The Province Phase I
RG-MH-88971 · RERA P52100018824 · Last updated on MahaRERA portal: 20 Jul 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 30 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Province Phase I is a Residential / Group Housing project by Bharat Developers in Punawale, 411033, registered with MahaRERA as P52100018824 on 6 Dec 2018. Possession was promised by 30 Apr 2024 and is now 30 months past that date.
At a glance
Project
- NameThe Province Phase I
- TypeResidential / Group Housing
- Location
- Koyate Vasti Road
- Punawale
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100018824
- ReraGenie IDRG-MH-88971
Builder
- NameBharat Developers
- Entity typePartnership
- PartnersRohit Tulsidas Harwani, Rajkumari Ghansham Daswani, Bharat Ghansham Daswani, Kundan Ramchandra Jachak, Rahul Tulsidas Harwani
- Other registrations2 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Dec 2018
- Promised completion30 Apr 2024
- Revised completionNone
- Buildings3 building records
- Documents filed116 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A2 Wing | NA | 14 | 0 | 0 | 0 | 0 |
| C Wing | NA | 14 | 0 | 0 | 0 | 0 |
| D Wing | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 97%.
A2 Wing81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 97% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
C Wing79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 94% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
D Wing74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 63% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities16
As on 20 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | Yes | 40% |
| Open Parking | Yes | 0% |
| Compound Wall | Yes | 0% |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A2 Wing | 34 | 34 |
| C Wing | 36 | 36 |
| D Wing | 58 | 58 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Vishwas Kulkarni |
| Engineer | Shree Balaji Enterprises |
| Chartered Accountant | ANR & Company |
| Partner | Role in project |
|---|---|
| Bharat Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Dec 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Dec 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed116
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: signd F1.pdf | 20 Jul 2024 |
| Other - FinanceFile: o technical.pdf | 19 Jul 2024 |
| Other - FinanceFile: phase 1 noc.pdf | 19 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: from 5 phase 1 FY-22-23.pdf | 26 Oct 2023 |
| Certificates of CA (Form 3)File: Bharat-Form-3 Mar 2019.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: form 3 CA Certificate Dec 2019_11zon.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate OCT 2020_11zon.pdf | 20 Oct 2023 |
| Certificates of CA (Form 3)File: Adobe Scan Sep 03, 2021 Phase 2_11zon.pdf | 20 Oct 2023 |
| Form 2AFile: Form 2A Phase 1.pdf | 12 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold-unsold Phase 1_compressed.pdf | 12 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 Phase 1_compressed.pdf | 12 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1.pdf | 9 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Province Ph 1 (1).pdf | 9 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: phase - 1 sold-unsold _11zon.pdf | 9 Oct 2023 |
| Layout approvalFile: 1-19_12_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 2-19_13_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 3-19_14_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 4-19_15_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 5-19_16_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 6-19_17_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 7-19_18_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 9-19_1_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 10-19_2_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 11-19_3_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 12-19_4_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 13-19_5_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 14-19_6_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 15-19_7_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 16-19_8_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 17-19_9_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 18-19_10_11zon.pdf | 6 Oct 2023 |
| Layout approvalFile: 19-19_11_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 1-19_12_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 2-19_13_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 3-19_14_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 4-19_15_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 5-19_16_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 6-19_17_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 7-19_18_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 9-19_1_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 10-19_2_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 11-19_3_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 12-19_4_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 13-19_5_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 14-19_6_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 15-19_7_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 16-19_8_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 17-19_9_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 18-19_10_11zon.pdf | 6 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 19-19_11_11zon.pdf | 6 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 220608 - CC.pdf | 6 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 220608 - Appendix D3.pdf | 6 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 Phase 1_compressed.pdf | 15 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Province Phase 1 F2_compressed.pdf | 29 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: PHASE-1.pdf | 29 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 230612 Architecture Cert Form 1, Bldg C,D , A2.pdf | 28 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture F1.pdf | 10 Apr 2023 |
| Certificates of CA (Form 3)File: Form3 Phase1_compressed.pdf | 10 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: The province phase 1 Engineers Certificate.pdf | 31 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 phase 1 21-22.pdf | 13 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architech certificate.pdf | 23 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: province pahse 1.pdf | 23 Dec 2022 |
| Certificates of CA (Form 3)File: Form-3 phase -1_compressed (1).pdf | 23 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Phase1.pdf | 3 Nov 2022 |
| Certificates of CA (Form 3)File: Bharat Developers Form3 Phase1_compressed (1).pdf | 3 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 22 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 22 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed (1).pdf | 6 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Province Ph 1_compressed.pdf | 6 Jul 2022 |
| Certificates of CA (Form 3)File: Form3 Phase -1_compressed (1).pdf | 6 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold Booked Inventory Phase 1_compressed.pdf | 25 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 220228 - Architecture Cert.pdf | 12 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Phase 1.pdf | 12 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Discolsure Of Sold Booked Inventory Phase 1_compressed.pdf | 12 Mar 2022 |
| Certificates of CA (Form 3)File: Bharat_Dev_Form3 Phase 1_compressed (1).pdf | 12 Mar 2022 |
| Layout approvalFile: Laypout Revise plan.pdf | 17 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Laypout Revise plan.pdf | 17 Sep 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 116 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep The Province Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Punawale
Filed coordinates, straight-line distance. 123 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: Bharat Developers
BHARAT DEVELOPERS has 3 registrations on MahaRERA, including LOTUS RESIDENCY and The Province Phase I. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that The Province Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if The Province Phase I is delayed beyond 30 Apr 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Province Phase I?
The registered promoter entity is Bharat Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Province Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Province Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Province Phase I?
The professionals named in the filing: Architect: Mr Vishwas Kulkarni; Engineer: Shree Balaji Enterprises; Chartered Accountant: ANR & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Province Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback