Home / Browse projects / Pune, Maharashtra / The Nook Phase 1

Completed No litigation declared Residential / Group Housing project

The Nook Phase 1

By Pyramid Developers

RG-MH-10546 · RERA P52100004015 · Last updated on MahaRERA portal: 27 Aug 2018

Source: official MahaRERA filing

Red flags

  • 23 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2019Possession promisedregistration recorded completed
19 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
23Complaints at MahaRERAon this registration
Jump to the 16 documents Report an error

The Nook Phase 1 is a Residential / Group Housing project by Pyramid Developers in Pune, Maharashtra, registered with MahaRERA as P52100004015 on 7 Aug 2017. The registration is recorded completed; possession was promised by 31 Oct 2019. The completion date has moved by 12 months from the original filing. 23 complaints are on record with the regulator.

At a glance

Project

  • NameThe Nook Phase 1
  • TypeResidential / Group Housing
  • Location
    • Tathwade
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004015
  • ReraGenie IDRG-MH-10546

Builder

  • NamePyramid Developers
  • Entity typePartnership
  • PartnersDeepak Krishanlal Anand, Vivek Chanderlal Mulchandani, Deeraj Sadhu Bhojwani
  • Other registrations6 more →
  • Completed4 of 7
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

this monthRegisteredAug 2017First promiseOct 2018Revised toOct 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Aug 2017
  • Promised completion31 Oct 2019
  • Revised completionRevised to 31 Oct 2019 (originally 31 Oct 2018)
  • Buildings3 building records
  • Documents filed16 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA140000
B WingNA140000
C WingNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 27 Aug 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

A Wing86%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises94%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B Wing62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.76%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Wing83%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Progress on shared amenities15

As on 27 Aug 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes30%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes45%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes10%
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes55%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes29%

Parking filed324

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots324
Closed/Covered188
Open Space136
BuildingClosed/CoveredOpen SpaceTotal
A Wing6737104
B Wing5264116
C Wing6935104

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,579 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Prathamesh DevelopersWarjePune
Balasaheb Parshuram PhengaseTathwadePune
Shantaram Parshuram PhengseTathwadePune
Kantilal Parshuram PhengseTathwadePune

Approvals and building plan

Permissible FSI17433.39
Proposed, not sanctioned17,433 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDwarka Lords Pimple Saudagar Pune 411027

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYojana Architect
EngineerG A Bhilare Consultants Pvt Ltd
PartnerRole in project
Pyramid Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000857Oct 2018 → Oct 2019

Reason as filed by the promoterThe extension period is required just for obtaining the Occupancy certificate which can be achieved once we get the environment clearance certificate . We have already applied for EC but there has been delay in receiving sanctions from the authorities for reasons which are beyond our control . We are trying our best to get the EC and as soon as we get it we will obtain the Occupancy certificate as soon as possible . We request you to please grant us extension for the same

Litigation declared1

CaseCourtStatus
403035/2015Chief Judicial Magistrate First Class PuneAppearance

Complaints filed with MahaRERA23

Case no.ComplainantRespondentFiled
CC005000000000102Sumit VashisthaKhemchand Uttamchand Bhojwani29/10/2017
CC005000000010661Abhudhay DevPyramid Developers06/12/2017
CC005000000000306Shubh RamKhemchand Uttamchand Bhojwani06/12/2017
CC005000000000308Dayanand Ravalnath PatilMr. Khemchand Uttamchand Bhojwani06/12/2017
CC005000000000310Laltu DeyKhemchand Uttamchand Bhojwani10/12/2017
CC005000000000309VISHAL P BORSEMr KHEMCHAND UTTAMCHAND BHOJWANI06/12/2017
CC005000000000311sanjeev kumarKhemchand uttamchand bhojwani06/12/2017
CC005000000010477Neeraj Singh VermaKhemchand Uttamchand Bhojwani05/11/2017
CC005000000010478NITIN GUPTAKHEMCHAND UTTAMCHAND BHOJWANI29/10/2017
CC005000000010480PRAVIN KUMAR CHAURASIAKHEMCHAND UTTAMCHAND BHOJWANI29/10/2017
CC005000000010553Ashok T GadeKemchand Uttamchand Bhojwani10/11/2017
CC005000000010669Sunil LidoriaMr. Khemchand Bhojwani07/12/2017
CC005000000010691Kapil ChansouriaKhemchand Uttamchand Bhojwani14/12/2017
CC005000000010671ATUL VIJAY PAWARPyradmid Developers13/12/2017
CC005000000010668mahendra kumar mishraKhemchand Uttamchand Bhojwani12/12/2017
CC005000000010670Nivesh YadavKHEMCHAND UTTAMCHAND BHOJWANI12/12/2017
CC005000000011252Ganesh Shriram ShelkeKhemchand Uttamchand Bhojwani25/03/2018
CC005000000011251Rahul Dnyandeo DeshmukhKhemchand Uttamchand Bhojwani25/03/2018
CC005000000011675Sushilkumar PatilKhemchand Uttamchand Bhojwani26/06/2018
CC005000000011674Mahesh ShelkePyramid Developers26/06/2018
CC005000000011677Pankaj ChoudharyKHECHAND UTTAMCHAND BHOJWANI25/06/2018
CC005000000011681Suraj PujariPyramid Develpoers25/06/2018
CC005000000011682RAVIRAJ KASHINATH SHINDEPYRAMID DEVELOPERS26/06/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed16

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 4)File: form4architectscertificate.pdf27 Aug 2018
Certificates of Architect (Form 4)File: Architect Certificate The Nook.pdf24 Aug 2018
OtherFile: possession mail.pdf24 Aug 2018
Layout approvalFile: Building Plan Layout.pdf31 Jul 2017
Building plan approvalFile: Building Plan Approval (IOD).pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Building Plan Layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: Building Plan Approval (IOD).pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Pyramid.PDF31 Jul 2017
Certificates of CA (Form 3)File: Certificate Of CA Pyramid.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Pyramid.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate Of Engg Form 2.PDF30 Jul 2017
Copy of the legal title reportFile: Copy of legal title report.pdf29 Jul 2017
Details of encumbrancesFile: Details of encumbrances.PDF29 Jul 2017
Declaration in FORM BFile: Declaration in FORM B.pdf29 Jul 2017
PAN CardFile: Pan Card.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf26 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Nook Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tathwade13,700+ in Pune

2 kmThe Nook Phase 1Completed 111Lapsed / revoked 42Other 93Dot size: filed unitsN

Filed coordinates, straight-line distance. 246 registered projects within 2 km.

Builder: Pyramid Developers

Pyramid Developers has 7 registrations on MahaRERA, including The Nook Phase 1 and 81 AUREATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if The Nook Phase 1 is delayed beyond 31 Oct 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Nook Phase 1?

The registered promoter entity is Pyramid Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Nook Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Nook Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for The Nook Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Nook Phase 1?

The professionals named in the filing: Architect: Yojana Architect; Engineer: G A Bhilare Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Nook Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Nook Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Nook Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.