Home / Browse projects / Pune, Maharashtra / HRIDAAN HEIGHTS
HRIDAAN HEIGHTS
By R SQUARE BUILDERS AND DEVELOPERS
RG-MH-21115 · RERA P52100010232 · Last updated on MahaRERA portal: 25 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 72 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HRIDAAN HEIGHTS is a Others project by R SQUARE BUILDERS AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100010232 on 24 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 72 months from the original filing. 8 of the 203 units on this registration are recorded sold or booked, and 21 of 55 construction stages are filed complete.
At a glance
Project
- NameHRIDAAN HEIGHTS
- TypeOthers
- Location
- NH 48
- NEAR GARUD VIHAR
- Kamshet
- Mawal
- Pune
- 410401
- Pincode410401
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100010232
- ReraGenie IDRG-MH-21115
Builder
- NameR SQUARE BUILDERS AND DEVELOPERS
- Entity typePartnership
- PartnerRAHUL DINESH PATEL
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Aug 2017
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2022)
- Buildings5 building records
- Documents filed109 files
Current status
Figures as on 25 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 9 | 7 | 35 | 0 | 35 |
| WING B | NA | 9 | 7 | 35 | 0 | 35 |
| WING C | NA | 9 | 7 | 56 | 0 | 56 |
| COMMERCIAL | NA | 3 | 3 | 0 | 21 | 21 |
| WING D | NA | 9 | 7 | 56 | 0 | 56 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 85%.
WING A62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B62%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING C29%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 12% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
COMMERCIAL46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING D18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING A | 9 | 0 | 9 |
| WING B | 9 | 0 | 9 |
| WING C | 12 | 0 | 12 |
| COMMERCIAL | 0 | 12 | 12 |
| WING D | 12 | 0 | 12 |
Land and ownership11
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| RAMCHANDR BABANRAO DHAMALE | Kamshet | Pune |
| VILAS RAGHUNATH DHAMALE | Kamshet | Pune |
| SANJAY BABANRAO DHAMALE | Kamshet | Pune |
| SACHIN ANKUSH DHAMALE | Kamshet | Pune |
| RAVI RAGHUNATH DHAMALE | Kamshet | Pune |
| KALIDAS GANPAT DHAMALE | Kamshet | Pune |
| RAGHUNATH SHRIPATI DHAMALE | Sangise | Pune |
| MURUTI SHRIPATI DHAMALE | Sangise | Pune |
| NITIN MOHAN DHAMALE | Sangise | Pune |
| DILIP MARUTI DHAMALE | Takave Kh. | Pune |
| BALASAHEB MARUTI DHAMALE | Khadakale (CT) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING C | NA | Rs 5.16 cr | Rs 40.85 lakh |
| WING D | NA | Rs 5.16 cr | Rs 20.45 lakh |
| WING A | NA | Rs 4.09 cr | Rs 3.43 cr |
| WING B | NA | Rs 4.09 cr | Rs 3.43 cr |
| - | NA | Rs 2.17 cr | Rs 25.00 lakh |
| COMMERCIAL | NA | Rs 1.70 cr | Rs 74.00 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DHARMESH BHALANI (M/S DESTINATION ARCHITECTURE INTERIOR DESIGNS) |
| Architect | DESTINATION ARCHITECTURE INTERIOR DESIGNS |
| Engineer | SAMARTH AGARWAL |
| Chartered Accountant | CA HITESH M SHAH |
| Chartered Accountant | CA JYOTI B GAJRA |
| Chartered Accountant | Pratik Ramesh Vora |
| Partner | Role in project |
|---|---|
| R SQUARE BUILDERS AND DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReason delayed due lack of labour post covid -19 lockdowns and sluggishness in the market
Reason as filed by the promoterDue to Covid the work had to be shut down for approximately 2 years. Also, after that due to financial problem the project was delayed.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed109
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1.pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1..pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Q4.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Q4.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: FORM3 25-26.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: FORM3 25-26.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 2025-26..pdf | 25 Jun 2026 |
| Form 1File: Form 1 Q4.pdf | 24 Jun 2026 |
| Form 2File: Form 2 Q4.pdf | 24 Jun 2026 |
| Form 3File: Form 3 Q4 2025-26_compressed.pdf | 24 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Inventory sold booked.pdf | 24 Jun 2026 |
| Form 1File: FORM1 Q3 25-26.pdf | 9 Feb 2026 |
| Form 2File: FORM2 Q3 25-26.pdf | 9 Feb 2026 |
| Form 3File: FORM3 Q3 25-26.pdf | 9 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Inventory Letter.pdf | 9 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form-5..pdf | 1 Dec 2025 |
| Form 1File: final form 1.pdf | 28 Jun 2025 |
| Form 2File: Final FORM 2.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 3File: Final form 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 2File: Final form 2.pdf | 28 Jun 2025 |
| Form 1File: FORM 1.pdf | 28 Jun 2025 |
| Form 3File: Final form 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 2File: Final form 2.pdf | 28 Jun 2025 |
| Form 1File: FORM 1.pdf | 28 Jun 2025 |
| Form 3File: final form 3.pdf | 28 Jun 2025 |
| Form 2File: Final form 2.pdf | 28 Jun 2025 |
| Form 1File: FORM 1.pdf | 28 Jun 2025 |
| Form 3File: final form 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 1File: FORM 1.pdf | 28 Jun 2025 |
| Form 2File: Final form 2.pdf | 28 Jun 2025 |
| Form 3File: Final form 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 1File: FORM 1.pdf | 28 Jun 2025 |
| Form 2File: FORM 2.pdf | 28 Jun 2025 |
| Form 3File: Final FORM 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Letter.pdf | 28 Jun 2025 |
| Form 1File: Form 1 dec-24.pdf | 28 Jun 2025 |
| Form 2File: Form 2 dec-24.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 3File: FInal FORM 3.pdf | 28 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory Sold Details.pdf | 28 Jun 2025 |
| Form 1File: Form 1 march-25.pdf | 28 Jun 2025 |
| Form 2File: Form 2 march-25.pdf | 28 Jun 2025 |
| Form 3File: FInal FORM 3.pdf | 28 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 20 Dec 2024 |
| Certificates of CA (Form 3)File: Final FORM 3.pdf | 20 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 20 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Sold Letter.pdf | 20 Dec 2024 |
| Declaration about Commencement CertificateFile: Declaration Commecement Certificate.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A March 24.pdf | 20 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A.pdf | 17 Dec 2024 |
| Certificates of CA (Form 3)File: final form 3-4.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: final form 3-5.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: final form 3-3.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: final form 3-2.pdf | 30 Nov 2024 |
| Certificates of CA (Form 3)File: final form 3-1.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-5.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-4.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-3.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-2.pdf | 30 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-1.pdf | 30 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory sold letter.pdf | 30 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 30 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_.pdf | 30 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_.pdf | 30 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_.pdf | 30 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_.pdf | 30 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_.pdf | 30 Oct 2024 |
| Declaration in FORM BFile: form B.pdf | 26 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_.pdf | 26 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 109 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep HRIDAAN HEIGHTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR GARUD VIHAR13,700+ in Pune
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
CANARY FARMS
CANARY FARMS
Amoda Reserve - South Park
Kalpataru Properties (Thane) Private Limit
Nakshatra Valley
Hariom Sai Developers
MANTRA DIVINE PHASE 2
MANTRA UNIVERSE PRIVATE LIMITED
EMERALD VILLAS
ASHWIN ARVIND SANGHVI
Manorath
Samarth Realty
Builder: R SQUARE BUILDERS AND DEVELOPERS
R SQUARE BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including HRIDAAN HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if HRIDAAN HEIGHTS is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HRIDAAN HEIGHTS?
The registered promoter entity is R SQUARE BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HRIDAAN HEIGHTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for HRIDAAN HEIGHTS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HRIDAAN HEIGHTS?
The professionals named in the filing: Architect: DHARMESH BHALANI (M/S DESTINATION ARCHITECTURE INTERIOR DESIGNS); Architect: DESTINATION ARCHITECTURE INTERIOR DESIGNS; Engineer: SAMARTH AGARWAL; Chartered Accountant: CA HITESH M SHAH; Chartered Accountant: CA JYOTI B GAJRA; Chartered Accountant: Pratik Ramesh Vora. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HRIDAAN HEIGHTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback