Home / Browse projects / Thane, Maharashtra / THARWANI MAJESTIC TOWERS PHASE I

Registration lapsed No litigation declared Residential / Group Housing project

THARWANI MAJESTIC TOWERS PHASE I

By ANIL HARDASMAL THARWANI

RG-MH-15726 · RERA P51700023841 · Last updated on MahaRERA portal: 23 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 68%
34 of 248Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

THARWANI MAJESTIC TOWERS PHASE I is a Residential / Group Housing project by ANIL HARDASMAL THARWANI in Thane, Maharashtra, registered with MahaRERA as P51700023841 on 7 Jan 2020. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 214 of the 248 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameTHARWANI MAJESTIC TOWERS PHASE I
  • TypeResidential / Group Housing
  • Location
    • JHULELAL CHOWK
    • KALYAN
    • Kalyan-Dombivali (M Corp.)
    • Thane
    • 421301
  • Pincode421301
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700023841
  • ReraGenie IDRG-MH-15726

Builder

  • NameANIL HARDASMAL THARWANI
  • Entity typeIndividual
  • Other registrations10 more →
  • Completed6 of 11
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

10 months past promisethis monthRegisteredJan 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Jan 2020
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed114 files

Current status

86%214 of 248 units booked

Figures as on 23 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CELESTONA37312480248

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 68%.

CELESTO: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure68%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed290

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots290
Closed/Covered290

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation
Permissible FSI3992.83
Proposed, not sanctioned3,993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 NEERAJ PARK NR MOHAN PRIDE KALYAN MH 421301

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDECON CONSULTANT ARCHITECT AND DESIGNERS REGD VALUES AND PROJECT CONSULTANT
EngineerEPICON CONSULTANTS
EngineerKIRAN SHARAD WARE
Chartered AccountantSUNNY BHAGIA AND ASSOCIATESAND ASSOCIATES
Chartered AccountantVINOD DHANKANI
PartnerRole in project
ANIL HARDASMAL THARWANI-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12600728Pawan lokumal dhanwaniANIL HARDASMAL THARWANI08/02/2026
CC12601233Jiten Ganesh KunderANIL HARDASMAL THARWANI06/03/2026
CC12601117Bhimrao Dnyandeo RahateANIL HARDASMAL THARWANI01/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: MAJESTIC PHASE I_SIGNED FORM 2A.pdf23 Apr 2026
Form 2A (FY 2022-2023)File: Form2A_MAJESTIC TOWER phase 1_FY2223.pdf21 Mar 2026
Form 2A (FY 2023-2024)File: THARAWANI MAJESTIC TOWERS PHASE- I.pdf21 Mar 2026
Form 5 (FY 2021-2022)File: FORM 5 Tharwani Majestic Phase I.pdf3 Feb 2026
Form 5 (FY 2022-2023)File: Scanned Form 5- Final with DSC.pdf3 Feb 2026
Form 5 (FY 2023-2024)File: Final Form 5_Majestic Ph I on Letterhead.pdf3 Feb 2026
Form 1File: Form 1 Majestic Phase 1_Sep 2025.pdf24 Jan 2026
Form 2File: Form 2of Majestic Phase 1.pdf24 Jan 2026
Form 3File: Final Form 3 Majestic Towers Phase I_01062025 to 30092025.pdf24 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory of Majestic Phase 1 September-25.pdf24 Jan 2026
Form 1File: Form 1_Majestic Ph I Dec 2025.pdf24 Jan 2026
Form 2File: Form 2_Majestic Ph I Dec 25.pdf24 Jan 2026
Form 3File: Final Form 3 _Majestic Phase I_December_2025.pdf24 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory_Majestic Ph I 31122025_Q3.pdf24 Jan 2026
Form 1File: Form 1_Majestic Tower Ph I.pdf24 Jan 2026
Form 2File: Form 2_Majestic Phase 1_12022025.pdf24 Jan 2026
Form 3File: Scanned Final Form-Feb 2025.pdf24 Jan 2026
Disclosure of Sold and Booked InventoryFile: Scanned Final Form-Feb 2025.pdf24 Jan 2026
OthersFile: Majestic Phase 1 OC.pdf24 Jan 2026
Form 1File: Form 1_Majestic Ph I_30062025.pdf14 Jan 2026
Form 2File: Form 2_Majestic Ph I_31052025.pdf14 Jan 2026
Form 3File: Scanned Form 3_Majestic Phase I_31052025.pdf14 Jan 2026
Disclosure of Sold and Booked InventoryFile: Majestic Ph I_Sold Booked_31052025_compressed.pdf14 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A_Majestic Phase 1_2024-25.pdf14 Jan 2026
Form 5 (FY 2024-2025)File: Final Form 5_Majestic Phase I 202425.pdf14 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Majestic Ph I_30062025.pdf16 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scanned Form 3_Majestic Phase I_31052025_compressed.pdf12 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Majestic Phase 1_12022025.pdf12 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Majestic Ph I_31052025.pdf12 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Majestic Tower A Celesto.pdf26 Apr 2025
Building plan approvalFile: Revised Approved Building Plan_compressed.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Majestic Phase 1_Dec 2024.pdf19 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf19 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Revised Approved Building Plan_compressed.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_Majestic Tower Ph I_Dec 2024.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_Majestic Ph I_12022025.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Majestic Phase 1_Dec 2024.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Majestic Phase 1_Sept 2024.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Final Form 3_Majestic Tower Ph I_Sep 2024.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Majestic P1_June 2024.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL SCANNED FORM 3_compressed.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5_Majestic Ph I on Letterhead.pdf28 Nov 2024
Proforma of Agreement for saleFile: MAJESTIC PHASE 1-AGREEMENT FOR SALE.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Majestic Tower PH I_Sep 2024.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tharwani majestic Tower -phase 1.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 MAJESTIC PHASE-I_compressed.pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: THARAWANI MAJESTIC TOWERS PHASE- I.pdf27 May 2024
Proforma of Agreement for saleFile: Majestic Phase I AGREEMENT FOR SALE.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_Majestic Ph I_March 2024.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 -THARWANI MAJESTIC TOWER A.pdf1 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tharwani Majestic Towers Phase 1.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 2023-24 Majestic Phase I_Final.pdf20 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: tharwani majestic PHASE 1 (2).pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: tharwani majestic phase 1 Form 2.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 2023-24 Majestic Phase I_SignedwithUDIN.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MAJESTIC PHASE -1.pdf10 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3- Majestic Phase I.pdf30 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Scanned Form 5- Final with DSC.pdf30 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Scanned Form 5- Final with DSC.pdf30 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MAJESTIC TOWAR PHASE 1 Form 1.pdf13 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: tharwani majestic towar (A).pdf28 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_Q4_202223_Majestic Phase I.pdf22 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q4_202223_Majeshtic Phase I.pdf22 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 2022-23 Majestic Phase I_Final_13072023.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A_MAJESTIC TOWER phase 1_FY2223.pdf13 Jul 2023
OtherFile: consent reply merged_compressed.pdf16 May 2023
Building plan approvalFile: 23-12-2022_compressed.pdf8 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 23-12-2022_compressed.pdf8 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: DocScanner Apr 7, 2023 7-20 PM_compressed.pdf7 Apr 2023
CERSAI detailsFile: CERSAI_Search_Report_200265056008_For_Asset_Based_Search_31_03_2023_13_33_02_586.pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tharwani majestic ph-1 31-3-22.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Majestic Phase I Jun 22.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate Majestic Phase 1 Sept 22.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Majestic Phase I Dec 22.pdf16 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 2022-23 Majestic Phase I_Final_DSC.pdf16 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 2022-23 Majestic Phase I_Final_DSC.pdf16 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 2022-23 Majestic Phase I_Final_DSC.pdf16 Feb 2023
Details of encumbrances concerned to FinanceFile: DocScanner 15 Feb 2023 3-17 pm-2.pdf15 Feb 2023
Details of encumbrances concerned to LegalFile: DocScanner 15 Feb 2023 3-17 pm-2.pdf15 Feb 2023
Declaration about Commencement CertificateFile: DocScanner 14 Feb 2023 11-46 am.pdf14 Feb 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
THARWANI ARIANA PHASE ISURVEY NO 133 1 AND 133 P VILLAGE CHIKHLOLI TALUKA AMBERNATH238CompletedDec 2016Dec 2016
RIVERDALE VISTASURVEY NO 25 HISSA NO 1 VILLAGE BARAVE TALUKA KALYAN188CompletedSep 2016Sep 2016
ROSEWOOD HEIGHTSPLOT NO 270 SECTOR 10 KHARGHAR NAVI MUMBAI234CompletedMar 2012Mar 2012

How this compares with Thane

86%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THARWANI MAJESTIC TOWERS PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

2 kmTHARWANI MAJESTIC TOWERSCompleted 56Lapsed / revoked 53Other 96Dot size: filed unitsN

Filed coordinates, straight-line distance. 205 registered projects within 2 km.

Builder: ANIL HARDASMAL THARWANI

ANIL HARDASMAL THARWANI has 11 registrations on MahaRERA, including THARWANI ARIANA PHASE II and THARWANI ARIANA PHASE III. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that THARWANI MAJESTIC TOWERS PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THARWANI MAJESTIC TOWERS PHASE I is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THARWANI MAJESTIC TOWERS PHASE I?

The registered promoter entity is ANIL HARDASMAL THARWANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THARWANI MAJESTIC TOWERS PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THARWANI MAJESTIC TOWERS PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THARWANI MAJESTIC TOWERS PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THARWANI MAJESTIC TOWERS PHASE I?

The professionals named in the filing: Architect: DECON CONSULTANT ARCHITECT AND DESIGNERS REGD VALUES AND PROJECT CONSULTANT; Engineer: EPICON CONSULTANTS; Engineer: KIRAN SHARAD WARE; Chartered Accountant: SUNNY BHAGIA AND ASSOCIATESAND ASSOCIATES; Chartered Accountant: VINOD DHANKANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THARWANI MAJESTIC TOWERS PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THARWANI MAJESTIC TOWERS PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THARWANI MAJESTIC TOWERS PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.