Home / Browse projects / Thane, Maharashtra / The Icon Phase 5

Registered No litigation declared Residential / Group Housing project

The Icon Phase 5

By Leading Frontier Private Limited

RG-MH-38985 · RERA P51700033286 · Last updated on MahaRERA portal: 6 May 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
8 of 11Construction stages donefurthest along: Internal walls, 86%
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

The Icon Phase 5 is a Residential / Group Housing project by Leading Frontier Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700033286 on 15 Feb 2022. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameThe Icon Phase 5
  • TypeResidential / Group Housing
  • Location
    • Highland Garden
    • Dhokali
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • RERA no.P51700033286
  • ReraGenie IDRG-MH-38985

Builder

  • NameLeading Frontier Private Limited
  • Entity typeCompany
  • CINU45309MH2017FTC290088
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Directorzhengxing chen
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed55 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Park 3NA330000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 86%.

Park 3: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.31%

Progress on shared amenities15

As on 6 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed241

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots241
Closed/Covered219
Open Space22

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,184 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Siddhi Real Estate DevelopersThane (M Corp.)Thane
Gowani Hotel Pvt LtdThane (M Corp.)Thane

Approvals and building plan

Permissible FSI15677.01
Proposed, not sanctioned15,677 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd, GF 05-06, JMD Pacific Square, Sector-15, Part II Gurgaon Haryana 122002

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDesign Consortium
EngineerMahimtura Consultants Pvt Ltd
Chartered AccountantAshwin B Shah & Co
PartnerRole in project
Leading Frontier Private Limited-

Litigation declared8

CaseCourtStatus
791/2010/2010Thane Civil CourtMatter is for evidence of defendants are ongoing next date eight march two thousand nineteen
1868/2016Bombay High CourtAt admission stage next date second july two thousand nineteen
8595 of 2015 I to R/2015Bombay High CourtAt admission stage next date twelve July two thousand nineteen
426/2017/2017Thane Civil CourtStage of Matter was for written statement and reply of the Defendants next date sixteenth March Two
R CA 65/2017/2017Thane Civil CourtBombay High Court F Y Five Hundred Tow by Two thousand One is disposed and Trfd to Thane High Court
7204 of2016/2016Bombay High CourtDoes not pertains to Land but pertain to DP road now at admission stage Next date Eleventh March T
Before SDO Officer Thane Appeal no202/2018 in Tahasildar Thane 84CC proceeding no 87/2017/2018Before Sub Divisional Officer ThaneTenancy Appeal against Order dated Eighteenth July Two Thousand Eighteen passed in Tahasildar Thane
35982/2018/2018Bombay High CourtWrit Petition is filed for quashing the proceedings filed before the Sub Divisional Office Thane bea

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE PHASE 5.pdf6 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Phase 5 - Form 3 - 31 March 2024.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Phase 5 - Form 3 - 30 June 2024.pdf7 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Phase 5 - Sept 2024.pdf2 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Phase 5 - Dec 2024.pdf2 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase5.PDF30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase 5.pdf4 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 PHASE 5 (1).pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA CERTIFICATE FOR PHASE 5.pdf1 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PHASE 5 (1) (1).PDF5 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A (Phase5) (Q4 2023).pdf5 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase 5_compressed.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A (Phase-5) (Q3 2023).pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Project Status Phase 5 (1).pdf4 Sep 2023
Disclosure of sold/ booked inventoryFile: P3 Rera data 31st March.pdf19 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wing C2.PDF18 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form-2A Phase-5.pdf18 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 5.pdf17 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 5 31-12-2022.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: RERA DISCLOSURE OF SOLD PH 5.pdf17 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 5 31-12-2022.pdf17 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 PH 5 FY 2021-22.pdf16 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase5_compressed (1).pdf10 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A Phase-5 Q3 2022.pdf10 Nov 2022
Disclosure of sold/ booked inventoryFile: Sold Disclosuer Phase - 5.pdf10 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase 5 (1).PDF21 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A P-5 Q2 2022.pdf21 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Disclosuer Phase - 5.pdf21 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 P5 Mar - 2022.pdf12 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form-2A P5 Q1 2022.pdf12 May 2022
Disclosure of sold/ booked inventoryFile: Sold Units Phase 5 March 2022.pdf10 May 2022
Layout approvalFile: Layout 1-1.pdf11 Feb 2022
Layout approvalFile: Layout 1-2.pdf11 Feb 2022
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf11 Feb 2022
Copy of Layout Approval (in case of layout)File: Layout 1-1.pdf11 Feb 2022
Copy of Layout Approval (in case of layout)File: Layout 1-2.pdf11 Feb 2022
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf11 Feb 2022
Proforma of Allotment letterFile: 2 Proforma of the allotment letter and agreement for sale.pdf4 Feb 2022
Building plan approvalFile: Building Plans 1.pdf27 Jan 2022
Building plan approvalFile: Building Plans 2.pdf27 Jan 2022
PAN CardFile: Pan Card.pdf27 Jan 2022
Copy of the legal title reportFile: Report 05012022 Final_compressed.pdf27 Jan 2022
Details of encumbrancesFile: Encumbrances Phase 5.pdf27 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plans 1.pdf27 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plans 2.pdf27 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Amended CC.pdf27 Jan 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf27 Jan 2022
Declaration in FORM BFile: Govani Form B Affidavit_compressed.pdf27 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_compressed (1).pdf27 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf27 Jan 2022
Disclosure of sold/ booked inventoryFile: Sold Units Detials.pdf27 Jan 2022
CERSAI detailsFile: 12 CERSAI_Search_Report_200227191455_For_Debtor_Based_Search_03_01_2022_11_50_43_274.pdf27 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 5.pdf27 Jan 2022
Proforma of Allotment letterFile: 14 Draft Agreement Phase V Park 3.pdf27 Jan 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Icon Phase 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhokali7,600+ in Thane

Builder: Leading Frontier Private Limited

Leading Frontier Private Limited has 5 registrations on MahaRERA, including The Icon Phase 1 and The Icon Phase 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if The Icon Phase 5 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Icon Phase 5?

The registered promoter entity is Leading Frontier Private Limited, a company as per the filing. Its CIN U45309MH2017FTC290088 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Icon Phase 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Icon Phase 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Icon Phase 5?

The professionals named in the filing: Architect: Design Consortium; Engineer: Mahimtura Consultants Pvt Ltd; Chartered Accountant: Ashwin B Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Icon Phase 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Icon Phase 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Icon Phase 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.