THE COURTYARD PHASE 3B
RG-MH-33046 · RERA P49600000182 · Last updated on MahaRERA portal: 9 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations.
See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE COURTYARD PHASE 3B is a Residential / Group Housing project by M/s LIVINGDWELL ENTERPRISE in Dadra & Nagar Haveli, registered with MahaRERA as P49600000182 on 16 Jun 2025. Possession is promised by 31 Mar 2030. 0 of the 10 units on this registration are recorded sold or booked, and 99 of 110 construction stages are filed complete.
At a glance
Project
- NameTHE COURTYARD PHASE 3B
- TypeResidential / Group Housing
- Location
- AMLI
- SILVASSA
- Dadra & Nagar Haveli
- 396230
- Pincode396230
- RERA no.P49600000182
- ReraGenie IDRG-MH-33046
Builder
- NameM/s LIVINGDWELL ENTERPRISE
- Entity typePartnership
- PartnersDAYABHAI NARANBHAI GUDRASIA, CHANABHAI NARANBHAI GUDRASIA, SANJAY DAYABHAI GUDRASIA, JAYANTIBHAI RAGHAVBHAI GUDRASIA
- Other registrations4 more →
- Completed3 of 5
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Jun 2025
- Promised completion31 Mar 2030
- Revised completionNone
- Buildings10 building records
- Documents filed45 files
Current status
Figures as on 9 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUNGLOW NO 1 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 4 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 5 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 6 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 7 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 14 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 17 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 19 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 56 | NA | 4 | 3 | 1 | 0 | 1 |
| BUNGLOW NO 58 | NA | 4 | 3 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building10
As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
99 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is External plumbing and external plaster, at 50%.
BUNGLOW NO 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 691%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 791%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 1486%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 1791%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 1991%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 5691%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGLOW NO 5891%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed22
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUNGLOW NO 1 | 1 | 3 | 4 |
| BUNGLOW NO 4 | 1 | 1 | 2 |
| BUNGLOW NO 5 | 1 | 1 | 2 |
| BUNGLOW NO 6 | 1 | 1 | 2 |
| BUNGLOW NO 7 | 1 | 1 | 2 |
| BUNGLOW NO 14 | 1 | 1 | 2 |
| BUNGLOW NO 17 | 1 | 1 | 2 |
| BUNGLOW NO 19 | 1 | 1 | 2 |
| BUNGLOW NO 56 | 1 | 1 | 2 |
| BUNGLOW NO 58 | 1 | 1 | 2 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUNGLOW NO 1 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 4 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 5 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 6 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 7 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 14 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 17 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 19 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 56 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| BUNGLOW NO 58 | NA | Rs 62.50 lakh | Rs 62.50 lakh |
| - | NA | Rs 62.50 lakh | Rs 62.50 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARC HARDIK PANCHAL |
| Architect | HARDIK PANCHAL |
| Engineer | ANIL PATEL |
| Chartered Accountant | VARUN JAIN |
| Chartered Accountant | SHAILNEDRA JAIN |
| Partner | Role in project |
|---|---|
| M/s LIVINGDWELL ENTERPRISE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Mar 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2030
Documents filed45
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 LDE PH 3B.pdf | 9 Jun 2026 |
| Withdrawal Update Form 2File: LDE PHASE 3B FORM 2 ENG CERT 2026.pdf | 9 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Living Dwell Enterprise Phase 3B 31-12-2025.pdf | 9 Jun 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: DECLARATION FOR LDE PH 3 B.pdf | 12 Apr 2025 |
| Other - TechnicalFile: combine 4 and 5 plot - converted.pdf | 8 Apr 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: BANK FORMAT A COURTYARD 3B-1.pdf | 2 Apr 2025 |
| Other - TechnicalFile: PHASE 3B LAYOUT - converted.pdf | 2 Apr 2025 |
| Other - TechnicalFile: LDE_3B_7_12-1 - converted.pdf | 1 Apr 2025 |
| Declaration in FORM BFile: FORM B LDE PHASE 3B - converted.pdf | 27 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3) (UT)File: SCAN_20250326_183343111-1.pdf | 26 Mar 2025 |
| Other - TechnicalFile: PLOT 17.pdf | 26 Mar 2025 |
| Other - TechnicalFile: DECLARATION-2.pdf | 26 Mar 2025 |
| Building plan approvalFile: PLOT17.pdf | 25 Mar 2025 |
| Building Plan Approval (IOD)File: PLOT17.pdf | 25 Mar 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE FOR SECUREDUNSECURED FINANCE AVAILED FOR THE PROJECT.pdf | 21 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1) (UT)File: FORM 1 ARCH FOR LDE PHASE 3B - converted.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2) (UT)File: FORM NO 2 FOR LDE THE COURTYARD PHASE3B.pdf | 20 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf | 19 Mar 2025 |
| Copy of the legal title reportFile: PHASE 3B LDE TITLE REPORT PLOT NO 1,4,5,6,7,14,17,19,56,58 - converted.pdf | 11 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: LDE ENCUMBRANCE CERTIFICATE LAND.pdf | 11 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: LDE ENCUMBRANCE CERTIFICATE LANDPHASE 3B - converted.pdf | 11 Mar 2025 |
| Details of encumbrances concerned to LegalFile: LDE ENCUMBRANCE CERTIFICATE LAND.pdf | 11 Mar 2025 |
| Details of encumbrances concerned to LegalFile: LDE ENCUMBRANCE CERTIFICATE LANDPHASE 3B - converted.pdf | 11 Mar 2025 |
| Layout approvalFile: LAYOUT PLAN 3B.pdf | 9 Mar 2025 |
| Building plan approvalFile: building plan phase 3b - converted.pdf | 9 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: PHASE 3B NO ENCUMBERANCE.pdf | 9 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN 3B.pdf | 9 Mar 2025 |
| Building Plan Approval (IOD)File: building plan phase 3b - converted.pdf | 9 Mar 2025 |
| CERSAI detailsFile: PHASE 3B CERSAI UNDERTAKING.pdf | 9 Mar 2025 |
| Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf | 9 Mar 2025 |
| Details of encumbrances concerned to LegalFile: PHASE 3B NO ENCUMBERANCE.pdf | 9 Mar 2025 |
| Other - TechnicalFile: PHASE 3B COMBINEPLOTS.pdf | 9 Mar 2025 |
| Other - TechnicalFile: PHASE 3B LAYOUT AND DECLARATION .pdf | 9 Mar 2025 |
| Other - TechnicalFile: PHASE 3B ANNEXURE A.pdf | 9 Mar 2025 |
| Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf | 9 Mar 2025 |
| Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 8 Mar 2025 |
| Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf | 8 Mar 2025 |
| Annual Report / Audited Financial Statements for the immediately preceding three financial yearsFile: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) (UT).pdf | 8 Mar 2025 |
| PAN CardFile: LDE pancard.pdf | 8 Mar 2025 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf | 8 Mar 2025 |
| Commencement CertificatesFile: PHASE 3B CP.pdf | 8 Mar 2025 |
| Other - LegalFile: LDE PURCHASE DEED PLOT NO 1,4,5,6,7,14,17,19,56,58_.pdf | 8 Mar 2025 |
| Other - LegalFile: LDE_3B_7_12_.pdf | 8 Mar 2025 |
| CERSAI detailsFile: cersai report phase3b.pdf | 8 Mar 2025 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf | 8 Mar 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dadra & Nagar Haveli
Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 4 other registrations, which the RERA portal never shows together
- All 45 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep THE COURTYARD PHASE 3B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SILVASSA210+ in Dadra & Nagar Haveli
PRAMUKH SHIVANTA
ROYAL ENTERPRISE
SHASHIKALP SAROVAR
AKS BUILDERS AND DEVELOPERES
Ekdant Silver Oak
Ekdant Developers
Nagjua Ananta
MICROMEGA PROJECTS
ROYAL VIEW-II
M & P DEVELOPERS
PARADISE ONE
JMB REALTY
See every Dadra & Nagar Haveli project, with the district possession charts
Builder: M/s LIVINGDWELL ENTERPRISE
M/s LIVINGDWELL ENTERPRISE has 5 registrations on MahaRERA, including THE COURTYARD 41 TO 45 and THE COURTYARD PHASE2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.
Frequently asked questions
What are my rights if THE COURTYARD PHASE 3B is delayed beyond 31 Mar 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE COURTYARD PHASE 3B?
The registered promoter entity is M/s LIVINGDWELL ENTERPRISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE COURTYARD PHASE 3B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE COURTYARD PHASE 3B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE COURTYARD PHASE 3B?
The professionals named in the filing: Architect: ARC HARDIK PANCHAL; Architect: HARDIK PANCHAL; Engineer: ANIL PATEL; Chartered Accountant: VARUN JAIN; Chartered Accountant: SHAILNEDRA JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE COURTYARD PHASE 3B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.