THE CHALETS AVENUE

By ASSETS REALITY

RG-MH-08096 · RERA P51700008568 · Last updated on MahaRERA portal: 25 Aug 2026

Source: official MahaRERA filing

Red flags

  • 27 complaints at MahaRERA
  • Completion date moved by 112 months
  • 8 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 112 months from the original
34 of 36Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 90%
2 of 142Units unsoldnot recorded sold or booked
27Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

THE CHALETS AVENUE is a Residential / Group Housing project by ASSETS REALITY in Thane, Maharashtra, registered with MahaRERA as P51700008568 on 19 Aug 2017. Possession is promised by 31 Mar 2028. The completion date has moved by 112 months from the original filing. 140 of the 142 units on this registration are recorded sold or booked, and 34 of 36 construction stages are filed complete. 27 complaints are on record with the regulator.

At a glance

Project

  • NameTHE CHALETS AVENUE
  • TypeResidential / Group Housing
  • Location
    • Survey No. 12/1
    • Sonivali
    • Badlapur (M Cl)
    • Ambarnath
    • Thane
    • 421503
  • Pincode421503
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008568
  • ReraGenie IDRG-MH-08096

Builder

  • NameASSETS REALITY
  • Entity typePartnership
  • PartnersBIDYA SATYADEV TIWARI, Ritesh Mishra

Key dates

this monthRegisteredAug 2017First promiseNov 2018Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 30 Nov 2018)
  • Buildings4 building records
  • Documents filed143 files

Current status

99%140 of 142 units booked
91.5%Work done, per cost certificate

Figures as on 25 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE ANA22808
TYPE BNA113808
TYPE CNA113808
WING ANA9910612118

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 25 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

34 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 90%.

TYPE A100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE C100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING A97%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises87%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 25 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes90%
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16
BuildingClosed/CoveredTotal
TYPE B88
TYPE C88

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,000 sq m
Land owned byThe promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Mar 2026
LandownerVillageDistrict
RITESH MISHRABadlapur (M Cl)Thane

Approvals and building plan

Sanctioning authorityKulgaon Badalapur Municipal Corporation
Permissible FSI5032.0
Proposed, not sanctioned5,032 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 15.77 cr
Cost incurredRs 14.43 cr
Work done91.53%
BuildingWingEstimatedIncurred
WING ANARs 10.05 crRs 9.55 cr
-NARs 2.05 crRs 1.40 cr
TYPE CNARs 1.41 crRs 1.34 cr
TYPE BNARs 1.36 crRs 1.29 cr
TYPE ANARs 89.90 lakhRs 85.40 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM SQUARE ARCHITECTS PROP MUKESH B MORE
ArchitectPRAMOD PATIL AND ASSOCIATES
EngineerSanjay Ramsagar Yadav
EngineerSAD CONSULTANT DARSHAN KASTURE
EngineerPRAMOD KAMBLE
Chartered AccountantCA Murtuza Husain Holawala
Chartered AccountantNirupam And Associates
Chartered AccountantS K Mhatre & Associates
Chartered AccountantCA UTPAL DESAI
PartnerRole in project
ASSETS REALITY-

Extensions applied for8

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700005431Nov 2018 → Dec 2020

Reason as filed by the promoterWe undersigned members of Project The Chalets Avenue Wing A Association developed by Mr. Ritesh V. Mishra having MAHARERA Registration No. P51700008568 whose registration has been expired dated 30 November 2018. For Extortion purpose Serial RTI Activist cum white colour Extortionist Vinod Prakashnath Tiwari have filed series RTI applications and complaints against our project. Subsequently Kulgaon Badlapur Municipal Council issued work stop notice (Stay) against given project (Enclosed) with great hardship and time involved promter & developer Mr. Ritesh V. Mishra obtained stay vacate NOC from

EXT51700009871Nov 2018 → Mar 2022

Reason as filed by the promoterRespected Sir/Madam, I, Ritesh Virendra Mishra, promoter and developer of project - ‘The Chalets Avenue’, (bearing RERA registration number P1700008568) most respectfully sheweth as under - 1) Currently our project registration is active till 31 June 2021 and we have completed 92% of work at our site. However progress of work at site has been severely affected due to default in timely slab-wise payments from 76% of allottees as per the terms notified in the sale agreements. 2) Moreover, 40% of our allottees have secured loan from troubled NBFCs namely Indiabulls Housing Finance Ltd. (IHFL) and

EXT51700012422Nov 2018 → Jun 2023

Reason as filed by the promoterDue to covid 19 lock down many and almost 95% of allottees defaulted on their payments, still till date with great financial hardship we have been able to complete 95% of the work. And so complete remaining 5% of the work with OC we need only 10 months extension. So I Ritesh V. Mishra hereby request Hon'ble MAHARERA to grant us last 10 months extension which is till 30th June 2023. We undersigned members and clients having purchased Units in given project constitute around 70% of the units sold by developer Ritesh V. Mishra hereby request Honourable Maharashtra Real Estate Regulatory Authority

EXT51700019328Nov 2018 → Mar 2025

Reason as filed by the promoterProject overall is complete and project is ready for occupation too, but because of online process wherein OC application is not getting upload since last 9-10 months. We are not able to get OC. And all developers are facing same problem in whole of Badlapur and Ambernath. On written request of Allottees we are giving conditional possession to respective allottees. Many developers Enclosed are follow ups application from Badlapur Ambernath Builders Association. So kindly help us give extension till 31st March 2025.

EXT51700016776Nov 2018 → Sep 2023

Reason as filed by the promoterProject overall is complete and project is ready for occupation too, but because of online process wherein OC application is not getting uploaded since last 45 to 50 days we are not able to get OC. And all developers are facing same problem in Badlapur area. So we request Hon'ble MAHARERA to kindly grant extension for 3 more months so that we can obtain OC.

EXT51700017595Nov 2018 → Mar 2024

Reason as filed by the promoterProject overall is complete and project is almost ready for occupation too, but because of online process wherein OC application is not getting upload since last 5 months. We are not able to apply and get OC through online process. And all developers are facing same problem in whole of Badlapur and Ambernath. Enclosed are follow ups application from Badlapur Ambernath Builders Association. Also as required have completed and uploaded all the required compliances of Form 1, Form 2, Form 2A, Form 3, Form 5, Form B, Format B and Disclosure of Inventory. Dated 07th October 2023 with great efforts

EXT51700027766Nov 2018 → Mar 2026

Reason as filed by the promoter1.Project is 96% Complete 2. Consent of 67.61 % of Allotees uploaded for Extension 3. In Other tab No. 1 uploaded The Revised Form B and also in the main Application 4. In Other Tab No. 2 uploaded PERT Chart for the remaining completion work and also in Other Technical Tab of the Main Application 5. In Other Tab No. 3 Uploaded Explanatory Note for Delay in project Completion and project will be completed by 31/03/2026 6. In Other Tab 4 Uploaded Appendix H 7. QPR till dates are updated 8. Due to unavoidable circumstances project has been delay and it will be completed by 31/03/2026

EA14052620959Nov 2018 → Mar 2028

Reason as filed by the promoter1. The project stands at 90% completion. 2. The consent of 69.01% of allottees has been uploaded in support of this extension application. 3. Form B uploaded. 4. PERT for the remaining completion work is uploaded in the Application. 5. The Project got delayed due to following reasons:- Reason 1: The project has faced delays due to repeated complaints and RTI applications filed by certain defaulting allottees. Although the concerned authorities inspected the project and found no irregularities, the continuous complaints and regulatory proceedings delayed the plan revision and Occupancy Certific

Complaints filed with MahaRERA27

Case no.ComplainantRespondentFiled
CC006000000044180Yogesh Harishankar DubeyPankaj Trivedi19/04/2018
CC006000000023906GANESH J GAWADERITESH MISHRA26/03/2018
CC006000000057076Rosy S PettersAsset Reality, Mr. Ritesh Mishra, Mr. Pankaj Trivedi28/11/2018
CC006000000078285YOGESH SHIVAJI DESHMUKHM/S ASSETS REALTY28/02/2019
CC006000000078288GORAKSHA GENU TANDALEM/S ASSETS REALTY28/02/2019
CC006000000078290DILIP BALKRISHNA UPLEKARM/S ASSETS REALTY28/02/2019
CC006000000078292AMITA MUKESH SHINDEM/S ASSETS REALTY28/02/2019
CC006000000078293ASHISH PRAKASH SUTARM/S ASSETS REALTY28/02/2019
CC006000000078297KIRAN RAMKRISHNA SATAVM/S ASSETS REALTY28/02/2019
CC006000000078299PRIYANKA PRAVIN MANEM/S ASSETS REALTY28/02/2019
CC006000000078302SACHIN SHRIKANT PURANIKM/S ASSETS REALTY28/02/2019
CC006000000078303SANJU MANOHAR MAKAWANAM/S ASSETS REALTY28/02/2019
CC006000000078446Rupesh Rajaram MohiteAssets Realty12/03/2019
CC006000000078479Mr Rajkiran Gangaram IngoleM/s Assets Realty14/03/2019
CC006000000078500Balkrishna Vilas TareM/s Assets Realty15/03/2019
CC006000000078535Rajesh Suresh ShevareM/s Assets Realty18/03/2019
CC006000000078539Rajendra Balu PhukeM/s Assets Realty18/03/2019
CC006000000078542Pandharinath Daulat RautM/s Assets Realty18/03/2019
CC006000000078543Mrs Gayatri Mahadev Prasad SharmM/s Assets Realty18/03/2019
CC006000000078609The Consumer's Guidance & Protection SocietyM/S ASSETS REALTY22/03/2019
CC006000000196221BIRENDRA RAM KARAN SHUKLAM/S ASSETS REALITY04/03/2021
CC006000000344216Vinod Baban MirkuteM/s Assets Reality17/05/2023
CC006000000397492Pandharinath Daulat RautASSETS REALITY14/09/2023
CC12503106ASSETS REALITYBirendra Ramkaran Shukla and Neelam Birendra Shukla04/09/2025
CC12503142ASSETS REALITYVinod Baban Mirkute and Vaishali Vinod Mirkute06/09/2025
CC12503144ASSETS REALITYPandharinath Daulat Raut and Pratiksha Pandharinath Raut07/09/2025
CC12602485Birendra Ramkaran Shukla and Neelam Birendra ShuklaASSETS REALITY28/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Jun 2021

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A_FY 24-25.pdf25 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A_FY 25-26.pdf24 Aug 2026
Withdrawal Update Form 1File: Form 1_30-06-2026.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 THE CHALETS AVENUE.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3_30-06-2026.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 June 25.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 Sept 25.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 Dec 25.pdf14 May 2026
Withdrawal Update Form 1File: Form 1_31-03-2026.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 June 25.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Sept 25.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf14 May 2026
Withdrawal Update Form 2File: Form 2_31-03-2026.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Q1 Assets Reality June.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Q2 Assets Reality Sept.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Q2 Assets Reality Sept.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Q4 Assets Reality march 26.pdf14 May 2026
Form 1File: 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 10 Certificates of CA (Form 3).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 10 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 9 Certificates of CA (Form 3).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 9 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 8 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 8 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 7 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 5 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 6 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 6 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 5 Disclosure of sold_ booked inventory (1).pdf27 Mar 2026
Form 1File: 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 3 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 3File: 4 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 4 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Form 1File: 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf27 Mar 2026
Form 2File: 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1).pdf27 Mar 2026
Form 3File: 2 Certificates of CA (Form 3) (1).pdf27 Mar 2026
Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory.pdf27 Mar 2026
Declaration in FORM BFile: Chalets Avenue Form B_Affd cum Declaration_.pdf16 Jun 2025
Other - TechnicalFile: Chaleets Avenue PERT Chart CPM-PERT Chart_14-06-2025 (1).pdf16 Jun 2025
Declaration in FORM BFile: Form B_Affd cum Declaration_24-05-25.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form 1_Arch_31-03-2023.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Form 1_Arch_30-06-2023.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Form 1_Arch_30-09-2023.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Form 1_Arch_31-12-2023.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5 Form 1_Arch_31-03-2024.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6 Form 1_Arch_30-06-2024.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Form 1_Arch_31-09-2024.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8 Form 1_Arch_31-12-2024.pdf28 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9 Form 1_Arch_31-03-2025.pdf28 May 2025
Certificates of CA (Form 3)File: 4 Form 3_CA Certif_31-12-2023.pdf28 May 2025
Certificates of CA (Form 3)File: 9 Form 3_CA_Certif_31-03-2025.pdf28 May 2025
Certificates of CA (Form 3)File: 8 Form 3_CA_Certif_31-12-2024.pdf28 May 2025
Certificates of CA (Form 3)File: 7 Form 3_CA Certif_30-09-2024.pdf28 May 2025
Certificates of CA (Form 3)File: 6 Form 3_CA Certif_30-06-2024.pdf28 May 2025
Certificates of CA (Form 3)File: 5 Form 3_CA Certif_31-03-2024.pdf28 May 2025
Certificates of CA (Form 3)File: 2 Form 3_CA Certif_30-06-2023.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2_Engr Certif_30-06-2023.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 Form 2_Engr Certif_31-03-2025.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Form 2_Engr Certif_31-12-2024.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Form 2_Engr Certif_30-09-2024.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Form 2_Engr Certif_30-06-2024.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2_Engr Certif_31-03-2024.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2_Engr Certif_31-12-2023.pdf28 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Form 2_Engr Certif_30-09-2023.pdf28 May 2025

How this compares with Thane

99%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 112 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE CHALETS AVENUE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sonivali7,600+ in Thane

2 kmTHE CHALETS AVENUECompleted 44Lapsed / revoked 11Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 78 registered projects within 2 km.

Builder: ASSETS REALITY

ASSETS REALITY has 1 registration on MahaRERA, including THE CHALETS AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if THE CHALETS AVENUE is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE CHALETS AVENUE?

The registered promoter entity is ASSETS REALITY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE CHALETS AVENUE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE CHALETS AVENUE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE CHALETS AVENUE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE CHALETS AVENUE?

The professionals named in the filing: Architect: M SQUARE ARCHITECTS PROP MUKESH B MORE; Architect: PRAMOD PATIL AND ASSOCIATES; Engineer: Sanjay Ramsagar Yadav; Engineer: SAD CONSULTANT DARSHAN KASTURE; Engineer: PRAMOD KAMBLE; Chartered Accountant: CA Murtuza Husain Holawala. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE CHALETS AVENUE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE CHALETS AVENUE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE CHALETS AVENUE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.