Home / Browse projects / Pune, Maharashtra / The Rivolo Residences at Forest Trails

Registered Litigation declared Residential / Group Housing project

The Rivolo Residences at Forest Trails

By PARANJAPE SCHEMES (CONSTRUCTION) LTD

RG-MH-22483 · RERA P52100031560 · Last updated on MahaRERA portal: 6 Mar 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
89 of 341Construction stages doneacross 31 buildings; furthest along: Excavation, 95%
8 of 31Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

The Rivolo Residences at Forest Trails is a Residential / Group Housing project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Pune, Maharashtra, registered with MahaRERA as P52100031560 on 31 Oct 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 23 of the 31 units on this registration are recorded sold or booked, and 89 of 341 construction stages are filed complete.

At a glance

Project

  • NameThe Rivolo Residences at Forest Trails
  • TypeResidential / Group Housing
  • Location
    • Paud Road
    • Bhugaon
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • RERA no.P52100031560
  • ReraGenie IDRG-MH-22483

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LTD
  • Entity typeCompany
  • ChairpersonSHRIKANT PURUSHOTTAM PARANJAPE
  • Managing DirectorSHASHANK PURUSHOTTAM PARANJAPE
  • Other registrations28 more →
  • Completed15 of 29
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

this monthRegisteredOct 2021First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Oct 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings31 building records
  • Documents filed87 files

Current status

74%23 of 31 units booked
50.4%Work done, per cost certificate

Figures as on 6 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Viila 1NA22101
Viila 2NA22101
Villa 3NA22101
Villa 4NA22101
Villa 5NA22101
Villa 6NA33101
Villa 7NA33101
Villa 8NA33101
Villa 9NA33101
Villa 10NA33101
Villa 11NA33101
Villa 12NA33101
Villa 13NA33101
Villa 14NA33101
Villa 15NA33101
Villa 16NA33101
Villa 17NA33101
Villa 18NA33101
Villa 19NA33101
Villa 20NA33101
Villa 21NA33101
Villa 22NA33101
Villa 23NA33101
Villa 24NA33101
Villa 25NA33101
Villa 26NA33101
Villa 27NA33101
Villa 28NA33101
Villa 29NA33101
Villa 30NA33101
Villa 31NA33101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 6 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 31 buildings; the table lists the first 20.

89 of 341 construction stages are filed complete across 31 buildings. The stage furthest along is Excavation, at 95%.

Viila 137%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Viila 237%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 373%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Villa 473%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Villa 519%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 69%
ActivityProgress
Excavation95%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 773%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Villa 88%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 930%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1027%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1124%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure66%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1230%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1319%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1422%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor10%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1530%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 168%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1714%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1824%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure66%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 1944%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villa 2044%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes30%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered60
BuildingClosed/CoveredTotal
Viila 122
Viila 222
Villa 322
Villa 422
Villa 522
Villa 622
Villa 722
Villa 822
Villa 922
Villa 1022
Villa 1122
Villa 1222
Villa 1322
Villa 1422
Villa 1522
Villa 1622
Villa 1722
Villa 1822
Villa 1922
Villa 2022
Villa 2122
Villa 2222
Villa 2422
Villa 2522
Villa 2622
Villa 2722
Villa 2822
Villa 2922
Villa 3022
Villa 3122

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area11,226 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025

Approvals and building plan

Sanctioning authorityPune metropolitan Region Development Authority
Permissible FSI10350.88
Proposed, not sanctioned10,251 sq m
Buildings approved31
Buildings sanctioned31

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhadarkar Road , Pune
Estimated costRs 35.46 cr
Cost incurredRs 17.88 cr
Work done50.41%
BuildingWingEstimatedIncurred
-NARs 6.42 crRs 2.61 cr
Viila 1NARs 93.68 lakhRs 49.26 lakh
Viila 2NARs 93.68 lakhRs 49.26 lakh
Villa 3NARs 93.68 lakhRs 49.26 lakh
Villa 4NARs 93.68 lakhRs 49.26 lakh
Villa 5NARs 93.68 lakhRs 49.26 lakh
Villa 6NARs 93.68 lakhRs 49.26 lakh
Villa 7NARs 93.68 lakhRs 49.26 lakh
Villa 8NARs 93.68 lakhRs 49.26 lakh
Villa 9NARs 93.68 lakhRs 49.26 lakh
Villa 10NARs 93.68 lakhRs 49.26 lakh
Villa 11NARs 93.68 lakhRs 49.26 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVaibhav Bondarde
ArchitectCorner stone Works Pvt Ltd
ArchitectCornerstone Pvt Ltd.
ArchitectCorner Stone Works Pvt Ltd.
EngineerShekhar Pingle
EngineerKundan Patil
Chartered AccountantGosavi Yardi & Co
Chartered AccountantKapure and Kapure Chartered Accountant
PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30122519148Dec 2025 → Dec 2027

Reason as filed by the promoterSelf - Declaration explaining reason is uploaded

Litigation declared3

CaseCourtStatus
1480/11/2011Civil Judge Senior Division PuneMatter is kept for examination in chief
593/2018/2018Civil Judge Junior Division PuneApplicant has taken steps for issue of summons
186/2018/2018Civil Judge Senior Division PuneMatter is kept for hearing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A_Rivolo Residences-FY 24-25.pdf6 Mar 2026
Withdrawal Update Form 1File: Form 1 Rivolo-DEC25.pdf21 Feb 2026
Withdrawal Update Form 2File: Form 2-Rivolo-Dec25-PSCL.pdf21 Feb 2026
Withdrawal Update Form 3File: FORM 3-Rivolo Residences-Dec25.pdf21 Feb 2026
Withdrawal Update Form 1File: Form 1 Rivolo Sept 25.pdf30 Dec 2025
Withdrawal Update Form 2File: Updated Form 2 - Rivolo.pdf30 Dec 2025
Withdrawal Update Form 3File: Form 3 Rivolo Sep 25_compressed.pdf30 Dec 2025
Withdrawal Update Form 1File: Form 1 Rivolo June 25.pdf29 Dec 2025
Withdrawal Update Form 2File: Form 2 Rivolo Resi JUne 25 shared on 08 July 25.pdf29 Dec 2025
Withdrawal Update Form 3File: Form 3 Rivolo June 25 compressed.pdf29 Dec 2025
Layout approvalFile: HPSC1443.pdf22 Dec 2025
Building plan approvalFile: HPSC1444.pdf22 Dec 2025
Building plan approvalFile: HPSC1445.pdf22 Dec 2025
Building plan approvalFile: HPSC1446.pdf22 Dec 2025
Building plan approvalFile: HPSC1447.pdf22 Dec 2025
Building plan approvalFile: HPSC1448.pdf22 Dec 2025
Building plan approvalFile: HPSC1450.pdf22 Dec 2025
Building plan approvalFile: HPSC1451.pdf22 Dec 2025
Building plan approvalFile: HPSC1452.pdf22 Dec 2025
Building plan approvalFile: HPSC1453.pdf22 Dec 2025
Building plan approvalFile: HPSC1454.pdf22 Dec 2025
Building plan approvalFile: HPSC1460.pdf22 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Rivolo Residencies.pdf8 Nov 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Rivolo-Mar'25-Uploaded.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-Rivolo-SEPT'24-uplaoded.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Rivolo-Dec'24-uploaded.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA FORM 2 DEC 24 of The Rivolo Residences-uploaded.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 -Rivolo-June '24-uploded.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rivolo 31-1-2024-uploaded-compressed.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-The Rivolo-Sept'24-uploaded.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Rivolo-Sept'24-uploaded.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Rivolvo Residences-FY '23-24-uploaded.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure-Sold-unsold-The Rivolo-June'24-uploaded.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 24 FORM 2-Rivolo-June'24-uploaded.pdf8 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Rivolo Resi-FORM 1-June'24-uploaded.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 8 The Rivolo -FORM 2A-June'24-uploaded.pdf4 Jul 2024
Disclosure of sold/ booked inventoryFile: Inventory Report-Rivolo-Mar'24-uploaded.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Rivolo Resi-Mar'24-uplaoded.pdf6 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2- THE RIVOLO RESIDENCE-Mar'24-uploaded.pdf4 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-The Rivolo-Mar'24-uploaded.pdf1 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-Rivolo -Dec'23-uplaoded.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Rivolo-Dec'23-uploaded.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A DEC 2023 RIVOLO-uploaded.pdf3 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2- Rivolo Residence-Sept'23-uploaded.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Rivolo Residences -Fy-'22-23-uploaded11oct23.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory data-The Rivolo Residences-Sept'23-uploaded.pdf10 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-The Rivolo-Sept'23.pdf5 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 A SEPT 23 RIVOLO-uploaded.pdf3 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory Report-Rivolo-June'23.pdf5 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2-Rivolo-June'23.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A RIVOLO June 23.pdf7 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 18 FORM 2-Forest Trails Rivolo Residence_Mar 23.pdf19 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1-form 1 RIVOLO MARCH 23-uploaded.pdf8 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Rivolo Residences.pdf20 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1OLD format-FORM2-Rivolo-Dec-2021.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 New FORM2 -Rivolo Residence-Mar 22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 New FORM2 -Rivolo Residence-June 22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 New FORM2 -Rivolo Residence-Sep 22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5New FORM2 -Rivolo Residence-Dec 22.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 RIVOLO Dec-2022-uploaded.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A Rivolo Mar 22.pdf26 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RIVOLO 1 st quarter ending June 2022.pdf26 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RIVOLO 2nd quarter ending Sept 2022.pdf26 Sep 2022
Building plan approvalFile: 7-Building Plan Approval.pdf27 Oct 2021
Building plan approvalFile: 8-Buliding Plan Approval.pdf27 Oct 2021
Building plan approvalFile: 2-Building plan Approval.pdf27 Oct 2021
Building plan approvalFile: 3-building Plan Approval.pdf27 Oct 2021
Building plan approvalFile: 4-building Plan Approval.pdf27 Oct 2021
Building plan approvalFile: 5-building Plan Approval.pdf27 Oct 2021
Building plan approvalFile: 6-Building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 2-Building plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 3-building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 4-building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 5-building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 6-Building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 7-Building Plan Approval.pdf27 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: 8-Buliding Plan Approval.pdf27 Oct 2021
Declaration in FORM BFile: FORM B Promoter -FT Rivolo.pdf27 Oct 2021
Layout approvalFile: Sanctioned LAyout.pdf21 Oct 2021
Copy of Layout Approval (in case of layout)File: Sanctioned LAyout.pdf21 Oct 2021

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
127 UPPER EASTP51800000454Andheri, Mumbai Suburban-Jul 2017CompletedJun 2024Registered original: Dec 2019Jan 1970
PRATHAM RESIDENTIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103035-CompletedApr 2016Mar 2016
THE BUSINESS HUBSURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 41102986-CompletedJan 2016Nov 2015
MADHUKOSH - IIISNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune258-CompletedAug 2015Aug 2015
PRATHAM COMMERCIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103032-CompletedJun 2015Apr 2015
PUNARVASUPRABHAT ROAD ERANDWANE PUNE 41100410-CompletedDec 2014Late, Jun 2015
MADHUKOSH - IISNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune150-CompletedDec 2013Oct 2013
MADHUKOSH - ISNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune289-CompletedMar 2012Feb 2012

How this compares with Pune

74%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Rivolo Residences at Forest Trails on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhugaon13,700+ in Pune

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD

PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if The Rivolo Residences at Forest Trails is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Rivolo Residences at Forest Trails?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Rivolo Residences at Forest Trails?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Rivolo Residences at Forest Trails?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Rivolo Residences at Forest Trails?

The professionals named in the filing: Architect: Vaibhav Bondarde; Architect: Corner stone Works Pvt Ltd; Architect: Cornerstone Pvt Ltd.; Architect: Corner Stone Works Pvt Ltd.; Engineer: Shekhar Pingle; Engineer: Kundan Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Rivolo Residences at Forest Trails?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Rivolo Residences at Forest Trails. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Rivolo Residences at Forest Trails to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.