THE SERAI PHASE - 1
RG-MH-86336 · RERA P51900007804 · Last updated on MahaRERA portal: 22 Mar 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE SERAI PHASE - 1 is a Others project by KATHAWALA REALTORS LLP in 400008, registered with MahaRERA as P51900007804 on 18 Aug 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 18 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameTHE SERAI PHASE - 1
- TypeOthers
- Location
- 400008
- Pincode400008
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900007804
- ReraGenie IDRG-MH-86336
Builder
- NameKATHAWALA REALTORS LLP
- Entity typePartnership
- PartnersZUZAR AHMEDALLY KATHAWALA, HASHIM HATIM KATHAWALA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 Aug 2017
- Promised completion29 Dec 2024
- Revised completionRevised to 29 Dec 2024 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed77 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| The Serai Phase-1 | NA | 28 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 60%.
The Serai Phase-1: 13% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 60% |
| Basement (if any) | 40% |
| Podiums (if any) | 0% |
| Plinth | 40% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities19
As on 22 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 5% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Herb Garden | Yes | 0% |
| Fitness Centre | Yes | 0% |
| Children Play Ground | Yes | 0% |
| Banquet Room | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AAKAR ARCHITECTS AND CONSULTANTS |
| Engineer | MAHIMTURA CONSULTANTS PVT LTD |
| Partner | Role in project |
|---|---|
| KATHAWALA REALTORS LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid - 19 pandemic, the construction pace and the sales of the projects has been hampered. Seeing the current scenario, we feel the need to extend the timeline previously mentioned by one year. The previously mentioned date was 30th June 2023. Now, we hereby request you you to kindly extend the project timeline to 29th June 2024. Also, we request you to kindly generate the new certificate with revised timeline.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000591596 | Masud Shaikh | Kathawala Realtors LLP | 20/08/2024 |
| CC12400771 | Shabnam Saleh Mohammed Merchant | KATHAWALA REALTORS LLP | 14/11/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed77
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 5)File: Form 5 - The Serai Phase 1 for FY 2017-18.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - The Serai Phase 1 for FY 2018-19.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - The Serai Phase 1 for FY 2019-20.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - The Serai Phase 1 for FY 2020-21.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - The Serai Phase 1 for FY 2021-22.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - The Serai Phase 1 for FY 2022-23.pdf | 22 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Certificates of CA (Form 5).pdf | 14 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 The Serai Phase -I as on September 2022.pdf | 27 Oct 2022 |
| Certificates of CA (Form 3)File: Form 3 as on September 2022.pdf | 27 Oct 2022 |
| Certificates of CA (Form 3)File: Form 3 as on September 2022.pdf | 27 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: The Serai Phase-1 FY 2021-22.pdf | 1 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: The Serai Phase 1 - Form 2 - June 2022.pdf | 25 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3 Serai Phase 1 June 22.pdf | 25 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: The Serai Phase 1 - Form 2 - 31_03_2022.pdf | 10 May 2022 |
| CERSAI detailsFile: The Serai.pdf | 10 May 2022 |
| Certificates of CA (Form 3)File: Form 3 Serai Phase 1 31st March 2022.pdf | 10 May 2022 |
| Layout approvalFile: The Serai Plan Page 1 of 1.pdf | 18 Feb 2022 |
| Building plan approvalFile: plan page 1A, 2 and 3.pdf | 18 Feb 2022 |
| Building plan approvalFile: plan the serai phase 3A and 4.pdf | 18 Feb 2022 |
| Building plan approvalFile: plan the serai phase page 5.pdf | 18 Feb 2022 |
| Building plan approvalFile: plan the serai phase 6_compressed.pdf | 18 Feb 2022 |
| Building plan approvalFile: plan the serai phase 7 and 8.pdf | 18 Feb 2022 |
| Building plan approvalFile: the serai page 9 and 10.pdf | 18 Feb 2022 |
| Building plan approvalFile: the serai page 11 and 12.pdf | 18 Feb 2022 |
| Building plan approvalFile: the serai 13 and 14.pdf | 18 Feb 2022 |
| Copy of Layout Approval (in case of layout)File: The Serai Plan Page 1 of 1.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: plan page 1A, 2 and 3.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: plan the serai phase 3A and 4.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: plan the serai phase page 5.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: plan the serai phase 6_compressed.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: plan the serai phase 7 and 8.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: the serai page 9 and 10.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: the serai page 11 and 12.pdf | 18 Feb 2022 |
| Building Plan Approval (IOD)File: the serai 13 and 14.pdf | 18 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 2307922Amendletter_signed (1).pdf | 18 Feb 2022 |
| Declaration about Commencement CertificateFile: form d (1).pdf | 18 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC REVALIDATION DEC-22.pdf | 15 Feb 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 The Serai Phase 1 Dec 2021.pdf | 25 Jan 2022 |
| Certificates of CA (Form 3)File: Form 3 Certificate 254.pdf | 25 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 The Serai Pase I Sept 2021.pdf | 30 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20-21 The Serai Phase-1.pdf | 30 Oct 2021 |
| Certificates of CA (Form 3)File: Form 3 Certificate 206.pdf | 27 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Further Cc.pdf | 2 Sep 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Document 36_compressed.pdf | 2 Sep 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ilovepdf_merged (28)_compressed.pdf | 12 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 The Serai Phase-1 Mar 2021.pdf | 5 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 The Serai Phase-1 Jun 2021.pdf | 5 Aug 2021 |
| Certificates of CA (Form 3)File: Form 3 The Serai Phase-1 Mar 2021.pdf | 5 Aug 2021 |
| Certificates of CA (Form 3)File: Form 3 The Serai Phase-1 Jun 2021.pdf | 5 Aug 2021 |
| Certificates of CA (Form 3)File: Form 3 Dec 2020 The Serai Phase-I.pdf | 22 Feb 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KATHWALA FORM 2 SEPT 2020.pdf | 4 Nov 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KATHWALA FORM 2 JUNE 2020.pdf | 4 Nov 2020 |
| Certificates of CA (Form 3)File: Form 3 The Serai Phase-1 June 2020.pdf | 4 Nov 2020 |
| Certificates of CA (Form 3)File: Form 3 The Serai Phase-1 September 2020.pdf | 4 Nov 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 The Serai Phase-1 FY 2019-20.pdf | 4 Nov 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31st Mar 2020-The Serai Phase-I.pdf | 13 Aug 2020 |
| Certificates of CA (Form 3)File: Form 3 31st March 2020 - The Serai Phase-I.pdf | 13 Aug 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2 The Serai Phase 1.pdf | 22 Jan 2020 |
| Certificates of CA (Form 3)File: Form 3 The Serai Phase-I.pdf | 22 Jan 2020 |
| Certificates of CA (Form 5)File: Audit 18-19.pdf | 29 May 2019 |
| Layout approvalFile: Plan_Layout.pdf | 12 Aug 2017 |
| Building plan approvalFile: IOD min.pdf | 12 Aug 2017 |
| PAN CardFile: PAN_new.pdf | 12 Aug 2017 |
| Copy of the legal title reportFile: Title_Certificate.pdf | 12 Aug 2017 |
| Details of encumbrancesFile: encumbrance letter.pdf | 12 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: Plan_Layout.pdf | 12 Aug 2017 |
| Building Plan Approval (IOD)File: IOD min.pdf | 12 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 12 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc revalidation letter.pdf | 12 Aug 2017 |
| Declaration in FORM BFile: Form B.pdf | 12 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-1-2 COMP.pdf | 12 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-3-3.pdf | 12 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate-new.pdf | 12 Aug 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE KATHAWALA 1 4.pdf | 12 Aug 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE KATHAWALA compressed.pdf | 12 Aug 2017 |
| Proforma of Allotment letterFile: Kathawala Draft Agrement rera.pdf | 12 Aug 2017 |
| Proforma of Allotment letterFile: Draft Kathawala Allotment.pdf | 12 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 77 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep THE SERAI PHASE - 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near this project
Filed coordinates, straight-line distance. 59 registered projects within 2 km.
FATIMA HEIGHTS
M K ENTERPRISES
Nexsa Sky Vista
D.K. REALTORS & DEVELOPERS LIMITED
Lakadawala Garden
M/s. Lakadawala Developers Pvt. Ltd.
La Mer Residences
EXCELLENT REALTOR DEVELOPERS
Godrej Avenue Eleven - Tower A
GODREJ RESIDENCY PRIVATE LIMITED
FUEGO
HILTON INFRASTRUCTURE
Builder: KATHAWALA REALTORS LLP
KATHAWALA REALTORS LLP has 1 registration on MahaRERA, including THE SERAI PHASE - 1. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that THE SERAI PHASE - 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if THE SERAI PHASE - 1 is delayed beyond 29 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE SERAI PHASE - 1?
The registered promoter entity is KATHAWALA REALTORS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE SERAI PHASE - 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against THE SERAI PHASE - 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for THE SERAI PHASE - 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE SERAI PHASE - 1?
The professionals named in the filing: Architect: AAKAR ARCHITECTS AND CONSULTANTS; Engineer: MAHIMTURA CONSULTANTS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE SERAI PHASE - 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback