr 2022
SELF ATTESTED WATER NOCFile: self attested water noc.pdf8 Apr 2022
TITLE SEARCH REPORTFile: search report.pdf8 Apr 2022
AFFIDAVIT ON FINAL HEARING NOTICEFile: affidavit.pdf8 Apr 2022
POLLUTION NOCFile: pollution noc.pdf8 Apr 2022
CLARIFICATIONFile: clarification.pdf8 Apr 2022
pollution nocFile: affidavith for pollution noc.pdf2 Mar 2022
Airport Authority NOC IS NOT APPLICABLE WITH ARCHITECT CERTIFICATE WITH LOCATIONFile: airport noc clarification.pdf2 Mar 2022
relinquishment deedFile: DANAPATRA.pdf2 Mar 2022
SEARCH REPORTFile: search report.pdf2 Mar 2022
SITE AND AIRPORT LOCATION DISTANCEFile: kirthi location distance to airport.jpg2 Mar 2022
CLARIFICATIONFile: clarification.pdf2 Mar 2022
RTC, survey 44/4-
Mutation, survey 44/4-
Encumbrance Certificate, survey 44/4-
Conversion/Alienation Order, survey 44/4-
Sale/Title/Gift Deed, survey 44/4-
Khatha, survey 44/4-
RTC, survey 44/5-
Mutation, survey 44/5-
Encumbrance Certificate, survey 44/5-
Conversion/Alienation Order, survey 44/5-
Sale/Title/Gift Deed, survey 44/5-
Khatha, survey 44/5-
RTC, survey 44/17-
Mutation, survey 44/17-
Encumbrance Certificate, survey 44/17-
Conversion/Alienation Order, survey 44/17-
Sale/Title/Gift Deed, survey 44/17-
Khatha, survey 44/17-
RTC, survey 45/4A2-
Mutation, survey 45/4A2-
Encumbrance Certificate, survey 45/4A2-
Conversion/Alienation Order, survey 45/4A2-
Sale/Title/Gift Deed, survey 45/4A2-
Khatha, survey 45/4A2-
RTC, survey 46/11-
Mutation, survey 46/11-
Encumbrance Certificate, survey 46/11-
Conversion/Alienation Order, survey 46/11-
Sale/Title/Gift Deed, survey 46/11-
Khatha, survey 46/11-
RTC, survey 44/6-
Mutation, survey 44/6-
Encumbrance Certificate, survey 44/6-
Conversion/Alienation Order, survey 44/6-
Sale/Title/Gift Deed, survey 44/6-
Khatha, survey 44/6-
Registration CertificateFile: PARTNERSHIP REG CERT.pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA CERTFICATE_compressed.pdf-
Certificate issued by Architect Form 2File: ARCHITECT'S CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: ENGINEER'S CERTIFICATE.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit litigation.pdf-
Certificate from Chartered AccountFile: approval certficate.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 20-21.pdf-
Balance Sheet 2019 - 2020File: BS 2019-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 18-19.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
KIRTHI PALMVILLE 1SHIRIBEEDU,UDUPIOngoingApr 2022Not delivered
ATHENAAJJARKAD,UDUPICompleted-Not delivered

How this compares with Udupi

56%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one has not
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep KIRTHI PALMVILLE PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

2 kmKIRTHI PALMVILLE PHASE IOther 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: KIRTHI CONSTRUCTION

KIRTHI CONSTRUCTION has 3 registrations on RERA Karnataka, including ATHENA and KIRTHI PALM VILLE-1. Its filings disclose 4 earlier RERA Karnataka projects, none completed yet. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if KIRTHI PALMVILLE PHASE II is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KIRTHI PALMVILLE PHASE II?

The registered promoter entity is KIRTHI CONSTRUCTION, a partnership firm as per the filing. Its GSTIN 29AAGFK6781Q1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KIRTHI PALMVILLE PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KIRTHI PALMVILLE PHASE II?

The professionals named in the filing: Architect: RAMANI HANDE; Engineer: RAJENDRA MAIYA; Chartered Accountant: SRINIDHI RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KIRTHI PALMVILLE PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KIRTHI PALMVILLE PHASE II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KIRTHI PALMVILLE PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.