The Doorways
RG-MH-19542 · RERA P52100078158 · Last updated on MahaRERA portal: 24 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Doorways is a Others project by MOON VALLEY RESORTS LLP in Pune, Maharashtra, registered with MahaRERA as P52100078158 on 25 Nov 2024. Possession is promised by 15 Dec 2028.
At a glance
Project
- NameThe Doorways
- TypeOthers
- Location
- DONGARGOAN- LONAVALA ROAD
- LONAVALA
- Dongargaon
- Mawal
- Pune
- 410401
- Pincode410401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100078158
- ReraGenie IDRG-MH-19542
Builder
- NameMOON VALLEY RESORTS LLP
- Entity typePartnership
- PartnersARJUN S BAJAJ, KAPILL K MALHOTRA, ANKIT K MALHOTRA, SHILPA K MALHOTRA, HETRAM M KUMHAR
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Nov 2024
- Promised completion15 Dec 2028
- Revised completionNone
- Buildings29 building records
- Documents filed36 files
Current status
Figures as on 24 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Unit no 28A and 28B | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 29 and 30 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 31 and 32 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 33 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 34A and 34B | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 35A and 35B | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 1 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 2A | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 2B and 03 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 4 and 7 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 5 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 6 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 9 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 10 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 11 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 12 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 14 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 15 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 16 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 17 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 18 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 19 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 20 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 21 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 22 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 23 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 24 and 25 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 26 | NA | 3 | 0 | 0 | 0 | 0 |
| Unit no 27A and 27B | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 29 buildings; the table lists the first 20.
87 of 319 construction stages are filed complete across 29 buildings. The stage furthest along is Slabs of Super Structure, at 98%.
Unit no 28A and 28B54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 29 and 3054%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 31 and 3254%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 3354%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 34A and 34B54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 35A and 35B54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 154%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 2A54%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 2B and 0354%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 4 and 754%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 554%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 654%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 954%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1054%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1154%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1254%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1454%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1554%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1654%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Unit no 1754%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 98% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 56% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 94% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 3% |
| Water Supply | Yes | 1% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 2% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 65% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed29
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Unit no 28A and 28B | 1 | 1 |
| Unit no 29 and 30 | 1 | 1 |
| Unit no 31 and 32 | 1 | 1 |
| Unit no 33 | 1 | 1 |
| Unit no 34A and 34B | 1 | 1 |
| Unit no 35A and 35B | 1 | 1 |
| Unit no 1 | 1 | 1 |
| Unit no 2A | 1 | 1 |
| Unit no 2B and 03 | 1 | 1 |
| Unit no 4 and 7 | 1 | 1 |
| Unit no 5 | 1 | 1 |
| Unit no 6 | 1 | 1 |
| Unit no 9 | 1 | 1 |
| Unit no 10 | 1 | 1 |
| Unit no 11 | 1 | 1 |
| Unit no 12 | 1 | 1 |
| Unit no 14 | 1 | 1 |
| Unit no 15 | 1 | 1 |
| Unit no 16 | 1 | 1 |
| Unit no 17 | 1 | 1 |
| Unit no 18 | 1 | 1 |
| Unit no 19 | 1 | 1 |
| Unit no 20 | 1 | 1 |
| Unit no 21 | 1 | 1 |
| Unit no 22 | 1 | 1 |
| Unit no 23 | 1 | 1 |
| Unit no 24 and 25 | 1 | 1 |
| Unit no 26 | 1 | 1 |
| Unit no 27A and 27B | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 15.19 cr | Rs 5.17 cr |
| Unit no 4 and 7 | NA | Rs 2.42 cr | Rs 1.18 cr |
| Unit no 24 and 25 | NA | Rs 2.06 cr | Rs 46.34 lakh |
| Unit no 31 and 32 | NA | Rs 2.01 cr | Rs 1.22 cr |
| Unit no 2B and 03 | NA | Rs 1.97 cr | Rs 52.69 lakh |
| Unit no 29 and 30 | NA | Rs 1.86 cr | Rs 1.14 cr |
| Unit no 15 | NA | Rs 1.53 cr | Rs 96.56 lakh |
| Unit no 28A and 28B | NA | Rs 1.51 cr | Rs 66.50 lakh |
| Unit no 27A and 27B | NA | Rs 1.51 cr | Rs 84.54 lakh |
| Unit no 34A and 34B | NA | Rs 1.50 cr | Rs 81.47 lakh |
| Unit no 35A and 35B | NA | Rs 1.50 cr | Rs 81.28 lakh |
| Unit no 1 | NA | Rs 1.18 cr | Rs 71.38 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAJESH CHAUHAN |
| Engineer | NILESH RAMESH BHOIR |
| Chartered Accountant | UMANG DOSHI |
| Chartered Accountant | ATUL PURANI |
| Partner | Role in project |
|---|---|
| MOON VALLEY RESORTS LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Nov 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 May 2025 - Building plan approvalNot on the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
- Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 15 Dec 2028
Documents filed36
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Architect Certificate_31032026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Engineer Certificate_31032026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: C A Certificate_31032026.pdf | 24 Apr 2026 |
| Form 2A (FY 2025-2026)File: Quality Ass Certificate_31032026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate 13 12 2025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Engineer Certificate 31 12 2025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: C A Certificate_31122025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Architech Certificate 30092025.pdf | 17 Nov 2025 |
| Withdrawal Update Form 2File: Engineers certificate300925.pdf | 17 Nov 2025 |
| Withdrawal Update Form 3File: C A Certificate30092025.pdf | 17 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form5 of Rera31032025.pdf | 17 Nov 2025 |
| Withdrawal Update Form 1File: Architectu0027s Certificate-30 06 2025.pdf | 24 Jul 2025 |
| Withdrawal Update Form 2File: Engineers Certificate-30 06 2025.pdf | 24 Jul 2025 |
| Withdrawal Update Form 3File: C A Certificate-30 06 2025.pdf | 24 Jul 2025 |
| Withdrawal Update Form 1File: Architech Certificate.pdf | 23 May 2025 |
| Withdrawal Update Form 1File: Architech Certificate.pdf | 23 May 2025 |
| Withdrawal Update Form 2File: Enginner Certificate 31 03 2025.pdf | 23 May 2025 |
| Withdrawal Update Form 2File: Enginner Certificate 31 03 2025.pdf | 23 May 2025 |
| Withdrawal Update Form 3File: C A Certificate-31 03 2025.pdf | 23 May 2025 |
| Withdrawal Update Form 3File: C A Certificate-31 03 2025.pdf | 23 May 2025 |
| Layout approval | 22 May 2025 |
| Layout approval | 22 May 2025 |
| Form 3File: C A Certificate-31 03 2025.pdf | 21 May 2025 |
| Form 1File: Architect Certificate-31 3 2025.pdf | 21 May 2025 |
| Disclosure of Sold and Booked InventoryFile: Promotor Certificate-31 03 2025.pdf | 21 May 2025 |
| Form 2File: Enginner Certificate 31 03 2025.pdf | 21 May 2025 |
| OthersFile: Quality Assurance Certificate- 31 03 2025.pdf | 21 May 2025 |
| Form 2A (FY 2024-2025) | 21 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architech Certificate.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf | 27 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Promotor Certificate.pdf | 27 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate.pdf | 27 Jan 2025 |
| Copy of the legal title reportFile: ilovepdf_merged (5).pdf | 18 Nov 2024 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale (2) (1).pdf | 18 Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 36 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep The Doorways on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near LONAVALA13,700+ in Pune
CANARY FARMS
CANARY FARMS
HRIDAAN HEIGHTS
R SQUARE BUILDERS AND DEVELOPERS
Amoda Reserve - South Park
Kalpataru Properties (Thane) Private Limit
Nakshatra Valley
Hariom Sai Developers
MANTRA DIVINE PHASE 2
MANTRA UNIVERSE PRIVATE LIMITED
EMERALD VILLAS
ASHWIN ARVIND SANGHVI
Builder: MOON VALLEY RESORTS LLP
MOON VALLEY RESORTS LLP has 1 registration on MahaRERA, including The Doorways. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if The Doorways is delayed beyond 15 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Doorways?
The registered promoter entity is MOON VALLEY RESORTS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Doorways?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for The Doorways?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Doorways?
The professionals named in the filing: Architect: RAJESH CHAUHAN; Engineer: NILESH RAMESH BHOIR; Chartered Accountant: UMANG DOSHI; Chartered Accountant: ATUL PURANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Doorways?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback