ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Terraform K - Residences

Registration lapsed Litigation declared Commercial project

Terraform K - Residences

By Money Magnum Constructions

RG-MH-10993 · RERA P51700002673 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 5 months past the filed date
  • Litigation declared, 24 cases
  • Completion date moved by 32 months
  • 4 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2026Possession promised5 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
8 of 69Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 257 documents Report an error

Terraform K - Residences is a Commercial project by Money Magnum Constructions in Thane, Maharashtra, registered with MahaRERA as P51700002673 on 2 Aug 2017. Possession was promised by 5 May 2026 and is now 5 months past that date. The completion date has moved by 32 months from the original filing. 61 of the 69 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameTerraform K - Residences
  • TypeCommercial
  • Location
    • KOLSHET ROAD
    • DHOKALI
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700002673
  • ReraGenie IDRG-MH-10993

Builder

  • NameMoney Magnum Constructions
  • Entity typePartnership
  • PartnersTosha Meet Pvt Ltd NA NA, Terraform Manjil Pvt Ltd NA NA, Money Magnum Nest Pvt Ltd NA NA, Nainesh Shah, Vimal Shah, Kishor Shah, Nainesh Shah, Money Magnum Nest Pvt Ltd NA NA, Vimal Shah, Tosha Meet Pvt Ltd NA NA, Kishor Shah, Terraform Manjil Pvt Ltd NA NA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

5 months past promisethis monthRegisteredAug 2017First promiseSep 2023Revised toMay 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Aug 2017
  • Promised completion5 May 2026
  • Revised completionRevised to 5 May 2026 (originally 30 Sep 2023)
  • Buildings1 building record
  • Documents filed257 files

Current status

88%61 of 69 units booked
71.0%Work done, per cost certificate

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Terraform K - Residences Project INA2206969

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Terraform K - Residences Project I: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed153

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots153
Closed/Covered153

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,237 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Sep 2025

Approvals and building plan

Permissible FSI43163.85
Proposed, not sanctioned2,405 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOpp Akbar Alys, Sion Tromaby Road, Chembur East, Mumbai -400071
Estimated costRs 24.69 cr
Cost incurredRs 17.54 cr
Work done71.04%
BuildingWingEstimatedIncurred
Terraform K - Residences Project INARs 24.69 crRs 17.54 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaakaar Architects
EngineerOmkar Hande
Chartered AccountantJ. D. Zatakia & Co.
Chartered AccountantJayesh S Vora
Chartered AccountantAnkit Goyanka & Associates
PartnerRole in project
Money Magnum Constructions-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017487Sep 2023 → Mar 2025

Reason as filed by the promoterTHE PROMOTERS OF THE COMPANY ARE SEEKING EXTENSION OF THE PROJECT DUE TO FOLLOWING REASONS:- 1. There was stay order by Court of Civil Judge, Thane in Regular Civil Suit case No. 251 of 2019 of Thane, on 25th day of June, 2019 due to which we were restrained from obtaining any permission for any further construction of the said Project or remaining part thereof till 01st day of July, 2020. 2. Due to sudden outbreak of the COVID - 19 pandemic by the order of Government of India only "Essential services" units were opened. Due to which our construction work got restricted and our project got del

EXT51700027975Sep 2023 → Sep 2025

Reason as filed by the promoterWe hereby apply for an Extension of the project completion timeline for the Real Estate Project “Terraform K - Residences” having project Registration No. P51700002673 for 6 (Six) Months, revising the project completion date from 30th March 2025 to 30th September 2025. The delay has occurred due to changes in planning following the introduction of the Unified Development Control and Promotion Regulations (UDCPR) and we have obtained revised Development Permission issued by the TMC on 08/04/2024. As we have achieved the @83% of the RCC construction of the project as completed Milestone of the P

EA30092517991Sep 2023 → Nov 2025

Reason as filed by the promoterExplanation on Part Occupation Certificate issued by Thane Municipal Corporation: The Build No. 21 is comprises of Ground & First Floor as Commercial, 2nd Floor as Service Slab and from 3rd to 23rd Floors as Residential Floors. As we had split the Building in Commercial and Residential separately and registered two different Real Estate Project in MahaRERA with two different completion date. The RERA Registration Number of Commercial portion (Ground and First floor) is P51700002673 and had 30/09/2025 as completion date and the RERA Registration Number of Residential portion (2nd to 23rd floor)

EA06022619748Sep 2023 → May 2026

Reason as filed by the promoterReason for Extension Application: To change the status of Project from “Laps” to “Active”, we are applying for Extension of Project. We hereby apply for an Extension of the Real Estate Project “Terraform K - Residences” having project Registration No. P51700002673 for 180 (One Hundred Eighty) Days (starting from 06/11/2025 till 05/05/2026). As we have obtained Occupation Certificate dated 06/11/2025, the Authority had granted the extension till 06/11/2025. Since the Occupation Certificate has been obtained and the extension application has been applied to regularize the Real Estate Project, we

Litigation declared24

CaseCourtStatus
346/2011High Court BombayFor Procurement of Judgment
Special Civil Suit No 709/2013In the Court of Civil Judge Senior Division ThaneClosed
Special Civil Suit No 710/2013In the Court of Civil Judge Senior Division ThaneClosed
Special Civil Suit No 711/2013In the Court of Civil Judge Senior Division ThaneClosed
Consumer Complaint No 678/2014District Consumer Disputes Redressal Forum ThaneClosed
SLP No 32570/2014Supreme CourtPENDING This case is not likely to affect this current project adversely
Special Civil Suit No 435/2016In the Court of Civil Judge Senior Division ThaneClosed
Consumer Complaint No 989/2017State Consumer Disputes Redressal Commission MaharashtraClosed
Consumer Complaint No 10/2018State Consumer Disputes Redressal Commission MaharashtraClosed
FA/1246/2018/2018National Consumer Forum DelhiPENDING This case is not likely to affect this current project adversely
FA/909/2018/2018National Consumer Forum DelhiPENDING This case is not likely to affect this current project adversely
FA/910/2018/2018National Consumer Forum DelhiPENDING This case is not likely to affect this current project adversely
Consumer Complaint No 578/2018State Consumer Disputes Redressal Commission MaharashtraPENDING This case is not likely to affect this current project adversely
5751/2018High Court BombayClosed
Execution on Application No 62/2018 in RBT/CC/17/1461/2018State Consumer Disputes Redressal Commission MaharashtraPENDING This case is not likely to affect this current project adversely
Execution on Application No 63/2018 in RBT/CC/17/1462/2018State Consumer Disputes Redressal Commission MaharashtraPENDING This case is not likely to affect this current project adversely
Consumer Complaint No 639/2019State Consumer Disputes Redressal Commission MaharashtraPENDING This case is not likely to affect this current project adversely
62/2020Additional District and Sessions Judge ThaneAs per Order of Hon Bom HC all proceedings between the parties pending before any judicial or non ju
367/2021 and IA No 3120/2021/2021High Court BombayAs per Order of Hon Bom HC all proceedings between the parties pending before any judicial or non ju
576/2022Dy District Registrar Co op SocietiesDisposed of
St No 23035/2023High Court BombayOngoing
10350/2023High Court BombayPENDING This case is not likely to affect this current project adversely
80/2024Deputy District Registrar Co op Societies ThanePending
346/2011High Court BombayOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 May 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed257

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 257 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 02_Withdrawal Application Form1_Signed.pdf14 Aug 2026
Withdrawal Update Form 2File: 03_Withdrawal Application Form2_Signed.pdf14 Aug 2026
Withdrawal Update Form 3File: 02_Withdrawal Application Form3 - Singed_CA_UKM.pdf14 Aug 2026
Form 5 (FY 2025-2026)File: 20260331-Form-5-K-Resi_10082026_CA_UM_Signed.pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form-2A_K-Resi_FY_2025-26_31072026.pdf1 Aug 2026
Withdrawal Update Form 1File: 02_Withdrawal Application Form1_Signed.pdf10 Jul 2026
Withdrawal Update Form 2File: 03_Withdrawal Application Form2_Signed.pdf10 Jul 2026
Withdrawal Update Form 3File: 02_Withdrawal Application Form3 - Singed_CA_UKM.pdf10 Jul 2026
Layout approvalFile: OC_K Residence_Plans_06112025.pdf8 May 2026
Withdrawal Update Form 1File: 02_Withdrawal Application Form1_Signed.pdf20 Apr 2026
Withdrawal Update Form 2File: 04_Withdrawal Application Form2_Signed.pdf20 Apr 2026
Withdrawal Update Form 3File: 04_Withdrawal Application Form3_Signed_CA_MMCs_BnW_15042026.pdf20 Apr 2026
Withdrawal Update Form 1File: 03_Form 1_K Residenses_20012026.pdf20 Jan 2026
Withdrawal Update Form 2File: 04_Form 2_K Residency_20012026.pdf20 Jan 2026
Withdrawal Update Form 3File: 04_Form 3_K Residences_20012026_Col.pdf20 Jan 2026
Withdrawal Update Form 1File: 07_Withdrawal Application Form1_from RERA Portal_03102025_Duly signed.pdf18 Oct 2025
Withdrawal Update Form 2File: 05_Withdrawal Application Form2_as on 300925_Signed by Engineer_By Promoter.pdf18 Oct 2025
Withdrawal Update Form 3File: 03_Withdrawal Application Form3_KR_Sign by CA__Promoter_Col_181025.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: RERA Form - 5 - K Residence Retail- 31 03 2025.pdf1 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A_Omkar Hande_FY2024-25_29092024_Signed.pdf29 Sep 2025
Form 2A (FY 2023-2024)File: Form 2A for FY 2023-24_K Residences.pdf29 Sep 2025
Form 5 (FY 2018-2019)File: 2019 09 17-Form-5-K-Resi.pdf28 Jul 2025
Form 5 (FY 2019-2020)File: 2020 09 29-Form-5-K-Resi.pdf28 Jul 2025
Form 5 (FY 2021-2022)File: 2022 09 27-Form-5-K-Resi.pdf28 Jul 2025
Form 5 (FY 2022-2023)File: 2023 09 25-Form-5-K-Resi.pdf28 Jul 2025
Form 5 (FY 2023-2024)File: 2024 09 30-Form-5-K-Resi.pdf28 Jul 2025
Form 1File: 2023 09 30-Form-1-K-Resi.pdf25 Jul 2025
Form 2File: 2023 09 30-Form-2-K-Resi.pdf25 Jul 2025
Form 3File: 2023 09 30-Form-3-K-Resi.pdf25 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2023 09 30 - Sold-Unsold K-Resi.pdf25 Jul 2025
Form 1File: 2023-03-31 Form 1 Terraform K Residences.pdf25 Jul 2025
Form 2File: 2023 03 31-Form-2-K-Resi.pdf25 Jul 2025
Form 3File: 2023 03 31-Form-3-K-Resi.pdf25 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2023 03 31 - Sold-Unsold-K-Resi.pdf25 Jul 2025
Form 5 (FY 2017-2018)File: 2018 09 12-Form-5-K-Resi.pdf25 Jul 2025
Form 1File: 20250331_Form 1_Saakar Architect_07042025.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Ph-I Quarter January to March 2025.pdf23 Jul 2025
Form 3File: Form 3 - K-Residence - March'25 - Singed Copy.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold data of Terraform K Residences 31032025.pdf23 Jul 2025
Form 1File: 2024-12-31 Form 1 Terraform K Residences.pdf23 Jul 2025
Form 2File: 2024 12 31 - Form-2-K-Residences.pdf23 Jul 2025
Form 3File: Form 3 - K Residence - Dec'24 - Singed Copy.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2025 01 04 - Sold-Unsold-K-Residences.pdf23 Jul 2025
Form 1File: 2024 10 01 - Form-1-K-Residences.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Ph-I Quarter July to September 2024.pdf23 Jul 2025
Form 3File: Form 3 - K Residence Retail - Sep'24 - Signed Copy.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2024 10 05 - Sold-Unsold-K-Residences.pdf23 Jul 2025
Form 1File: 30-06-2024 Form 1 Terraform K Residences.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Ph-I Quarter April to June 2024 (2).pdf23 Jul 2025
Form 3File: RERA Form 3 - K Residence Retail - Jun'24 - Signed Copy.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2024 07 03 - Sold-Unsold-K-Residences.pdf23 Jul 2025
Form 1File: 2024-03-31 Form 1 K Terraform K Residences.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Ph-I Quarter January to March 2024.pdf23 Jul 2025
Form 3File: RERA Form 3 - K Recidences Retail - Mar'24 - Singed Copy.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2024 03 31 -Sold-Unsold- K-Residences.pdf23 Jul 2025
Form 1File: 2023-12-31 Form 1 Terraform K Residences.pdf23 Jul 2025
Form 3File: Form 3 - K Residency Retail - Dec23.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Terraform K Residence Details of Sold and Unsold Dec 23.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Ph-I Quarter October to December 2023.pdf23 Jul 2025
Form 1File: 2023-06-30 Form 1 K Residences.pdf23 Jul 2025
Form 2File: Form 2 - K Residence Wing A Quarter April to June 2023.pdf23 Jul 2025
Form 3File: 2023 06 30 CA form 3 K Residences.pdf23 Jul 2025
Disclosure of Sold and Booked InventoryFile: Details of Sold and Unsold Terraform K Residences.pdf23 Jul 2025
Form 1File: 20250331_Form 1_Saakar Architect_07042025.pdf19 Jul 2025
Form 2File: 2025 06 30-Form 2-K-Residence.pdf19 Jul 2025
Form 3File: 2025 07 18-Form-3-K-Residence.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: 2025 06 30-Sold and Unsold-K-Residences.pdf19 Jul 2025
Certificates of CA (Form 3)File: 2025 04 30 - Form-3-K-Residences.pdf30 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20250331_Form 1_Saakar Architect_07042025.pdf21 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Terraform K Residences 02042025.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold data of Terraform K Residences 31032025.pdf15 Apr 2025
Declaration in FORM BFile: 09_Form B_Notarised_10022025_Notarised_LR.pdf25 Mar 2025
CERSAI detailsFile: CERSAI_Search_Report_200345976124_For_Debtor_Based_Search_20_03_2025_16_23_57_010.pdf24 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_FY 2023-24.pdf24 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2025 01 27 - Form-1-K-Residences.pdf28 Jan 2025
Certificates of CA (Form 3)File: 2025 01 08 - Form-3 - K-Residence.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2024 12 31 - Form-2-K-Residences.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: 2025 01 04 - Sold-Unsold-K-Residences.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2024 10 01 - Form-1-K-Residences.pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - K Residence - March 24.pdf10 Oct 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Terraform ArcadeP51700002110DHOKALI NAKA, Thane-Jul 2017CompletedJul 2022Dec 2018
LavenderEverest World Opp Bayer India Ltd Kolshet Road Thane West Pin 400607136-CompletedOct 2011Late, Mar 2015
AspenEverest World Opp Bayer India Ltd Kolshet Road Thane West Pin 40060780-CompletedApr 2011Late, May 2014

How this compares with Thane

88%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 32 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Terraform K - Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHOKALI7,600+ in Thane

2 kmTerraform K - ResidencesCompleted 164Lapsed / revoked 57Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 336 registered projects within 2 km.

Builder: Money Magnum Constructions

Money Magnum Constructions has 2 registrations on MahaRERA, including Terraform K - Residences and Terraform Arcade. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Terraform K - Residences shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Terraform K - Residences is delayed beyond 5 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Terraform K - Residences?

The registered promoter entity is Money Magnum Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Terraform K - Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Terraform K - Residences?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Terraform K - Residences?

The professionals named in the filing: Architect: Saakaar Architects; Engineer: Omkar Hande; Chartered Accountant: J. D. Zatakia & Co.; Chartered Accountant: Jayesh S Vora; Chartered Accountant: Ankit Goyanka & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Terraform K - Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Terraform K - Residences. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Terraform K - Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.