ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / The Terraces Phase 2

Completed No litigation declared Residential / Group Housing project

The Terraces Phase 2

By Rashmi Commercial Company Limited

RG-MH-11934 · RERA P52100004039 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 98%
6 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 136 documents Report an error

The Terraces Phase 2 is a Residential / Group Housing project by Rashmi Commercial Company Limited in Pune, Maharashtra, registered with MahaRERA as P52100004039 on 7 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2026. 14 of the 20 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameThe Terraces Phase 2
  • TypeResidential / Group Housing
  • Location
    • Balewadi
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004039
  • ReraGenie IDRG-MH-11934

Builder

  • NameRashmi Commercial Company Limited
  • Entity typeCompany
  • DirectorAmit Almal
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed136 files

Current status

70%14 of 20 units booked
69.0%Work done, per cost certificate

Figures as on 24 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Terraces Phase 2 / Wing BNA131120020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

The Terraces Phase 2 / Wing B: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes95%
Street LightingYes75%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered40

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI4585.9
Proposed, not sanctioned4,586 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMillenium Star Dhole Patil Road Pune 411001
Estimated costRs 26.48 cr
Cost incurredRs 18.27 cr
Work done68.98%
BuildingWingEstimatedIncurred
The Terraces Phase 2 / Wing BNARs 20.99 crRs 15.14 cr
-NARs 5.49 crRs 3.12 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVikas Bhandari
EngineerVishwanath Yadawad
Chartered AccountantSharad Shah & CO
Chartered AccountantA C Bhuteria & Co
PartnerRole in project
Rashmi Commercial Company Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jun 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed136

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 136 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Occupancy Certificate.pdf24 Jun 2026
Layout approvalFile: Marked Layout.pdf18 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf1 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf1 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf1 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf1 Jun 2026
Withdrawal Update Form 3File: Form 3.pdf1 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 (2024-2025).pdf2 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf21 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf21 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf21 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf18 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf18 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf18 Jul 2025
Form 1File: Form 1.pdf16 Jul 2025
Form 2File: Form 2.pdf16 Jul 2025
Form 3File: Form 3.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory.pdf16 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2025
Withdrawal Update Form 1File: Form 1.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf16 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf16 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf16 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf16 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf16 Jul 2025
Withdrawal Update Form 3File: Form 3.pdf16 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf17 Apr 2025
Certificates of CA (Form 3)File: Form 3.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf12 Feb 2025
Certificates of CA (Form 3)File: Form 3.pdf12 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf12 Feb 2025
Disclosure of sold/ booked inventoryFile: 2025 01 16-RCCL-Disclosure of Sold or Booked Inventory TT Phase 2.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 (2023-2024).pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2024.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - Jun 2024.pdf16 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf19 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2023.pdf6 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2023.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2023.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf31 Jul 2023
Proforma of Agreement for saleFile: Draft Agreement.pdf20 Mar 2023
Layout approvalFile: Layout.pdf16 Mar 2023
Building plan approvalFile: Plan 1.pdf16 Mar 2023
Building plan approvalFile: Plan 2.pdf16 Mar 2023
Building plan approvalFile: Plan 3.pdf16 Mar 2023
Building plan approvalFile: Plan 4.pdf16 Mar 2023
Building plan approvalFile: Plan 5.pdf16 Mar 2023
Building plan approvalFile: Plan 6.pdf16 Mar 2023
Copy of Layout Approval (in case of layout)File: Layout.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 1.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 2.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 3.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 4.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 5.pdf16 Mar 2023
Building Plan Approval (IOD)File: Plan 6.pdf16 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf16 Mar 2023
Declaration about Commencement CertificateFile: Format D.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: G - 2023 03 15 - Disclosure of Inventory.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - January 2023.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf22 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 4 Certificates of CA (Form 5).pdf22 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf22 Nov 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
The Terraces Phase 1Balewadi Pune 41104510CompletedSep 2012Late, Mar 2015

How this compares with Pune

70%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Terraces Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Balewadi13,700+ in Pune

2 kmThe Terraces Phase 2Completed 127Lapsed / revoked 46Other 121Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: Rashmi Commercial Company Limited

Rashmi Commercial Company Limited has 1 registration on MahaRERA, including The Terraces Phase 2. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if The Terraces Phase 2 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Terraces Phase 2?

The registered promoter entity is Rashmi Commercial Company Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Terraces Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Terraces Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Terraces Phase 2?

The professionals named in the filing: Architect: Vikas Bhandari; Engineer: Vishwanath Yadawad; Chartered Accountant: Sharad Shah & CO; Chartered Accountant: A C Bhuteria & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Terraces Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Terraces Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Terraces Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.