Home / Browse projects / Thane, Maharashtra / THE WHITE VILLAS
THE WHITE VILLAS
By St. Angelo's VNCT Ventures Pvt. Ltd.
RG-MH-07609 · RERA P51700000038 · Last updated on MahaRERA portal: 3 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 70 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 2 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE WHITE VILLAS is a Residential / Group Housing project by St. Angelo's VNCT Ventures Pvt. Ltd. in Thane, Maharashtra, registered with MahaRERA as P51700000038 on 16 Jun 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 70 months from the original filing. 33 of the 43 units on this registration are recorded sold or booked, and 43 of 473 construction stages are filed complete.
At a glance
Project
- NameTHE WHITE VILLAS
- TypeResidential / Group Housing
- Location
- THANE
- Kalamgaon
- Shahapur
- 420601
- Pincode420601
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700000038
- ReraGenie IDRG-MH-07609
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Jun 2017
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 30 Jun 2021)
- Buildings43 building records
- Documents filed118 files
Current status
Figures as on 3 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ZEUS VILLA NO 1 | NA | 2 | 2 | 1 | 0 | 1 |
| ATLANTIS VILLA NO 2 | NA | 2 | 2 | 1 | 0 | 1 |
| APHRODITE VILLA NO 3 | NA | 2 | 2 | 1 | 0 | 1 |
| APOLLO VILLA NO 4 | NA | 2 | 2 | 1 | 0 | 1 |
| ARTEMIS VILLA NO 5 | NA | 2 | 2 | 1 | 0 | 1 |
| ASTRAEA VILLA NO 6 | NA | 2 | 2 | 1 | 0 | 1 |
| ATHENA VILLA NO 7 | NA | 2 | 2 | 1 | 0 | 1 |
| ATLAS VILLA NO 8 | NA | 2 | 2 | 1 | 0 | 1 |
| ATTIS VILLA NO 9 | NA | 2 | 2 | 1 | 0 | 1 |
| BIA VILLA NO 10 | NA | 2 | 2 | 1 | 0 | 1 |
| CASTOR VILLA NO 11 | NA | 2 | 2 | 1 | 0 | 1 |
| CERUS VILLA NO 12 | NA | 2 | 2 | 1 | 0 | 1 |
| KETO VILLA NO 13 | NA | 2 | 2 | 1 | 0 | 1 |
| CLIO VILLA NO 14 | NA | 2 | 2 | 1 | 0 | 1 |
| CRONUS VILLA NO 15 | NA | 2 | 2 | 1 | 0 | 1 |
| CYBELE VILLA NO 16 | NA | 2 | 2 | 1 | 0 | 1 |
| DEMETER VILLA NO 17 | NA | 2 | 2 | 1 | 0 | 1 |
| ELECTRA VILLA NO 18 | NA | 2 | 2 | 1 | 0 | 1 |
| EOS VILLA NO 19 | NA | 2 | 2 | 1 | 0 | 1 |
| ERATO VILLA NO 20 | NA | 2 | 2 | 1 | 0 | 1 |
| EROS VILLA NO 21 | NA | 2 | 2 | 1 | 0 | 1 |
| GAIA VILLA NO 22 | NA | 2 | 2 | 1 | 0 | 1 |
| HARMONIA VILLA NO 23 | NA | 2 | 2 | 1 | 0 | 1 |
| ZEPHYR VILLA NO 24 | NA | 2 | 2 | 1 | 0 | 1 |
| HELIOS VILLA NO 25 | NA | 2 | 2 | 1 | 0 | 1 |
| HEMERA VILLA NO 26 | NA | 2 | 2 | 1 | 0 | 1 |
| HERA VILLA NO 27 | NA | 2 | 2 | 1 | 0 | 1 |
| URANIA VILLA NO 28 | NA | 2 | 2 | 1 | 0 | 1 |
| HERMES VILLA NO 29 | NA | 2 | 2 | 1 | 0 | 1 |
| HESPERUS VILLA NO 30 | NA | 2 | 2 | 1 | 0 | 1 |
| TRITON VILLA NO 31 | NA | 2 | 2 | 1 | 0 | 1 |
| IRIS VILLA NO 33 | NA | 2 | 2 | 1 | 0 | 1 |
| KRATOS VILLA NO 34 | NA | 2 | 2 | 1 | 0 | 1 |
| MAIA VILLA NO 35 | NA | 2 | 2 | 1 | 0 | 1 |
| METIS VILLA NO 36 | NA | 2 | 2 | 1 | 0 | 1 |
| THALIA VILLA NO 37 | NA | 2 | 2 | 1 | 0 | 1 |
| NYX VILLA NO 38 | NA | 2 | 2 | 1 | 0 | 1 |
| OCEANUS VILLA NO 39 | NA | 2 | 2 | 1 | 0 | 1 |
| PHEME VILLA NO 40 | NA | 2 | 2 | 1 | 0 | 1 |
| PLUTUS VILLA NO 41 | NA | 2 | 2 | 1 | 0 | 1 |
| RHEA VILLA NO 42 | NA | 2 | 2 | 1 | 0 | 1 |
| SELENE VILLA NO 43 | NA | 2 | 2 | 1 | 0 | 1 |
| STYX VILLA NO 44 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 43 buildings; the table lists the first 20.
43 of 473 construction stages are filed complete across 43 buildings. The stage furthest along is Excavation, at 80%.
ZEUS VILLA NO 160%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ATLANTIS VILLA NO 260%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
APHRODITE VILLA NO 360%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
APOLLO VILLA NO 460%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ARTEMIS VILLA NO 560%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ASTRAEA VILLA NO 660%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ATHENA VILLA NO 760%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ATLAS VILLA NO 860%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ATTIS VILLA NO 960%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BIA VILLA NO 1060%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CASTOR VILLA NO 1160%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CERUS VILLA NO 1260%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
KETO VILLA NO 1360%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CLIO VILLA NO 1460%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CRONUS VILLA NO 1560%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CYBELE VILLA NO 1660%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
DEMETER VILLA NO 1760%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ELECTRA VILLA NO 1860%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
EOS VILLA NO 1960%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
ERATO VILLA NO 2060%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 30.22 cr | Rs 30.19 cr |
| ZEUS VILLA NO 1 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ATLANTIS VILLA NO 2 | NA | Rs 3.32 cr | Rs 3.31 cr |
| APHRODITE VILLA NO 3 | NA | Rs 3.32 cr | Rs 3.31 cr |
| APOLLO VILLA NO 4 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ARTEMIS VILLA NO 5 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ASTRAEA VILLA NO 6 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ATHENA VILLA NO 7 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ATLAS VILLA NO 8 | NA | Rs 3.32 cr | Rs 3.31 cr |
| ATTIS VILLA NO 9 | NA | Rs 3.32 cr | Rs 3.31 cr |
| BIA VILLA NO 10 | NA | Rs 3.32 cr | Rs 3.31 cr |
| CASTOR VILLA NO 11 | NA | Rs 3.32 cr | Rs 3.31 cr |
Certifying professionals and partners10
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TANGENT ARCHITECTS |
| Architect | TANGENT ARCHITECT |
| Engineer | AECON PROJECT |
| Engineer | ATUL SHAH |
| Engineer | B SQUARE CONSTRUCTION |
| Engineer | TANGENT ARCHITECTS |
| Chartered Accountant | Puneet Singhvi & Associates |
| Chartered Accountant | kiran vora |
| Chartered Accountant | NEHALI DHAVAL DOSHI |
| Chartered Accountant | NEHALI AND CO |
| Partner | Role in project |
|---|---|
| St. Angelo's VNCT Ventures Pvt. Ltd. | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid 19 the project was not able to get completed in time. We would like to request you to further grant us extension for 12 month.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023
Reason as filed by the promoterDUE TO COVID 19 NOT ABLE TO COMPLETE PROJECT PLEASE GRANT US EXTENSION TILL 31/12/2026
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Feb 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2027
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Form 5 Shahapur (CA certificate).pdf | 3 Sep 2026 |
| Form 2A (FY 2025-2026)File: form 2A (engineer certificate) Shahapur.pdf | 19 Aug 2026 |
| Withdrawal Update Form 1File: form 1 (architect certificate) Shahapur 15072026.PDF | 20 Jul 2026 |
| Withdrawal Update Form 2File: form 2 (engineer certificate) Shahapur- 15072026.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: form 1.PDF | 26 May 2026 |
| Withdrawal Update Form 2File: form 2.PDF | 26 May 2026 |
| Withdrawal Update Form 3File: Resigned CA.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: form 1.PDF | 11 Feb 2026 |
| Withdrawal Update Form 2File: form 2.PDF | 11 Feb 2026 |
| Withdrawal Update Form 3File: form 3.pdf | 11 Feb 2026 |
| Withdrawal Update Form 1File: form 1 (architect certificate) Shahapur.PDF | 13 Nov 2025 |
| Withdrawal Update Form 2File: form 2 (engineer certificate) Shahapur.PDF | 13 Nov 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate - Shahpur sept25 (1) (1).pdf | 13 Nov 2025 |
| Withdrawal Update Form 1File: Shahpur Form 1 Q1.PDF | 14 Oct 2025 |
| Withdrawal Update Form 2File: Shahapur Form 2 Q1.PDF | 14 Oct 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate - Kasara 1 june25.pdf | 14 Oct 2025 |
| Form 2A (FY 2024-2025)File: form 2A (engineer certificate) Shahapur Scan copy FY 2024-25.PDF | 16 Sep 2025 |
| Withdrawal Update Form 1File: Shahpur Form 1 Q1.PDF | 4 Sep 2025 |
| Withdrawal Update Form 2File: Shahapur Form 2 Q1.PDF | 4 Sep 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate - Kasara 1 june25.pdf | 4 Sep 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.PDF | 27 May 2024 |
| Certificates of CA (Form 3)File: FORM 3.PDF | 27 May 2024 |
| CERSAI detailsFile: Cersai dec.PDF | 16 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Shahpur Form A.pdf | 16 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.PDF | 26 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 06.PDF | 26 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.PDF | 26 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 09 22.PDF | 26 Dec 2023 |
| Certificates of CA (Form 3)File: Form 3 03.PDF | 26 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.PDF | 26 Dec 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate - Shahpur Sept'22.pdf | 1 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahshpur Ar certificate.pdf | 5 May 2022 |
| Certificates of CA (Form 3)File: Signed CA Certificate - Shahpur New Format.pdf | 29 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 (2).pdf | 12 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 12 Jan 2022 |
| Certificates of CA (Form 3)File: FORM 3.PDF | 12 Jan 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Shahapur_compressed (1).pdf | 25 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: fORM 2 Shahapur_compressed.pdf | 25 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21 Shahapur.pdf | 12 Oct 2021 |
| Certificates of CA (Form 3)File: signed CA Certificate SHAHPUR WHITE VILLA.pdf | 4 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A SHAHPUR.pdf | 4 Sep 2021 |
| Certificates of CA (Form 3)File: signed CA Certificate SHAHPUR jun'21.pdf | 23 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order Copy (1).pdf | 13 Jul 2021 |
| Declaration about Commencement CertificateFile: Decla Letter_Promotor_Land Bearing Gut No 420(1).PDF | 12 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SITE SUPERVISOR CERTIFICATE 20-21.pdf | 12 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate FORM 2.pdf | 10 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SITE SUPERVISOR CERTIFICATE 20-21.pdf | 10 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory_Shahapur.PDF | 10 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - Shahpur 18-19.pdf | 10 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - Shahpur 19-20.pdf | 10 Jul 2021 |
| Certificates of CA (Form 3)File: THE WHITE VILLAS.pdf | 22 Apr 2021 |
| Certificates of CA (Form 3)File: signed Ca certificate shahpur.pdf | 3 Mar 2021 |
| Certificates of CA (Form 3)File: REVISED SIGNED CERTIFICATE SHAHPUR.pdf | 18 Feb 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH THE WHITE VILLAS_compressed.pdf | 15 Oct 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SHAHPUR RERA.pdf | 10 Sep 2020 |
| Certificates of CA (Form 3)File: SAHAPUR.pdf | 26 Jul 2019 |
| Layout approvalFile: LAYOUT PLAN.pdf | 19 Feb 2019 |
| Building plan approvalFile: IOD.pdf | 19 Feb 2019 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.pdf | 19 Feb 2019 |
| Building Plan Approval (IOD)File: IOD.pdf | 19 Feb 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf | 19 Feb 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate comp.pdf | 19 Feb 2019 |
| Form 2AFile: site supervisior certificate.pdf | 19 Feb 2019 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 19 Feb 2019 |
| Certificates of CA (Form 5)File: ashwin form 5.PDF | 15 Oct 2018 |
| Layout approvalFile: Scan1.PDF | 13 Jun 2017 |
| Layout approvalFile: 1 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: layout plan sanction letter (764).pdf | 13 Jun 2017 |
| Layout approvalFile: 2 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: layout plan sanction letter (383).pdf | 13 Jun 2017 |
| Layout approvalFile: 3 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: 4 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: 5 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: 6 Copy of Layout.pdf | 13 Jun 2017 |
| Layout approvalFile: 7 Copy of Layout.pdf | 13 Jun 2017 |
| Building plan approvalFile: Scan10001.PDF | 13 Jun 2017 |
| Building plan approvalFile: 1 Copy of Layout.pdf | 13 Jun 2017 |
| Building plan approvalFile: layout plan sanction letter (764).pdf | 13 Jun 2017 |
| Building plan approvalFile: 2 Copy of Layout.pdf | 13 Jun 2017 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| THE WHITE VILLAS KASARA | NEAR WASHALA PHATA ADJ TO NHAI OFFICE NH3 MUMBAI NASHIK HIGHWAY | 20 | Completed | Dec 2020 | Dec 2020 |
| THE WHITE VILLAS | THE WHITE VILLAS VILLAGE KALAM NEAR ATGAON STATION TALUKA SHAHAPUR BEHIND MIDWAY PARK RESORT KALAMGAON MAHARASHTRA 420601. | 43 | Completed | Dec 2020 | Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep THE WHITE VILLAS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near THANE7,600+ in Thane
Filed coordinates, straight-line distance. 55 registered projects within 2 km.
CHADHA RESIDENCY
CHADHA DEVELOPERS AND PROMOTERS
Plot No -1A,Sector -19, Vashi Truck Terminal
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
GODREJ UPAVAN
PRAKHHYAT DWELLINGS LLP
Constrcution of 2557 EWS tenements at S.No.157
ARUN SHANKARRAO BORGAVE
PRADHAN MANTRI AWAS YOJANA - URBAN
KULGAON BADLAPUR MUNICIPAL COUNCIL
Runwal Gardens Phase I
Runwal Residency Private Limited
See every Thane project, with the district possession charts
Builder: St. Angelo's VNCT Ventures Pvt. Ltd.
St. Angelo's VNCT Ventures Pvt. Ltd. has 3 registrations on MahaRERA, including THE WHITE VILLAS and THE WHITE VILLAS KASARA. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if THE WHITE VILLAS is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE WHITE VILLAS?
The registered promoter entity is St. Angelo's VNCT Ventures Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE WHITE VILLAS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE WHITE VILLAS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE WHITE VILLAS?
The professionals named in the filing: Architect: TANGENT ARCHITECTS; Architect: TANGENT ARCHITECT; Engineer: AECON PROJECT; Engineer: ATUL SHAH; Engineer: B SQUARE CONSTRUCTION; Engineer: TANGENT ARCHITECTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE WHITE VILLAS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback