Home / Browse projects / Pune, Maharashtra / TEJ MAYURBAN
TEJ MAYURBAN
RG-MH-16570 · RERA P52100026669 · Last updated on MahaRERA portal: 18 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Completion date moved by 11 months
- 2 extensions taken
- Rs 42.50 crore secured on the land, in favour of STATE BANK OF INDIA
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TEJ MAYURBAN is a Residential / Group Housing project by TEJRAJ PROFILE INFRA LLP in Pune, Maharashtra, registered with MahaRERA as P52100026669 on 21 Oct 2020. Possession is promised by 24 May 2027. The completion date has moved by 11 months from the original filing. 14 of the 75 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameTEJ MAYURBAN
- TypeResidential / Group Housing
- Location
- Model Colony
- Shivajinagar Bhamburda
- Pune (M Corp.)
- Pune City
- Pune
- 411016
- Pincode411016
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026669
- ReraGenie IDRG-MH-16570
Builder
- NameTEJRAJ PROFILE INFRA LLP
- Entity typePartnership
- PartnersTEJRAJ GANPATRAO PATIL, RAJESH MADANMOHAN CHOUDHRY
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on21 Oct 2020
- Promised completion24 May 2027
- Revised completionRevised to 24 May 2027 (originally 30 Jun 2026)
- Buildings1 building record
- Documents filed163 files
Current status
Figures as on 18 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MAYURBAN | NA | 24 | 22 | 75 | 0 | 75 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.
MAYURBAN: 64% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed180
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| MAYURBAN CO OP HOUSING SOCIETY LTD | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MAYURBAN | NA | Rs 40.00 cr | Rs 30.97 cr |
| - | NA | Rs 12.57 cr | Rs 4.68 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A DESIGN STUDIO |
| Engineer | ANIL VEER |
| Engineer | Suresh Fulari |
| Engineer | Yuvraj Kamble |
| Chartered Accountant | CA P B SHAH |
| Chartered Accountant | V S POTDAR |
| Chartered Accountant | DRP & CO LLP |
| Chartered Accountant | Ritesh Chandrakant Gujar |
| Partner | Role in project |
|---|---|
| TEJRAJ PROFILE INFRA LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterFor upgradation of project due to UDCPR sanction delayed
Reason as filed by the promoterThe construction work of the said project is substantially completed, and only certain infrastructure-related works are pending. Therefore, additional time is required to complete the project
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 45/2019/2019 | Co Op Court | Closed |
| 51/2020 | Co Op Court | ON HEARING |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Sep 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Feb 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 24 May 2027
Documents filed163
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 163 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Tej Mayurban Form - 1.pdf | 18 Jul 2026 |
| Withdrawal Update Form 2File: Tej Mayurban_RERA Form 02_Q1 FY 2026-27.pdf | 18 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Mayurban With Sign_0001.pdf | 18 Jul 2026 |
| Form 2A (FY 2025-2026)File: Tej Mayurban Form 2A.pdf | 21 Apr 2026 |
| Withdrawal Update Form 1File: Tej Mayurban.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2_001.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Tej Mayurban_.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Tej Mayurban Form 1 Dec 25.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: Tej Mayurban Form 2.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Tej Mayurban Form 3 Dec 25.pdf | 16 Jan 2026 |
| Form 5 (FY 2024-2025)File: From 5_Tej Mayurban_2024-25.pdf | 14 Nov 2025 |
| Form 2A (FY 2020-2021)File: Form 2A_Tej Mayurban_2020-21.pdf | 3 Nov 2025 |
| Form 2A (FY 2021-2022)File: Form 2A_Tej Mayurban_2021-22.pdf | 3 Nov 2025 |
| Form 2A (FY 2022-2023)File: Form 2A_Tej Mayurban_2022-23.pdf | 3 Nov 2025 |
| Form 2A (FY 2023-2024)File: Form 2A_Tej Mayurban_2023-24.pdf | 3 Nov 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A_Tej Mayurban_2024-25.pdf | 3 Nov 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form-2_Tej_Mayurban_Sep-25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form-2_Tej_Mayurban_Sep-25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Form-2_Tej_Mayurban_Sep-25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_Sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_Sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_Sept 25.pdf | 18 Oct 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 21 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 21 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 20 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 20 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 20 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 20 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 19 Jul 2025 |
| Withdrawal Update Form 1File: Form 1_Tej Mayurban_June 2025.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Form 2_Tej Mayurban_June 25.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: Form 3_Tej Mayurban_June 25.pdf | 19 Jul 2025 |
| Form 1File: Form 1 Tej Mayurban.pdf | 27 Jun 2025 |
| Form 2File: Form 2 Tej Mayurban.pdf | 27 Jun 2025 |
| Form 3File: Form 3 Tej Mayurban June 24.pdf | 27 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Tej Mayurban June 24_0001_0001_0001.pdf | 27 Jun 2025 |
| Form 1File: Form 1 - Architect's certificate_March 24.pdf | 27 Jun 2025 |
| Form 2File: Form 2 - Engineer Cert_March 24.pdf | 27 Jun 2025 |
| Form 3File: Form 3 - CA Certificate_March 24.pdf | 27 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventory disclosure_March 24.pdf | 27 Jun 2025 |
| Form 1File: Form 1_Tej Mayurban_March 25.pdf | 25 Jun 2025 |
| Form 2File: Form 2_Tej Mayurban_March 25.pdf | 25 Jun 2025 |
| Form 3File: Form 3_CA Certificate_Tej Mayurban_March 25.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold_Tej Mayurban_March 25.pdf | 25 Jun 2025 |
| Form 1File: Form 1_Tej Mayurban_Dec 24.pdf | 25 Jun 2025 |
| Form 2File: Form 2 Tej Mayurban_Dec 24.pdf | 25 Jun 2025 |
| Form 3File: Form 3_Mayurban_Dec 2024.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold_Mayurban_Dec 2024.pdf | 25 Jun 2025 |
| Form 1File: Form 1 Tej Mayurban Sept 24.pdf | 25 Jun 2025 |
| Form 2File: Form 2 Mayurban_Sept 24.pdf | 25 Jun 2025 |
| Form 3File: Form 3 CA Certificate_Sept_2024.pdf | 25 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold and Unsold as on for Sept 2024.pdf | 25 Jun 2025 |
| Form 5 (FY 2020-2021)File: Form 5 20-21.pdf | 25 Jun 2025 |
| Form 5 (FY 2021-2022)File: Form 5 - 21-22.pdf | 25 Jun 2025 |
| Form 5 (FY 2022-2023)File: Form 5 22-23.pdf | 25 Jun 2025 |
| Form 5 (FY 2023-2024)File: Form 5_MAYURBAN_2023-24.pdf | 25 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Tej Mayurban_March 25.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1_Tej Mayurban_March 25.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_CA Certificate_Tej Mayurban_March 25.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Tej Mayurban_March 25.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold_Tej Mayurban_March 25.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- MAYURBAN_Sept_2021.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- MAYURBAN_Dec_2021.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- MAYURBAN_June_2022.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Tej Mayurban - June 23.pdf | 16 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Tejraj Profile Infra LLP.pdf | 16 Apr 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 163 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TEJ MAYURBAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shivajinagar Bhamburda13,700+ in Pune
Filed coordinates, straight-line distance. 439 registered projects within 2 km.
KUSUM CO. OPERATIVE HOUSING SOCIETY LIMITED
M/S FORTUNE DEVELOPERS
VB FOREST CASTLE BY ASCENT LANDMARKS
ASCENT LANDMARKS LLP
The Luxe Towers - Building I and J
Neelsidhi Mohar Raisoni Developers LLP
TEJ MIDTOWN
TEJRAJ GANPATRAO PATIL
Bellagio Courtyards
MICHELNGELO LLP
SHUBHAMKAROTI
CHAPHALKAR KARANDIKAR DEVELOPERS
Builder: TEJRAJ PROFILE INFRA LLP
TEJRAJ PROFILE INFRA LLP has 2 registrations on MahaRERA, including TEJ MAYURBAN and TEJ NOVA. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if TEJ MAYURBAN is delayed beyond 24 May 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TEJ MAYURBAN?
The registered promoter entity is TEJRAJ PROFILE INFRA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TEJ MAYURBAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TEJ MAYURBAN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TEJ MAYURBAN?
The professionals named in the filing: Architect: A DESIGN STUDIO; Engineer: ANIL VEER; Engineer: Suresh Fulari; Engineer: Yuvraj Kamble; Chartered Accountant: CA P B SHAH; Chartered Accountant: V S POTDAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TEJ MAYURBAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback