THARWANI SOLITAIRE PHASE IV

By ANIL HARDASMAL THARWANI

RG-MH-30293 · RERA P51700030172 · Last updated on MahaRERA portal: 8 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 3 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2026Possession promised3 months past this date
18 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 95%
123 of 208Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

THARWANI SOLITAIRE PHASE IV is a Residential / Group Housing project by ANIL HARDASMAL THARWANI in Thane, Maharashtra, registered with MahaRERA as P51700030172 on 5 Aug 2021. Possession was promised by 29 Jul 2026 and is now 3 months past that date. The completion date has moved by 24 months from the original filing. 85 of the 208 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete.

At a glance

Project

  • NameTHARWANI SOLITAIRE PHASE IV
  • TypeResidential / Group Housing
  • Location
    • KALYAN MURBAD ROAD
    • SHAHAD
    • mharal
    • Kalyan
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700030172
  • ReraGenie IDRG-MH-30293

Builder

  • NameANIL HARDASMAL THARWANI
  • Entity typeIndividual
  • Other registrations10 more →
  • Completed6 of 11
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

3 months past promisethis monthRegisteredAug 2021First promiseJul 2024Revised toJul 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2021
  • Promised completion29 Jul 2026
  • Revised completionRevised to 29 Jul 2026 (originally 31 Jul 2024)
  • Buildings3 building records
  • Documents filed108 files

Current status

41%85 of 208 units booked
101.7%Work done, per cost certificate

Figures as on 8 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOPAZNA191588088
SPINELNA191560060
VIVIANITENA191560060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 95%.

TOPAZ91%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SPINEL60%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)75%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VIVIANITE69%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)75%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Closed/Covered110
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
TOPAZ501060
SPINEL40545
VIVIANITE20525

Land and ownership25

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,163 sq m
Land owned byThe promoter, with other names on the file
Named landowners25
LandownerVillageDistrict
MURLIDHAR RAMCHANDRA PANVELKARAmbarnath(M Cl)Thane
MAYA MURLIDHAR PANVELKARAmbarnath(M Cl)Thane
MAHESH MURLIDHAR PANVELKARAmbarnath(M Cl)Thane
POONAM MAHESH PANVELKARAmbarnath(M Cl)Thane
MONESH MURLIDHAAR PANVELKARAmbarnath(M Cl)Thane
PRIYANKA MONESH PANVELKARAmbarnath(M Cl)Thane
VIJAY RAMCHANDRA PANVELKARAmbarnath(M Cl)Thane
SEEMA VIJAY PANVELKARAmbarnath(M Cl)Thane
RAHUL VIJAY PANVELKARAmbarnath(M Cl)Thane
PRIYANKA VIJAY PANVELKARAmbarnath(M Cl)Thane
SNEHA VIJAY PANVELKARAmbarnath(M Cl)Thane
NARAYAN RAMCHANDRA PANVELKARAmbarnath(M Cl)Thane
GEETA NARAYAN PANVELKARAmbarnath(M Cl)Thane
RAJASHREE NARAYAN PANVELKARAmbarnath(M Cl)Thane
PRITAM NARAYAN PANVELKARAmbarnath(M Cl)Thane
SHWETA PRITAM PANVELKARAmbarnath(M Cl)Thane
VISHWANATH RAMCHANDRA PANVELKARAmbarnath(M Cl)Thane
AHSALATA VISHWANATH PANVELKARAmbarnath(M Cl)Thane
SONALI VISHWANATH PANVELKARAmbarnath(M Cl)Thane
BHAGYASHREE ABHIJEET SHETEAmbarnath(M Cl)Thane
VINAYAK RAMCHANDRA PANVELKARAmbarnath(M Cl)Thane
NEETA VINAYAK PANVELKARAmbarnath(M Cl)Thane
VAISHALI VINAYAK PANVELKARAmbarnath(M Cl)Thane
YOGESH VINAYAK PANVELKARAmbarnath(M Cl)Thane
AMIT VINAYAK PANVELKARAmbarnath(M Cl)Thane

Approvals and building plan

Sanctioning authorityTOWN PLANNING AND DEVELOPMENT AUTHORITY, THANE
Permissible FSI24162.77
Proposed, not sanctioned24,163 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHADAKPADA THANE 421301
Estimated costRs 40.63 cr
Cost incurredRs 41.33 cr
Work done101.7%
BuildingWingEstimatedIncurred
TOPAZNARs 16.52 crRs 19.31 cr
SPINELNARs 11.70 crRs 10.71 cr
VIVIANITENARs 9.49 crRs 10.04 cr
-NARs 2.93 crRs 1.27 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDINESH BAJAJ
EngineerKIRAN SHARAD SURVE
Chartered AccountantSUNNY BHAGIA & ASSOCIATES
Chartered AccountantVINOD SANTOSHKUMAR DHANKANI
PartnerRole in project
ANIL HARDASMAL THARWANI-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019730Jul 2024 → Jul 2025

Reason as filed by the promoterDELAY IN OBTAINING ENVIRONMENT CLEARANCES AND OTHER CLEARANCES RESULTING INTO ULTIMATE DELAY IN PROJECT EXECUTION

EA16072502088Jul 2024 → Jul 2026

Reason as filed by the promoterDue to undue delay in obtaining environmental clearances and other clearances for Wing I and Wing J i.e Spine! and Vivianite resulting into an overall delay in project execution and implementation. Further, we have received Occupancy certificate for Wing H i.e. Topaz on 03° July, 2025 which we are enclosing for your reference.

Litigation declared2

CaseCourtStatus
RCC 217/2016KALYANCROSS EXAMINATION
MCA 114/2016KALYANARGUMENT

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Signed_Form 1_Tharwani Solitaire Phase IV_Mar 26.pdf8 Jul 2026
Withdrawal Update Form 2File: Signed_Form - 2 - Certificates of Engineer-Solitaire phase IV March 2026 Final.pdf8 Jul 2026
Withdrawal Update Form 3File: Final Form 3 Solitaire Ph IV_20032026.pdf8 Jul 2026
Form 2A (FY 2025-2026)File: SOLITAIRE PHASE IV_SIGNED FORM 2A_compressed.pdf23 Apr 2026
Form 2A (FY 2021-2022)File: Form 2A Solitaire Phase IV 2021-2022.pdf21 Mar 2026
Form 2A (FY 2022-2023)File: Form2A_SOLITAIRE phase 4_FY2223.pdf21 Mar 2026
Form 2A (FY 2023-2024)File: THARAWANI SOLITAIRE PHASE -IV.pdf21 Mar 2026
Withdrawal Update Form 1File: Form 1 Solitaire Ph IV_Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 2File: Form 2_Solitaire Phase IV Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 3File: Final Form 3-Solitaire Phase IV Dec 2025.pdf21 Feb 2026
Withdrawal Update Form 1File: Form 1_Solitaire Ph IV Sept 25.pdf20 Feb 2026
Withdrawal Update Form 2File: Form 2_Solitaire Phase IV Sep 2025.pdf20 Feb 2026
Withdrawal Update Form 3File: Final Form 3-Solitaire Phase IV Sep 2025.pdf20 Feb 2026
Withdrawal Update Form 1File: Form 1_Soltaire Ph IV 30062025.pdf5 Dec 2025
Withdrawal Update Form 2File: Form 2_Solitaire Ph IV 30062025.pdf5 Dec 2025
Withdrawal Update Form 3File: Scanned Form 3_Solitaire Ph IV June 2025_compressed.pdf5 Dec 2025
Form 5 (FY 2024-2025)File: FORM 5 _ THARWANI REALTY - SOLITAIRE PHASE IV.pdf11 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A_Solitaire Ph IV_2024-25.pdf4 Aug 2025
Form 1File: Solitaire-Form1.pdf10 Jun 2025
Form 2File: Form 2_Solitaire Ph IV 25032025.pdf10 Jun 2025
Form 3File: Final Form 3_Solitaire Ph IV March 2025.pdf10 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory.pdf10 Jun 2025
Self-declaration of Quarterly ProgressFile: Self Declaration for Quaterly Progress.pdf10 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 _Solitaire_31-12-2024.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Solitaire-Form1.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scanned Form 3_Solitaire Ph IV Dec 2024_compressed.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Solitaire Ph IV Dec 2024.pdf25 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 _Solitaire Ph IV_Sept 24.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scanned Form 3_Solitaire Ph IV_Sep 2024_compressed.pdf6 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Solitaire IV_June 2024.pdf31 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scanned Form 3 Solitaire Ph IV June 2024_compressed.pdf17 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5_Solitaire Ph IV on Letterhead.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: scan- solitaire phase-IV.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Solitaire Ph IV_Sep 2024.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Solitaire Phase IV.pdf29 Jul 2024
Layout approvalFile: 01 Revised Approved Plan with Phase IV highlighted.pdf4 Jul 2024
Building plan approvalFile: 02 H Wing Layout Plan_Part 1.pdf4 Jul 2024
Building plan approvalFile: 03 H Wing Layout Plan_Part 2.pdf4 Jul 2024
Building plan approvalFile: 04 I Wing Layout Plan.pdf4 Jul 2024
Building plan approvalFile: 05 J Wing Layout Plan.pdf4 Jul 2024
Copy of Layout Approval (in case of layout)File: 01 Revised Approved Plan with Phase IV highlighted.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 02 H Wing Layout Plan_Part 1.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 03 H Wing Layout Plan_Part 2.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 04 I Wing Layout Plan.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: 05 J Wing Layout Plan.pdf4 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: 06 Revised Commencement Certificate.pdf4 Jul 2024
Declaration about Commencement CertificateFile: 07 Declaration about Commencement Certificate_Form D.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 THARAWANI SOLITAIRE - IV_compressed.pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: THARAWANI SOLITAIRE PHASE -IV.pdf27 May 2024
Proforma of Agreement for saleFile: Tharwani solitaire phase IV- AFS.pdf27 May 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf10 May 2024
CERSAI detailsFile: NO SECURITY INTEREST.pdf10 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A-Dislcosure in Other Real Estate Organisation.pdf10 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A-Declaration about Seperate Bank Account details.pdf10 May 2024
Declaration in FORM BFile: Affidavit Cum Declaration.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory.pdf9 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 Solitaire Ph IV_March 2024.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Solitaire Ph IV.pdf7 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tharwani Solitaire Phase IV.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 2023-2024_Final with UDIN.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tharwani solitaire phase 4(2).pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Solitaire Ph IV Form 2.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 Solitaire Ph IV- Sep 2023 with UDIN.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SOLITAIRE PHASE 4 form 1.pdf13 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Final Form 5- Signed with UDIN.pdf29 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Final Form 5- Signed with UDIN.pdf29 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Solitaire phase 4 FORM 1.pdf27 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SOLITAIRE PHASE 4 FORM 2.pdf27 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3- Signed_compressed.pdf27 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phase IV.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q4_FY2022-2023_Solitaire Phase IV.pdf20 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q4_FY2022-2023_Solitaire Phase IV.pdf20 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 2022-2023_Final_Signed_22062023_compressed.pdf20 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A_SOLITAIRE phase 4_FY2223.pdf13 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A solitaire phase 4 2020 -2021.pdf29 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Solitaire Phase IV 2021-2022.pdf29 Apr 2023
Details of encumbrances concerned to FinanceFile: DocScanner 9 Mar 2023 5-44 pm.pdf9 Mar 2023
Details of encumbrances concerned to LegalFile: DocScanner 9 Mar 2023 5-44 pm.pdf9 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 June 22 solitaire ph 4 form 1.pdf14 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30 September 22 solitaire ph 4 form 1.pdf14 Feb 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
THARWANI ARIANA PHASE ISURVEY NO 133 1 AND 133 1 P VILLAGE CHIKHLOLI TALKUA AMBERNATH238CompletedDec 2016Dec 2016
RIVERDALE VISTASURVEY NO 25 HISSA NO 1 VILLAGE BARAVE TALUKA KALYAN188CompletedSep 2016Sep 2016
ROSEWOOD HEIGHTSPLOT NO 270 SECTOR 10 KHARGHAR NAVI MUMBAI234CompletedMar 2012Mar 2012

How this compares with Thane

41%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THARWANI SOLITAIRE PHASE IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHAHAD7,600+ in Thane

2 kmTHARWANI SOLITAIRE PHASECompleted 13Lapsed / revoked 15Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: ANIL HARDASMAL THARWANI

ANIL HARDASMAL THARWANI has 11 registrations on MahaRERA, including THARWANI ARIANA PHASE II and THARWANI ARIANA PHASE III. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that THARWANI SOLITAIRE PHASE IV shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THARWANI SOLITAIRE PHASE IV is delayed beyond 29 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THARWANI SOLITAIRE PHASE IV?

The registered promoter entity is ANIL HARDASMAL THARWANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THARWANI SOLITAIRE PHASE IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THARWANI SOLITAIRE PHASE IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THARWANI SOLITAIRE PHASE IV?

The professionals named in the filing: Architect: DINESH BAJAJ; Engineer: KIRAN SHARAD SURVE; Chartered Accountant: SUNNY BHAGIA & ASSOCIATES; Chartered Accountant: VINOD SANTOSHKUMAR DHANKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THARWANI SOLITAIRE PHASE IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THARWANI SOLITAIRE PHASE IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THARWANI SOLITAIRE PHASE IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.