THE NEW GREEN CHAMBERS CHS
RG-MH-12771 · RERA P51900022675 · Last updated on MahaRERA portal: 5 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 42 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE NEW GREEN CHAMBERS CHS is a Others project by ELITE CONSTRUCTION CO in Byculla, 400008, registered with MahaRERA as P51900022675 on 12 Oct 2019. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 42 months from the original filing.
At a glance
Project
- NameTHE NEW GREEN CHAMBERS CHS
- TypeOthers
- Location
- Sofia Zuber road
- Byculla
- 400008
- Pincode400008
- RERA no.P51900022675
- ReraGenie IDRG-MH-12771
Builder
- NameELITE CONSTRUCTION CO
- Entity typePartnership
- PartnersAsma Juned Alam Khan, Junedalam Azizullah Khan
- Other registrations3 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Oct 2019
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed130 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE NEW GREEN CHAMBERS CHS | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
THE NEW GREEN CHAMBERS CHS: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 5 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed21
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| ELITE CONSTRUCTION CO | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the lockdown in 2020 and most of 2021, our construction work had come to a stand still. Moreover, there was shortage of labors as most of them had moved to their hometown. The work has now resumed and is in full swing. Kindly allow us to extend the project.
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 88.89% allottees for purpose of extension of RERA registration period of the said project.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and delay in OC. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval o
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Sep 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Sep 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Apr 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 29 Nov 2021
Documents filed130
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 130 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 - The New Green Chambers as on March 2025.pdf | 5 Sep 2025 |
| Form 2File: Form 2 - The New Green Chambers as on March 2025.pdf | 5 Sep 2025 |
| Form 3File: Form 3 - The New Green Chambers as on March 2025.pdf | 5 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29 - The New Green Chambers as on March 2025.pdf | 5 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - The New Green Chambers as on March 2025.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 15 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 NGC final.pdf | 29 Mar 2025 |
| Declaration in FORM BFile: Affidavit cum Declaration (8).pdf | 24 Mar 2025 |
| Declaration in FORM BFile: Affidavit cum Declaration (8).pdf | 24 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate as on 31st December 2024 (1).pdf | 24 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 for 31st December 2024 (2)_11zon.pdf | 24 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure -B as on 31-12-2024.pdf | 24 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Adobe Scan 24 Mar 2025 (2).pdf | 24 Mar 2025 |
| Other - TechnicalFile: P51900022675_FileName_3.pdf | 24 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Format Form 3_The New Green Chambers 30th September 2023.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers 31st December 2023 Signed.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers 31st March 2024.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers 30th June 2024.pdf | 10 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers 30th September 2024.pdf | 10 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers as on September 2023.pdf | 10 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers CHS Dec 2023 Signed.pdf | 10 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers as on March 2024.pdf | 10 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers as on June 2024.pdf | 10 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers as on September 2024.pdf | 10 Mar 2025 |
| Declaration about Commencement CertificateFile: 2 Declaration about Commencement Certificate.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 16 Jan 2025 |
| Declaration about Commencement CertificateFile: Affidavit.pdf | 16 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023 24.pdf | 16 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Adobe Scan 15 Jan 2025.pdf | 16 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 The New Green Chambers FY 2023-24.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec_11zon.pdf | 26 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 26 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 26 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 26 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf | 26 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 26 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 26 Feb 2024 |
| Declaration in FORM BFile: Form B(1).pdf | 7 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 7 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec_11zon.pdf | 7 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 7 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - The New Green Chambers CHS Dec 2023.pdf | 15 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers 31st December 2023.pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Circualr 29 - The New Green Chambers as on Dec 2023.pdf | 13 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - The New Green Chambers as on Dec 2023.pdf | 8 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 23.pdf | 6 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf | 6 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf | 6 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf | 6 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf | 6 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 23_11zon.pdf | 6 Sep 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 1 Sep 2023 |
| Declaration in FORM BFile: Form B.pdf | 1 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 1 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 1 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- The New Green Chambers.pdf | 19 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A- The New Green Chambers as on 2020-21.pdf | 9 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_The New Green Chamber 30th June 2023.pdf | 1 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The New Green Chambers_30-06-2023.pdf | 31 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: The New Green Chambers CHS Mar 23 - Form 2.pdf | 15 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- The New Green Chambers as on 31-03-2023.pdf | 15 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Elite Construction_FY 2021-22.pdf | 15 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- The New Green Chambers as on December 2022.pdf | 7 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- The New Green Chambers as on December 2022.pdf | 7 Apr 2023 |
| Building plan approvalFile: Latest Layout_compressed (1)-1.pdf | 6 Apr 2023 |
| Building plan approvalFile: Latest Layout_compressed (1)-2.pdf | 6 Apr 2023 |
| Building plan approvalFile: Latest Layout_compressed (1)-3.pdf | 6 Apr 2023 |
| Building plan approvalFile: Latest Layout_compressed (1)-4.pdf | 6 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Latest Layout_compressed (1)-1.pdf | 6 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Latest Layout_compressed (1)-2.pdf | 6 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Latest Layout_compressed (1)-3.pdf | 6 Apr 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Latest Layout_compressed (1)-4.pdf | 6 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- The New Green Chambers as on September 2022.pdf | 21 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- The New Green Chambers as on September 2022.pdf | 21 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- The New Green Chambers.pdf | 17 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2022.pdf | 21 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- June 2022.pdf | 21 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate 299.pdf | 21 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate 300.pdf | 21 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Certificate 283.pdf | 19 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 130 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep THE NEW GREEN CHAMBERS CHS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Byculla
FATIMA HEIGHTS
M K ENTERPRISES
Nexsa Sky Vista
D.K. REALTORS & DEVELOPERS LIMITED
Lakadawala Garden
M/s. Lakadawala Developers Pvt. Ltd.
La Mer Residences
EXCELLENT REALTOR DEVELOPERS
Godrej Avenue Eleven - Tower A
GODREJ RESIDENCY PRIVATE LIMITED
FUEGO
HILTON INFRASTRUCTURE
Builder: ELITE CONSTRUCTION CO
Elite Construction Co. has 4 registrations on MahaRERA, including Elite Tower and THE NEW GREEN CHAMBERS CHS. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that THE NEW GREEN CHAMBERS CHS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if THE NEW GREEN CHAMBERS CHS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE NEW GREEN CHAMBERS CHS?
The registered promoter entity is ELITE CONSTRUCTION CO, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE NEW GREEN CHAMBERS CHS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE NEW GREEN CHAMBERS CHS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in THE NEW GREEN CHAMBERS CHS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback