ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / The Big World

Completed No litigation declared Commercial project

The Big World

By SOMAN SUN CITI

RG-MH-71522 · RERA P51700014517 · Last updated on MahaRERA portal: 5 Aug 2021

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2018Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 16 documents Report an error

The Big World is a Commercial project by SOMAN SUN CITI in Thane, Maharashtra, registered with MahaRERA as P51700014517 on 8 Dec 2017. The registration is recorded completed; possession was promised by 31 Dec 2018.

At a glance

Project

  • NameThe Big World
  • TypeCommercial
  • Location
    • Kalyan-Dombivali (M Corp.)
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700014517
  • ReraGenie IDRG-MH-71522

Builder

  • NameSOMAN SUN CITI
  • Entity typePartnership
  • PartnersAmrutlal G Shanklesha Through Marudhara Builders, Gulabrao Karanjule Through CITI BUILDCON PRIVATE LIMITED, Kishore M Soman Through Soman and Associates

Key dates

this monthRegisteredDec 2017PromisedDec 2018Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Dec 2017
  • Promised completion31 Dec 2018
  • Revised completionNone
  • Buildings1 building record
  • Documents filed16 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Big WorldNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

The Big World: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,769 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI677.06
Proposed, not sanctioned677 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMustafa Manzil, Shankar Rao Chowk, Kalyan

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDe- Con Consultants
EngineerC M Consultants
PartnerRole in project
SOMAN SUN CITI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001026Dec 2018 → Dec 2019

Reason as filed by the promoterThe project is under construction & we are trying at our best to complete it as early as possible with assured quality of service. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date 31/12/2018, but while estimating the proposed date we had not considered that there are two completed floors already existing on the premises, above which we are constructing the 3rd and 4th floor. We are facing many difficulties for movement of raw material for the project and restrictions on work timings. On the other hand there is also delay on

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Dec 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Dec 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Dec 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Aug 2021

Documents filed16

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION CERTIFICATE.pdf5 Aug 2021
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE FORM-4 001.pdf5 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Soman Sun Citi_Form 5_compressed.pdf31 Dec 2019
Certificates of CA (Form 5)File: soman sun citi.pdf15 Oct 2018
Building plan approvalFile: COMMENCEMENT CERTIFICATE.pdf4 Dec 2017
Layout approvalFile: LAYOUT.pdf4 Dec 2017
PAN CardFile: SSC PAN.pdf4 Dec 2017
Copy of the legal title reportFile: Title 1.pdf4 Dec 2017
Details of encumbrancesFile: NO ECNUMBRANCE.PDF4 Dec 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf4 Dec 2017
Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE.pdf4 Dec 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf4 Dec 2017
Declaration in FORM BFile: FORM B.PDF4 Dec 2017
Certificates of CA (Form 3)File: CA Certificate.PDF4 Dec 2017
Proforma of Allotment letterFile: Sample Agreement 1.pdf4 Dec 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.PDF4 Dec 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Big World on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kalyan-Dombivali (M Corp.)7,600+ in Thane

2 kmThe Big WorldCompleted 71Lapsed / revoked 54Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 243 registered projects within 2 km.

Builder: SOMAN SUN CITI

SOMAN SUN CITI has 1 registration on MahaRERA, including The Big World. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if The Big World is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Big World?

The registered promoter entity is SOMAN SUN CITI, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Big World?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Big World?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Big World?

The professionals named in the filing: Architect: De- Con Consultants; Engineer: C M Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Big World?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Big World. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Big World to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one