Home / Browse projects / Pune, Maharashtra / The Cliff Garden-Phase 2A

Registration lapsed No litigation declared Residential / Group Housing project

The Cliff Garden-Phase 2A

By VH Township Private Limited

RG-MH-17137 · RERA P52100028926 · Last updated on MahaRERA portal: 3 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 90%
1Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

The Cliff Garden-Phase 2A is a Residential / Group Housing project by VH Township Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100028926 on 15 Apr 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameThe Cliff Garden-Phase 2A
  • TypeResidential / Group Housing
  • Location
    • Maan Pirangut Road
    • Maan
    • Hinjawadi
    • Man
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100028926
  • ReraGenie IDRG-MH-17137

Builder

  • NameVH Township Private Limited
  • Entity typeCompany
  • CINU45400MH2007PTC171668
  • DirectorPrasanta Kumar Biswal
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredApr 2021PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Apr 2021
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed88 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing INA220000
Wing JNA220000
Wing KNA220000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 3 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 90%.

Wing I45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing J46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure62%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing K47%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure66%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 3 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes10%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Underground water tanks and pumpsYes20%

Parking filed560

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots560
Closed/Covered233
Open Space327
BuildingClosed/CoveredOpen SpaceTotal
Wing I6694160
Wing J11882200
Wing K49151200

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,296 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024

Approvals and building plan

Sanctioning authorityMaharashtra Industrial Development Corporation
Permissible FSI33312.58
Proposed, not sanctioned33,313 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJEHANGIR BUILDING, GROUND FLOOR, MG ROAD, MUMBAI 400001

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV K : a Architecture
EngineerJW Consultants LLP
EngineerUNiCORN M.E.P Consultants Pvt. Ltd.
EngineerM/s Bose Consultant
Chartered AccountantM/s Dutta & Co
PartnerRole in project
VH Township Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400290VH Township Private LimitedLalit VIjay01/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Jan 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Jan 2025

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: Clarification to MahaRera Letter dt 03032025.pdf3 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: Signed copy-Form 4 for VHTPL 2A.pdf23 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VHTPL Occupancy Cert Ph 2A.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert_Dec 24.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VHTPL CA Cert_Dec 24.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_31Dec24.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Sep24.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sep24.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_Sep 24.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VHTPL- Annual RERA Certificate - FY 2023-24 (1).pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VHTPL 2A- Architect certificate 30 June 2024.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_June 24.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Cert_June 24.pdf20 Jul 2024
Proforma of Allotment letterFile: Allotment Letter 13052024.pdf13 May 2024
Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy 13052024.pdf13 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Mar24_compressed.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 310324.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 310324.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22042023_compressed.pdf16 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 13042024-compressed.pdf16 Apr 2024
Proforma of Allotment letterFile: Allotment Letter.pdf8 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Sheet.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for IJK 311223.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 311223.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 311223.pdf18 Jan 2024
Copy of the legal title reportFile: Format A_Title Report 13122023.pdf21 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230930 - RERA Certificate for IJK_Architect Cert_compressed.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 300923.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Certificate Sep23.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual RERA CA Certificate signed by Pwc_260923.pdf28 Sep 2023
Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy 04092023 compressed.pdf12 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert_June23_compressed.pdf18 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Cert_June23.pdf18 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert_June23.pdf18 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf25 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 22042023.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230331-RERA Certificate for IJK_230410_120655_compressed.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 180423ENGINEERING CERTIFICATE PHASE II.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 180123 CA CERTIFICATE_1MB.pdf20 Apr 2023
Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy R1 (27 March 2023).pdf4 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 221231-RERA Certificate for IJK Oct-Dec 22_compressed.pdf23 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate_Dec 22.pdf23 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA CA Certificate_Dec 22.pdf23 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Phase 2A 22NOV2022.pdf22 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220930-RERA Certificate for IJK.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineer)_VHTPL_Ph 2_2A_Registration_F_300922_signed.pdf20 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(CA)_VHTPL_Ph 2_2A_Sep'22_signed.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual RERA certification sgined by Pwc.pdf30 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220630-RERA Certificate for IJK_compressed.pdf29 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_2A_Engineer Certificate_30062022_R.pdf29 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A .pdf29 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VHTPL_2A_CA Certificate_30062022.pdf29 Jul 2022
Copy of the legal title reportFile: Title Opinion VHTPL Phase 2 MahaRERA Format (20 June 2022)-compressed (1).pdf12 Jul 2022
Declaration about Commencement CertificateFile: MahaRERA Form D- VHTPL.pdf12 Jul 2022
Proforma of Allotment letterFile: Agreement Revised for RERA VHTPL Phase 2A (22 June 2022).pdf24 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220331-RERA Certificate-IJK_compressed.pdf3 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_Ph 2A_Engineer Certificate_Mar 2022.pdf3 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA compliance certf 310322.pdf3 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - RERA Certificate_compressed.pdf17 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf17 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Certificate Ph 2A_Dec 21__final compressed.pdf17 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 211207 - RERA Certificate (1).pdf10 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_Phase 2A_Engineer Certificate_Sep 2021.pdf10 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA RERA 02122021.pdf10 Dec 2021
Proforma of Allotment letterFile: Agreement Revised for RERA VHTPL Phase 2A (25 Oct 2021).pdf25 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Certificate - June 2021.pdf30 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - June 2021.pdf30 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - June 2021.pdf30 Sep 2021
Proforma of Allotment letterFile: Agreement VHTPL Phase 2A- July 16 2021.pdf16 Jul 2021
Disclosure of sold/ booked inventoryFile: RERA Sold Unsold - Phase 2A - 20May21.pdf25 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate along with Clarification letter.pdf5 Apr 2021
Building plan approvalFile: Building Plan approval drawing Wing I.pdf30 Mar 2021
Building plan approvalFile: Building Plan approval drawing Wing J and K.pdf30 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Plan approval drawing Wing I.pdf30 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Building Plan approval drawing Wing J and K.pdf30 Mar 2021
PAN CardFile: VHTPL New PAN05032020.pdf26 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 201113 - RERA Certificate for I J K-1-compressed_compressed.pdf18 Feb 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer_VHTPL_Ph 2_2A_Registration_F_31122020.pdf18 Feb 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_VHTPL_Ph 2_2A_Registration_311220_compressed.pdf18 Feb 2021
Proforma of Allotment letterFile: Agreement VHTPL Phase 2A.pdf18 Feb 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
The Cliff GardenR2-1 Pune Maan Hinjawadi224CompletedDec 2022Aug 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Cliff Garden-Phase 2A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Maan, Hinjawadi13,700+ in Pune

2 kmThe Cliff Garden-Phase 2Completed 27Lapsed / revoked 10Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 58 registered projects within 2 km.

Builder: VH Township Private Limited

VH Township Private Limited has 3 registrations on MahaRERA, including The Cliff Garden and The Cliff Garden. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that The Cliff Garden-Phase 2A shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if The Cliff Garden-Phase 2A is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Cliff Garden-Phase 2A?

The registered promoter entity is VH Township Private Limited, a company as per the filing. Its CIN U45400MH2007PTC171668 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Cliff Garden-Phase 2A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Cliff Garden-Phase 2A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for The Cliff Garden-Phase 2A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Cliff Garden-Phase 2A?

The professionals named in the filing: Architect: V K : a Architecture; Engineer: JW Consultants LLP; Engineer: UNiCORN M.E.P Consultants Pvt. Ltd.; Engineer: M/s Bose Consultant; Chartered Accountant: M/s Dutta & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Cliff Garden-Phase 2A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Cliff Garden-Phase 2A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Cliff Garden-Phase 2A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.