Red flags

  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.
Jan 2030Possession promisedmoved 60 months from the original
40 of 77Construction stages doneacross 7 buildings; furthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

Thakrewadi is a Residential / Group Housing project by vyankatesh infraalliance in Chandrapur, Maharashtra, registered with MahaRERA as P50900019910 on 13 Mar 2019. Possession is promised by 1 Jan 2030. The completion date has moved by 60 months from the original filing.

At a glance

Project

  • NameThakrewadi
  • TypeResidential / Group Housing
  • Location
    • Wadgaon
    • Chandrapur (M Cl)
    • Chandrapur
    • 442401
  • Pincode442401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50900019910
  • ReraGenie IDRG-MH-58255

Builder

  • Namevyankatesh infraalliance
  • Entity typeOthers
  • Named personsChandrakant Namdeorao Wasade, Mrs Amrita Thakre
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2019First promiseJan 2025Revised toJan 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on13 Mar 2019
  • Promised completion1 Jan 2030
  • Revised completionRevised to 1 Jan 2030 (originally 15 Jan 2025)
  • Buildings7 building records
  • Documents filed84 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1NA20000
A2NA20000
Wing ANA60000
Wing BNA60000
Wing CNA60000
Wing DNA60000
Wing ENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 16 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of Lifts, at 90%.

A143%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A280%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Wing A28%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B27%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Wing E90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 16 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered5
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
A1011
A2011
Wing A112
Wing B112
Wing C112
Wing D112
Wing E112

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,785 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Vyankatesh InfraallianceChandrapur (M Cl)Chandrapur

Approvals and building plan

Permissible FSI7459.96
Proposed, not sanctioned6,333 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch pLOT NO 87/2 Tayde Bhavan Bapat Nagar Nagpur road Wadgaon,Chandrapur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Prashant Satpute
EngineerMr Akshay Thakre
Chartered AccountantMr Anjum Gous
PartnerRole in project
vyankatesh infraalliance-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50900025029Jan 2025 → Jan 2030

Reason as filed by the promoterDue to delay in OC

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 1 Jan 2030

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 form 1 Architect Certificate 31-12-2024.pdf10 Jan 2025
Certificates of CA (Form 3)File: form-3 CA certificate.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 15 form-2 Engineer's Certificate 31-12-2024.pdf10 Jan 2025
Disclosure of sold/ booked inventoryFile: 11_ Annexure-29-31-12-2024.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 form 1 -Architect's Certificate - 30-09-2024.pdf30 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 form- Architect's Certificate -30-06-2024.pdf30 Nov 2024
Certificates of CA (Form 3)File: From- 3 CA certificate - 30-09-2024.pdf30 Nov 2024
Certificates of CA (Form 3)File: From -3 CA Certificate 30-06-2024.pdf30 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 13 Form 2 30-06-2024.pdf30 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 14 form 2- Engineers certificate - 30-09-2024.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1form- 2 A - Engineer's certificate (Quality Assurance)31-03-2020.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1_Vyankatesh Form-5 - 19-20.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2_Vyankatesh Form-5 20-21.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2from- 2A Engineer's Certificate ( quality Assurance) 31-03-2021.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 9_11- Annexure-29 30-06-2023.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 14_11- Annexure-29 30-09-2024.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 13_11- Annexure-29 30-06-2024.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 12_11- Annexure-29 31-03-2024.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 11_11- Annexure-29 31-12-2023.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 10_11- Annexure-29 30-09-2023.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 8_11- Annexure-29 _31-03-2023.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 7_11- Annexure-29 31-12-2022.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 6_11- Annexure-29 30-09-2022.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 5_11- Annexure-29 30-06-2022.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 4_11- Annexure-29 31-03-2022.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 11- Annexure-29 31-03-2021.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 11- Annexure-29 31-12-2021.pdf30 Nov 2024
Disclosure of sold/ booked inventoryFile: 11- Annexure-29-31-03-2020.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 3_Vyankatesh Form-5 - 21-22.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 3 From- 2A - Engineers certificate (Quality Assurance) 31-03-2022.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 4 from- 2A Engineer's Certificate ( Quality Assurance)31-03-2023.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 4_Vyankatesh Form-5 - 22 - 23.pdf30 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5from 2A- Engineers certificate ( Quality Assurance) 31-03-2024.pdf30 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 5_Vyankatesh Form-5 - 23-24.pdf30 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 Form 1- Architect's Certificate 31-03-2024.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 form 1- Architect's Certificate 30-09-2023.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 form 1- Architect Certificate 30-06-2023.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Form 1- Architect's Certificate 31-12-2023.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form 3- 31-03-2024.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form 3 - 31-12-2023.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form 3 - 30-09-2034.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form 3- 30-06-2023.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 form 2- Engineer's certificate 30-06-2023.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 form 2- Engineer's certificate 30-09-2023.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 form 2 - Engineer's Certificate 30-12-2023.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 form-2 Engineer's Certificate 31-03-2024.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_FORM -1 (31-03-2020).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2_FORM-1 (31-03-2021).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3_FORM-1 (31-12-2021).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4_FORM-1 (31-03-2022).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5_FORM-1(30-06-2022).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6_FORM-1 (30-09-2022).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7_FORM-1 (31-12-2022).pdf3 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8_FORM-1 (31-03-2023).pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1_Annexure-B 31-03-2020.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Annexure- B 31-03-2021.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3_Annexure-B 31-12-2021.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4_Annexure-B 31-03-2022.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5_Annexure-B 30-06-2022.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6_Annexure-B 30-09-2022.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7_Annexure- B 31-12-2022.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8_Annexure-B 31-03-2023_.pdf3 Apr 2024
Certificates of CA (Form 3)File: 1_Doc Vyankatesh Infraalliance 31-03-2020.pdf23 Mar 2024
Certificates of CA (Form 3)File: 2_Doc Vyankatesh Infraalliance 31-03-2021.pdf23 Mar 2024
Certificates of CA (Form 3)File: 3_Doc Vyankatesh Infraalliance 31-12-2021.pdf23 Mar 2024
Certificates of CA (Form 3)File: 4_Doc Vyankatesh Infraalliance 31-03-2022.pdf23 Mar 2024
Certificates of CA (Form 3)File: 5_Doc Vyankatesh Infraalliance 30-06-2022.pdf23 Mar 2024
Certificates of CA (Form 3)File: 6_Doc Vyankatesh Infraalliance 30-09-2022.pdf23 Mar 2024
Certificates of CA (Form 3)File: 7_Doc Vyankatesh Infraalliance 31-12-2022.pdf23 Mar 2024
Certificates of CA (Form 3)File: 8_Doc Vyankatesh Infraalliance 31-03-2023.pdf23 Mar 2024
Declaration in FORM BFile: agreement.pdf8 Mar 2019
Building plan approvalFile: MAP 1-min_compressed_compressed-compressed.pdf2 Mar 2019
Layout approvalFile: lay out permission.pdf2 Mar 2019
PAN CardFile: Pan card cert.pdf2 Mar 2019
Copy of the legal title reportFile: serch report-min.pdf2 Mar 2019
Details of encumbrancesFile: vyankatesh.pdf2 Mar 2019
Copy of Layout Approval (in case of layout)File: lay out permission.pdf2 Mar 2019
Building Plan Approval (IOD)File: MAP 1-min_compressed_compressed-compressed.pdf2 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: comencment cert.pdf2 Mar 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
shreelaxmi Chamberscivil lines chandrapur11CompletedJul 2017Jun 2017

How this compares with Chandrapur

10%of Chandrapur projects moved their completion datethis one moved by 60 months
39%of Chandrapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.

Keep Thakrewadi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadgaon220+ in Chandrapur

2 kmThakrewadiCompleted 9Lapsed / revoked 9Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: vyankatesh infraalliance

vyankatesh infraalliance has 1 registration on MahaRERA, including Thakrewadi. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Chandrapur district page.

Frequently asked questions

What are my rights if Thakrewadi is delayed beyond 1 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Thakrewadi?

The registered promoter entity is vyankatesh infraalliance, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Thakrewadi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Thakrewadi?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Thakrewadi?

The professionals named in the filing: Architect: Mr Prashant Satpute; Engineer: Mr Akshay Thakre; Chartered Accountant: Mr Anjum Gous. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Thakrewadi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Thakrewadi. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Thakrewadi to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.