The Cliff Garden-Phase 2A
By VH Township Private Limited
RG-MH-17137 · RERA P52100028926 · Last updated on MahaRERA portal: 3 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
The Cliff Garden-Phase 2A is a Residential / Group Housing project by VH Township Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100028926 on 15 Apr 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameThe Cliff Garden-Phase 2A
- TypeResidential / Group Housing
- Location
- Maan Pirangut Road
- Maan
- Hinjawadi
- Man
- Mulshi
- Pune
- 411057
- Pincode411057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100028926
- ReraGenie IDRG-MH-17137
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Apr 2021
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings3 building records
- Documents filed88 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing I | NA | 22 | 0 | 0 | 0 | 0 |
| Wing J | NA | 22 | 0 | 0 | 0 | 0 |
| Wing K | NA | 22 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 3 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 90%.
Wing I45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 85% |
| Slabs of Super Structure | 62% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 15% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing J46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 85% |
| Slabs of Super Structure | 62% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing K47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 66% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 3 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 10% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Underground water tanks and pumps | Yes | 20% |
Parking filed560
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing I | 66 | 94 | 160 |
| Wing J | 118 | 82 | 200 |
| Wing K | 49 | 151 | 200 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | V K : a Architecture |
| Engineer | JW Consultants LLP |
| Engineer | UNiCORN M.E.P Consultants Pvt. Ltd. |
| Engineer | M/s Bose Consultant |
| Chartered Accountant | M/s Dutta & Co |
| Partner | Role in project |
|---|---|
| VH Township Private Limited | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400290 | VH Township Private Limited | Lalit VIjay | 01/10/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Dec 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Jan 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Mar 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 23 Jan 2025
Documents filed88
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: Clarification to MahaRera Letter dt 03032025.pdf | 3 Mar 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Signed copy-Form 4 for VHTPL 2A.pdf | 23 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VHTPL Occupancy Cert Ph 2A.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert_Dec 24.pdf | 17 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VHTPL CA Cert_Dec 24.pdf | 17 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_31Dec24.pdf | 17 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Sep24.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sep24.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_Sep 24.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: VHTPL- Annual RERA Certificate - FY 2023-24 (1).pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: VHTPL 2A- Architect certificate 30 June 2024.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert_June 24.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Cert_June 24.pdf | 20 Jul 2024 |
| Proforma of Allotment letterFile: Allotment Letter 13052024.pdf | 13 May 2024 |
| Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy 13052024.pdf | 13 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Mar24_compressed.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 310324.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 310324.pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22042023_compressed.pdf | 16 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 13042024-compressed.pdf | 16 Apr 2024 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 8 Feb 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Sheet.pdf | 8 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for IJK 311223.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 311223.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 311223.pdf | 18 Jan 2024 |
| Copy of the legal title reportFile: Format A_Title Report 13122023.pdf | 21 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230930 - RERA Certificate for IJK_Architect Cert_compressed.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate 300923.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Certificate Sep23.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual RERA CA Certificate signed by Pwc_260923.pdf | 28 Sep 2023 |
| Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy 04092023 compressed.pdf | 12 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert_June23_compressed.pdf | 18 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Cert_June23.pdf | 18 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert_June23.pdf | 18 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf | 25 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 22042023.pdf | 25 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 230331-RERA Certificate for IJK_230410_120655_compressed.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 180423ENGINEERING CERTIFICATE PHASE II.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 180123 CA CERTIFICATE_1MB.pdf | 20 Apr 2023 |
| Proforma of Agreement for saleFile: Agreement VHTPL Phase 2A Clean Copy R1 (27 March 2023).pdf | 4 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 221231-RERA Certificate for IJK Oct-Dec 22_compressed.pdf | 23 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate_Dec 22.pdf | 23 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA CA Certificate_Dec 22.pdf | 23 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Phase 2A 22NOV2022.pdf | 22 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220930-RERA Certificate for IJK.pdf | 20 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Engineer)_VHTPL_Ph 2_2A_Registration_F_300922_signed.pdf | 20 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3(CA)_VHTPL_Ph 2_2A_Sep'22_signed.pdf | 20 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual RERA certification sgined by Pwc.pdf | 30 Sep 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220630-RERA Certificate for IJK_compressed.pdf | 29 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_2A_Engineer Certificate_30062022_R.pdf | 29 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A .pdf | 29 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: VHTPL_2A_CA Certificate_30062022.pdf | 29 Jul 2022 |
| Copy of the legal title reportFile: Title Opinion VHTPL Phase 2 MahaRERA Format (20 June 2022)-compressed (1).pdf | 12 Jul 2022 |
| Declaration about Commencement CertificateFile: MahaRERA Form D- VHTPL.pdf | 12 Jul 2022 |
| Proforma of Allotment letterFile: Agreement Revised for RERA VHTPL Phase 2A (22 June 2022).pdf | 24 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 220331-RERA Certificate-IJK_compressed.pdf | 3 Jun 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_Ph 2A_Engineer Certificate_Mar 2022.pdf | 3 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA compliance certf 310322.pdf | 3 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - RERA Certificate_compressed.pdf | 17 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 17 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA Certificate Ph 2A_Dec 21__final compressed.pdf | 17 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 211207 - RERA Certificate (1).pdf | 10 Dec 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: VHTPL_Phase 2A_Engineer Certificate_Sep 2021.pdf | 10 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA RERA 02122021.pdf | 10 Dec 2021 |
| Proforma of Allotment letterFile: Agreement Revised for RERA VHTPL Phase 2A (25 Oct 2021).pdf | 25 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Certificate - June 2021.pdf | 30 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - June 2021.pdf | 30 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - June 2021.pdf | 30 Sep 2021 |
| Proforma of Allotment letterFile: Agreement VHTPL Phase 2A- July 16 2021.pdf | 16 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: RERA Sold Unsold - Phase 2A - 20May21.pdf | 25 May 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate along with Clarification letter.pdf | 5 Apr 2021 |
| Building plan approvalFile: Building Plan approval drawing Wing I.pdf | 30 Mar 2021 |
| Building plan approvalFile: Building Plan approval drawing Wing J and K.pdf | 30 Mar 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan approval drawing Wing I.pdf | 30 Mar 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan approval drawing Wing J and K.pdf | 30 Mar 2021 |
| PAN CardFile: VHTPL New PAN05032020.pdf | 26 Feb 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 201113 - RERA Certificate for I J K-1-compressed_compressed.pdf | 18 Feb 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer_VHTPL_Ph 2_2A_Registration_F_31122020.pdf | 18 Feb 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_VHTPL_Ph 2_2A_Registration_311220_compressed.pdf | 18 Feb 2021 |
| Proforma of Allotment letterFile: Agreement VHTPL Phase 2A.pdf | 18 Feb 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| The Cliff Garden | R2-1 Pune Maan Hinjawadi | 224 | Completed | Dec 2022 | Aug 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 88 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep The Cliff Garden-Phase 2A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Maan, Hinjawadi13,700+ in Pune
Filed coordinates, straight-line distance. 58 registered projects within 2 km.
Godrej Evergreen Square
Godrej Projects Development Limited
The Aqua Retreat at Godrej Park World
Maan-Hinje Township Developers Private Lim
The Gale at Godrej Park World
Maan-Hinje Township Developers LLP
VTP BELLISSIMO PHASE 1
MAGNITE DEVELOPERS PRIVATE LIMITED
Life Republic Sector R1 - 1st Avenue
KOLTE-PATIL DEVELOPERS LIMITED
The Greenfront at Godrej Park World
Maan Hinje Township Developers Private Lim
Builder: VH Township Private Limited
VH Township Private Limited has 3 registrations on MahaRERA, including The Cliff Garden and The Cliff Garden. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that The Cliff Garden-Phase 2A shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if The Cliff Garden-Phase 2A is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of The Cliff Garden-Phase 2A?
The registered promoter entity is VH Township Private Limited, a company as per the filing. Its CIN U45400MH2007PTC171668 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in The Cliff Garden-Phase 2A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against The Cliff Garden-Phase 2A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for The Cliff Garden-Phase 2A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at The Cliff Garden-Phase 2A?
The professionals named in the filing: Architect: V K : a Architecture; Engineer: JW Consultants LLP; Engineer: UNiCORN M.E.P Consultants Pvt. Ltd.; Engineer: M/s Bose Consultant; Chartered Accountant: M/s Dutta & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in The Cliff Garden-Phase 2A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback