ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / THE VELVET

Registered Litigation declared Residential / Group Housing project

THE VELVET

By KAMALKUMAR SATYANARAYAN AGRAWAL

RG-MH-18742 · RERA P50500077551 · Last updated on MahaRERA portal: 12 Apr 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 75%
38 of 42Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

THE VELVET is a Residential / Group Housing project by KAMALKUMAR SATYANARAYAN AGRAWAL in Nagpur, Maharashtra, registered with MahaRERA as P50500077551 on 10 Oct 2024. Possession is promised by 31 Dec 2027. 4 of the 42 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTHE VELVET
  • TypeResidential / Group Housing
  • Location
    • RAMKRISHNA HOUSING SOCIETY MOUZA SOMALWADA NEAR VASUNDHARA ENCLAVE
    • NARENDRA NAGAR
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440025
  • Pincode440025
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500077551
  • ReraGenie IDRG-MH-18742

Builder

  • NameKAMALKUMAR SATYANARAYAN AGRAWAL
  • Entity typeIndividual

Key dates

this monthRegisteredOct 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Oct 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed169 files

Current status

10%4 of 42 units booked
28.9%Work done, per cost certificate

Figures as on 12 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE VELVETNA8742042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 75%.

THE VELVET: 36% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Closed/Covered66

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,765 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Aug 2025

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION
Permissible FSI4854.0
Proposed, not sanctioned4,854 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 9, RAMKRISHNA NAGAR, AJNI SQUARE, WARDHA ROAD, NAGPUR ,NAGPUR ,MAHARASHTRA PIN 440015
Estimated costRs 15.22 cr
Cost incurredRs 4.40 cr
Work done28.91%
BuildingWingEstimatedIncurred
THE VELVETNARs 15.22 crRs 4.40 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEMANATE DESIGN
EngineerAAJ ENGINEERS AND CONSULTANTS PVT. LTD.
EngineerSumed P Patil
Chartered AccountantASHISH LAXMINARAYAN AGARWAL
Chartered AccountantSUMIT CHANDWANI
PartnerRole in project
KAMALKUMAR SATYANARAYAN AGRAWAL-

Litigation declared1

CaseCourtStatus
7221/2023/2023CIVIL COURTCOMPLIANCE

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12401252Naman Ashok TrivediKAMALKUMAR SATYANARAYAN AGRAWAL27/12/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect certificate Dec 25.pdf12 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 26.pdf12 Apr 2026
Withdrawal Update Form 3File: CA Certificate Velvet March 26.pdf12 Apr 2026
Withdrawal Update Form 1File: Architect certificate Dec 25.pdf20 Jan 2026
Withdrawal Update Form 2File: Engineer certificate Dec 25.pdf20 Jan 2026
Withdrawal Update Form 3File: CA Certificate -Velvet Dec 25.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 Architect certificate Sept 25.pdf11 Oct 2025
Withdrawal Update Form 2File: From 2 Engineer Certificate Sept 25.pdf11 Oct 2025
Withdrawal Update Form 3File: CA CERTIFICATE The Velvet - Sept 25.pdf11 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: FORM 5 FY 24-25_VELVET.pdf22 Sep 2025
Withdrawal Update Form 1File: Final Architect Certificate.pdf21 Aug 2025
Withdrawal Update Form 2File: Final Aaj Enginering (Kamal Agarwal) (1).pdf21 Aug 2025
Withdrawal Update Form 3File: Final CA Certificate June 25 The Velvet.pdf21 Aug 2025
Form 3File: Form 3.pdf16 Jul 2025
Form 1File: Form 1.pdf16 Jul 2025
Form 2File: Form 2.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Booked Inventory.pdf16 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer cert mar 25.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD BOOK.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect cert signed.pdf13 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Mar25 The Velvet-3.pdf2 Apr 2025
Declaration in FORM BFile: form b.pdf1 Apr 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format a.pdf1 Apr 2025
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBRANCE.pdf31 Mar 2025
Details of encumbrances concerned to LegalFile: FINANCIAL ENCUMBRANCE.pdf31 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: format b.pdf29 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: disclosure of secured finance.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Form 1 - The velvet - Dec 24.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 - The velvet - Dec 24.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Form 2 - The velvet - Dec 24.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: 4 Sold Booked Inv - The velvet - Dec 24.pdf20 Jan 2025
Other - LegalFile: AGREEMENT TO SELL-RERA -THE VELVET KAMAL AGRAWAL SAMPLE 2024.pdf8 Oct 2024
Other - LegalFile: ALLOTMENT LETTER KAMAL AGRAWAL SOMALWADA SAMPLE 2024 RERA FORMAT.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Agreement for Sale.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Allotment Letter.pdf8 Oct 2024
Other - LegalFile: TITLE Search Report Rera - The Velvet_compressed.pdf8 Oct 2024
Other - FinanceFile: Form 3 - The Velvet.pdf8 Oct 2024
Other - FinanceFile: Financial Encumbrance.pdf8 Oct 2024
Other - TechnicalFile: Annexure A - Disclosure of Interest - Velvet Infra.pdf8 Oct 2024
Other - LegalFile: AGREEMENT TO SELL-RERA -THE VELVET KAMAL AGRAWAL SAMPLE 2024.pdf8 Oct 2024
Other - LegalFile: ALLOTMENT LETTER KAMAL AGRAWAL SOMALWADA SAMPLE 2024 RERA FORMAT.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Agreement for Sale.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Allotment Letter.pdf8 Oct 2024
Other - LegalFile: TITLE Search Report Rera - The Velvet_compressed.pdf8 Oct 2024
Other - FinanceFile: Form 3 - The Velvet.pdf8 Oct 2024
Other - FinanceFile: Financial Encumbrance.pdf8 Oct 2024
Other - TechnicalFile: Annexure A - Disclosure of Interest - Velvet Infra.pdf8 Oct 2024
Other - LegalFile: AGREEMENT TO SELL-RERA -THE VELVET KAMAL AGRAWAL SAMPLE 2024.pdf8 Oct 2024
Other - LegalFile: ALLOTMENT LETTER KAMAL AGRAWAL SOMALWADA SAMPLE 2024 RERA FORMAT.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Agreement for Sale.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Allotment Letter.pdf8 Oct 2024
Other - LegalFile: TITLE Search Report Rera - The Velvet_compressed.pdf8 Oct 2024
Other - FinanceFile: Form 3 - The Velvet.pdf8 Oct 2024
Other - FinanceFile: Financial Encumbrance.pdf8 Oct 2024
Other - TechnicalFile: Annexure A - Disclosure of Interest - Velvet Infra.pdf8 Oct 2024
Other - LegalFile: AGREEMENT TO SELL-RERA -THE VELVET KAMAL AGRAWAL SAMPLE 2024.pdf8 Oct 2024
Other - LegalFile: ALLOTMENT LETTER KAMAL AGRAWAL SOMALWADA SAMPLE 2024 RERA FORMAT.pdf8 Oct 2024
Other - TechnicalFile: Annexure A - Disclosure of Interest - Velvet Infra.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Agreement for Sale.pdf8 Oct 2024
Other - LegalFile: Declaration About Deviation in Allotment Letter.pdf8 Oct 2024
Other - FinanceFile: Financial Encumbrance.pdf8 Oct 2024
Other - FinanceFile: Form 3 - The Velvet.pdf8 Oct 2024
Other - LegalFile: TITLE Search Report Rera - The Velvet_compressed.pdf8 Oct 2024
Other - FinanceFile: Format A - The Velvet.pdf13 Aug 2024
Other - TechnicalFile: Format A - The Velvet.pdf13 Aug 2024
Other - FinanceFile: Format A - The Velvet.pdf13 Aug 2024
Other - TechnicalFile: Format A - The Velvet.pdf13 Aug 2024
Other - FinanceFile: Format A - The Velvet.pdf13 Aug 2024
Other - TechnicalFile: Format A - The Velvet.pdf13 Aug 2024
Building plan approvalFile: PLAN 2.pdf22 Jul 2024
Layout approvalFile: PLAN 2.pdf22 Jul 2024
Building plan approvalFile: PLAN 2.pdf22 Jul 2024
Layout approvalFile: PLAN 2.pdf22 Jul 2024
Building plan approvalFile: PLAN 2.pdf22 Jul 2024
Layout approvalFile: PLAN 2.pdf22 Jul 2024
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf22 Jul 2024
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf22 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf22 Jul 2024
Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf22 Jul 2024

How this compares with Nagpur

10%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE VELVET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NARENDRA NAGAR2,800+ in Nagpur

2 kmTHE VELVETCompleted 32Lapsed / revoked 14Other 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 101 registered projects within 2 km.

Builder: KAMALKUMAR SATYANARAYAN AGRAWAL

KAMALKUMAR SATYANARAYAN AGRAWAL has 1 registration on MahaRERA, including THE VELVET. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if THE VELVET is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE VELVET?

The registered promoter entity is KAMALKUMAR SATYANARAYAN AGRAWAL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE VELVET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE VELVET?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE VELVET?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE VELVET?

The professionals named in the filing: Architect: EMANATE DESIGN; Engineer: AAJ ENGINEERS AND CONSULTANTS PVT. LTD.; Engineer: Sumed P Patil; Chartered Accountant: ASHISH LAXMINARAYAN AGARWAL; Chartered Accountant: SUMIT CHANDWANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE VELVET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE VELVET. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE VELVET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.