Home / Browse projects / Pune, Maharashtra / TEJ ONE
TEJ ONE
By TEJRAJ PATIL
RG-MH-22679 · RERA P52100035004 · Last updated on MahaRERA portal: 19 Oct 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 33 months, 4 of them under MahaRERA's automatic 4-month extension
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TEJ ONE is a Commercial project by TEJRAJ PATIL in Pune, Maharashtra, registered with MahaRERA as P52100035004 on 28 Apr 2022. Possession is promised by 24 Mar 2028. The completion date has moved by 33 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 8 of the 30 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameTEJ ONE
- TypeCommercial
- Location
- Shivajinagar (Bhamburda)
- Shivajinagar
- Pune (M Corp.)
- Pune City
- Pune
- 411004
- Pincode411004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100035004
- ReraGenie IDRG-MH-22679
Builder
- NameTEJRAJ PATIL
- Entity typeIndividual
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Apr 2022
- Promised completion24 Mar 2028
- Revised completionRevised to 24 Mar 2028 (originally 24 Jun 2025)
- Buildings1 building record
- Documents filed114 files
Current status
Figures as on 19 Oct 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TEJ ONE | NA | 13 | 11 | 0 | 30 | 30 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 95%.
TEJ ONE: 26% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 95% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed36
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| TEJ ONE | NA | Rs 15.90 cr | Rs 9.58 cr |
| - | NA | Rs 2.37 cr | Rs 2.04 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mangesh Gotal |
| Engineer | Yuvraj Kamble |
| Engineer | Suresh Fulari |
| Chartered Accountant | Ritesh Chandrakant Gujar |
| Chartered Accountant | V S POTDAR & CO |
| Chartered Accountant | DRP & CO LLP |
| Partner | Role in project |
|---|---|
| TEJRAJ PATIL | - |
Extensions2
A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.
Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.
Reason as filed by the promoterConstruction Delayed due to local issues
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jan 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 24 Mar 2028
Documents filed114
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 5_TEJONE FORM-1_001.pdf | 19 Oct 2026 |
| Withdrawal Update Form 2File: 4_Form 2 Tej One Goodluck.pdf | 19 Oct 2026 |
| Withdrawal Update Form 3File: 10_Form 3 Tej one Good Luck Chowk with Tejraj Sir signed.pdf | 19 Oct 2026 |
| Form 5 (FY 2025-2026)File: 4_Form 5 Singed-Tejone GC.pdf | 10 Oct 2026 |
| Form 2A (FY 2025-2026)File: Tej One Good Luck Chowk Form 2A.pdf | 28 Jul 2026 |
| Withdrawal Update Form 1File: Tej One GLC Form 1.pdf | 16 Jul 2026 |
| Withdrawal Update Form 2File: Form 02 Tejone.pdf | 16 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Tej One With Sign.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 Tej One_Good Luck (1).pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Form-2 TejOne_RERA Form 02_Q4_FY_2025-26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: form 3 Tejone Gook Luck_compressed.pdf | 20 Apr 2026 |
| Commencement certificateFile: CC tejone good luck chowk 15 Jan 2025.pdf | 17 Jan 2026 |
| Building plan approvalFile: 1-5.pdf | 17 Jan 2026 |
| Building plan approvalFile: 2-5.pdf | 17 Jan 2026 |
| Building plan approvalFile: 3-5.pdf | 17 Jan 2026 |
| Building plan approvalFile: 4-5.pdf | 17 Jan 2026 |
| Building plan approvalFile: 5-5.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: Tej One GC Form 1 Dec 25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: Tej One GC Form 2 Dec 25.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: Tej One- Form 3- Dec-2025_compressed.pdf | 17 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5_TEJ ONE_2024-25.pdf | 17 Nov 2025 |
| Withdrawal Update Form 1File: Form 1_Tej one GC_June 25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: Form 1_Tej One GC_Sept 25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: FORM -2 TEJ ONE GLC_June 25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form-2_Tej_One_Sep-25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Tej One GC_June 2025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Tej One_Sept 25.pdf | 17 Oct 2025 |
| Form 2A (FY 2023-2024)File: Form 2A- TejOne_2023-24.pdf | 18 Aug 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - TEJ ONE GLC_2024-25.pdf | 18 Aug 2025 |
| Withdrawal Update Form 1File: Form 1_Tej one GC_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej one GC_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: FORM -2 TEJ ONE GLC_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: FORM -2 TEJ ONE GLC_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej One GC_June 2025.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej One GC_June 2025.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej one GC_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: FORM -2 TEJ ONE GLC_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej One GC_June 2025.pdf | 20 Jul 2025 |
| Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf | 25 Jun 2025 |
| Form 5 (FY 2023-2024)File: Form 5_TEJ ONE_2023-24.pdf | 25 Jun 2025 |
| Form 1File: Form 1_Tej One_March 25.pdf | 23 Jun 2025 |
| Form 2File: Form 2_Tej One_March 25.pdf | 23 Jun 2025 |
| Form 3File: Form 3_Tej One_March 2025.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory_Tej One_March 25.pdf | 23 Jun 2025 |
| Form 1File: Form -1-Tej One_Dec_2024.pdf | 23 Jun 2025 |
| Form 2File: Form 2 Tej One_Dec 24.pdf | 23 Jun 2025 |
| Form 3File: Form 3_TejOne_Dec 2024.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Tejone_Dec 2024.pdf | 23 Jun 2025 |
| Form 1File: Form 1_Tej one_Sept 24.pdf | 23 Jun 2025 |
| Form 2File: Form 2_TEJ ONE_Sept 24.pdf | 23 Jun 2025 |
| Form 3File: Form 3_Tej One_Sept 2024.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and unsold_Tej one_Sept 2024.pdf | 23 Jun 2025 |
| Form 1File: Form 1 Tej One_ June 24.pdf | 23 Jun 2025 |
| Form 2File: Form 2 Tej One june 24.pdf | 23 Jun 2025 |
| Form 3File: Form 3_Tej One_June 2024.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Tej One June 24_0001.pdf | 23 Jun 2025 |
| Form 1File: Form 1_Tejone_March 2024.pdf | 23 Jun 2025 |
| Form 2File: Form 2_Tej One_March 2024.pdf | 23 Jun 2025 |
| Form 3File: Form 3_Tej One_March 2024.pdf | 23 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold_unsold_March 2024.pdf | 23 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory_Tej One_March 25.pdf | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Tej One_March 25.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Tej One_March 25.pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1-Tej One_Good Luck Chowk_RERA _Dec_2024.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_TejOne_Dec 2024.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tej One_Dec 24.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold_Tejone_Dec 2024.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- CA certificate_Tej One Goodluck_Sept 2024_compressed.pdf | 27 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and unsold_Tej one_Sept 2024.pdf | 27 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 TEJ ONE_Sept 24.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Tej one_Sept 24.pdf | 22 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_TEJ ONE_2023-24_compressed.pdf | 21 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Rera Designated Bank Account- Tej One.pdf | 8 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure- TP.pdf | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_0001.pdf | 31 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tej One_ Good Luck Chowk.pdf | 29 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tej One june 24.pdf | 29 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Tej One June 24_0001.pdf | 29 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1.pdf | 27 Jul 2024 |
| Proforma of Agreement for saleFile: Draft Agreement - Tej One.pdf | 21 Jun 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| DIVYATEJ | CTS NO 967 PLOT NO 3 397 BAMBURDA PUNE 16 | 20 | Completed | Dec 2019 | Late, Jan 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 114 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TEJ ONE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shivajinagar14,000+ in Pune
Filed coordinates, straight-line distance. 522 registered projects within 2 km.
VENKATESH ERANDWANE CENTRAL - BUILDING-B1 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C. Road Phase 3
PALASH REALTORS LLP
45 NIRVAANA HILL - C2 WING
SINEW DEVELOPERS PRIVATE LIMITED
VENKATESH ERANDWANE CENTRAL - BUILDING-B2 - PH
SHREE VENKATESH BUILDCON PVT LTD
VENKATESH ERANDWANE CENTRAL - BUILDING-B3 - PH
SHREE VENKATESH BUILDCON PVT LTD
One Place-F.C Road Phase 2
PALASH REALTORS LLP
Builder: TEJRAJ PATIL
TEJRAJ PATIL has 1 registration on MahaRERA, including TEJ ONE. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if TEJ ONE is delayed beyond 24 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TEJ ONE?
The registered promoter entity is TEJRAJ PATIL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TEJ ONE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TEJ ONE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TEJ ONE?
The professionals named in the filing: Architect: Mangesh Gotal; Engineer: Yuvraj Kamble; Engineer: Suresh Fulari; Chartered Accountant: Ritesh Chandrakant Gujar; Chartered Accountant: V S POTDAR & CO; Chartered Accountant: DRP & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TEJ ONE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback