Home / Browse projects / Mumbai Suburban, Maharashtra / THE KOLLAGE

Registration lapsed Litigation declared Residential / Group Housing project

THE KOLLAGE

By ZIRE RUSHI CONSTRUCTION

RG-MH-27097 · RERA P51800012084 · Last updated on MahaRERA portal: 30 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 2 months past the filed date
  • Litigation declared, 3 cases
  • 3 complaints at MahaRERA
  • Completion date moved by 44 months
  • 4 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
10 of 11Construction stages donefurthest along: Internal walls, 99%
17 of 73Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

THE KOLLAGE is a Residential / Group Housing project by ZIRE RUSHI CONSTRUCTION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012084 on 1 Sep 2017. Possession was promised by 15 Aug 2026 and is now 2 months past that date. The completion date has moved by 44 months from the original filing. 56 of the 73 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameTHE KOLLAGE
  • TypeResidential / Group Housing
  • Location
    • Dr. N.S. Phadke Marg
    • Andheri (East)
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012084
  • ReraGenie IDRG-MH-27097

Builder

  • NameZIRE RUSHI CONSTRUCTION
  • Entity typeOthers
  • GSTIN27AAGFH1786A1ZK
  • Named personsANIL CHANDULAL SHAH, SEEMA ANIL SHAH, JAL PVT LTD, JAYESH PANNALAL CHOKSI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

2 months past promisethis monthRegisteredSep 2017First promiseDec 2022Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion15 Aug 2026
  • Revised completionRevised to 15 Aug 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed112 files

Current status

77%56 of 73 units booked
97.5%Work done, per cost certificate

Figures as on 30 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE KOLLAGENA181272173

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

THE KOLLAGE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,869 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBrihanmumbai Municipal Corporation
Permissible FSI9238.6
Proposed, not sanctioned5,420 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHOLANATH CHS LTD GROUND FLOOR SUBHASH ROAD VILE PARLE EAST MUMBAI 400057
Estimated costRs 31.50 cr
Cost incurredRs 30.71 cr
Work done97.49%
BuildingWingEstimatedIncurred
THE KOLLAGENARs 28.50 crRs 27.71 cr
-NARs 3.00 crRs 3.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUMESH BHATT
ArchitectUmesh Bhatt Architect & Interior Designer
EngineerHARDIK RAJESH SHAH
EngineerSunil R Shah
Chartered AccountantMITTAL AGARWAL AND COMPANY
Chartered AccountantSHILPA BANSAL
PartnerRole in project
ZIRE RUSHI CONSTRUCTION-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013087Dec 2022 → Dec 2023

Reason as filed by the promoterThe present project comprising of Phase-I having Basement, Ground Plus 12 floors including 2 podium and Phase-II having additional four residential upper floors above 12 floors. Part Occupancy Permissions for Phase - I is received on 26th March 2021 and and balance oc upto 12th floor on 19th October 2022. The balance of Phase-II is under construction and delayed due to reasons beyond our control as under: 1. Originally although the concessions for the present project was approved till 16 upper floors, due to subsequent restrictions by the Aviation Authorities on account of directions of the Ho

EXT51800019125Dec 2022 → Dec 2024

Reason as filed by the promoterThe Promoter is developing a project with as on date, two wings i.e. wing A & B having common Basement (for stack parking) + 3rd to 13 th upper floors for both wings as per plans and permissions approved by the MCGM from time to time. The Promoter have already obtained Part Occupancy Permissions for the two wings till 12 th Upper Floors and handed over possession to all the Allottees of the Project Occupation certificate of one upper floor at 13 th Floor level is pending The construction of the balance one upper floor i.e. 13 th Floor and overhead water tank, is at the advanced stage and t

EXT51800026076Dec 2022 → Jun 2025

Reason as filed by the promoterwe, M/s. Zire Rushi Construction, hereby declare the following with respect to the project The Kollage bearing registration number. P51800012084 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 12/06/2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timel

EA18052621002Dec 2022 → Aug 2026

Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 12/06/2025 and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and the total number of parking. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide

Litigation declared3

CaseCourtStatus
60/2017BOMBAY HIGH COURTPENDING
1634/2017BOMBAY HIGH COURTPENDING
2005/2011BOMBAY HIGH COURTPENDING

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000056057Manoj Mohan BhagchandaniM/s ZIRE RUSHI CONSTRUCTION10/09/2018
CC006000000210098Zire Rushi ConstructionsVAISHALI KISAN BHAISANE18/02/2022
CC12603935ZIRE RUSHI CONSTRUCTIONLaxmi Govind Parsekar25/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Nov 2022

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf30 May 2026
Withdrawal Update Form 1File: Form 1.pdf30 May 2026
Withdrawal Update Form 1File: Form 1.pdf30 May 2026
Withdrawal Update Form 2File: Form 2 ( OC Date).pdf30 May 2026
Withdrawal Update Form 2File: Form 2 ( OC Date).pdf30 May 2026
Withdrawal Update Form 2File: Form 2.pdf30 May 2026
Withdrawal Update Form 3File: Form 3.pdf30 May 2026
Withdrawal Update Form 3File: Form 3.pdf30 May 2026
Withdrawal Update Form 3File: Form 3.pdf30 May 2026
Form 2A (FY 2024-2025)File: Form2A_2024-25.pdf30 May 2026
Withdrawal Update Form 1File: Form 1.pdf18 May 2026
Withdrawal Update Form 2File: Form 2 ( OC Date).pdf18 May 2026
Withdrawal Update Form 3File: Form 3.pdf18 May 2026
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf23 Apr 2025
Certificates of CA (Form 3)File: Form 3 Mar 25.pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Dec 24.pdf5 Feb 2025
Certificates of CA (Form 3)File: Form 3 Dec 24.pdf5 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory.pdf2 Jan 2025
Certificates of CA (Form 3)File: Form 3 Jun 24 signed.pdf23 Oct 2024
Certificates of CA (Form 3)File: Form 3 Sept 24 signed.pdf23 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Jun 24.pdf20 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Sept 24.pdf20 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Jun 24.pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sept 24.pdf19 Oct 2024
Certificates of CA (Form 3)File: Form 3 Jun 24.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf27 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf24 May 2024
Certificates of CA (Form 3)File: FORM 3.pdf24 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SEPT 23.pdf16 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DEC 23.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate for RERA - The Kollage 30062023_compressed.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate for RERA - The Kollage 30092023_compressed.pdf16 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate for RERA - The Kollage 31122023_compressed.pdf16 Feb 2024
Certificates of CA (Form 3)File: Form 3 june signed_compressed.pdf16 Feb 2024
Certificates of CA (Form 3)File: Form 3 sept signed_compressed.pdf16 Feb 2024
Certificates of CA (Form 3)File: Form 3 Dec 23 signed_compressed.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf16 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf16 Feb 2024
Disclosure of sold/ booked inventoryFile: Book of sold unsold inventory - 310323.pdf15 Feb 2024
Disclosure of sold/ booked inventoryFile: Book of sold unsold inventory - 300623.pdf15 Feb 2024
Disclosure of sold/ booked inventoryFile: Book of sold unsold inventory - 300923.pdf15 Feb 2024
Disclosure of sold/ booked inventoryFile: Book of sold unsold inventory - 311223.pdf15 Feb 2024
Proforma of Agreement for saleFile: Proforma for Agreement for Sale.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf22 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf22 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sept.pdf22 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec.pdf22 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Mar.pdf22 Sep 2023
Certificates of CA (Form 3)File: Form 3 Dec 22.pdf4 Sep 2023
Certificates of CA (Form 3)File: Form 3 Mar 23.pdf4 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Mar 22.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Jun 22.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Sept 22.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineer Jun 22.pdf17 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineer Sept 22.pdf17 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Mar 22.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Qc mar 22.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: List inventory.pdf17 Jan 2023
Certificates of CA (Form 3)File: Form 3 Mar 22.pdf17 Jan 2023
Certificates of CA (Form 3)File: Form 3 Jun 22.pdf17 Jan 2023
Certificates of CA (Form 3)File: Form 3 Sept 22.pdf17 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2342034_OC_signed.pdf15 Nov 2022
Certificates of CA (Form 3)File: Form 3 Dec 21 - NEW.pdf6 Oct 2022
Details of encumbrancesFile: Letter for RERA - PAP.pdf15 Jun 2022
Certificates of CA (Form 3)File: Form 3 Sept 21.pdf7 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Sept.pdf4 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Dec.pdf4 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: kollage engg certificate Sept 2021.pdf4 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: kollage engg certificate Dec 2021.pdf4 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf1 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf31 Jan 2022
Certificates of CA (Form 3)File: Form 3 Jun 21.pdf31 Jan 2022
OtherFile: Extention Letter.pdf4 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf23 Jun 2021

How this compares with Mumbai Suburban

77%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 44 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE KOLLAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri (East)6,700+ in Mumbai Suburban

2 kmTHE KOLLAGECompleted 171Lapsed / revoked 89Other 181Dot size: filed unitsN

Filed coordinates, straight-line distance. 441 registered projects within 2 km.

Builder: ZIRE RUSHI CONSTRUCTION

ZIRE RUSHI CONSTRUCTION has 2 registrations on MahaRERA, including THE KOLLAGE and Kyron. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that THE KOLLAGE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE KOLLAGE is delayed beyond 15 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE KOLLAGE?

The registered promoter entity is ZIRE RUSHI CONSTRUCTION, an others as per the filing. Its GSTIN 27AAGFH1786A1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE KOLLAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE KOLLAGE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE KOLLAGE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE KOLLAGE?

The professionals named in the filing: Architect: UMESH BHATT; Architect: Umesh Bhatt Architect & Interior Designer; Engineer: HARDIK RAJESH SHAH; Engineer: Sunil R Shah; Chartered Accountant: MITTAL AGARWAL AND COMPANY; Chartered Accountant: SHILPA BANSAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE KOLLAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE KOLLAGE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE KOLLAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.