Home / Browse projects / Mumbai City, Maharashtra / Techno Kalpana

Registration lapsed No litigation declared Residential / Group Housing project

Techno Kalpana

By MEHTA ENTERPRISES

RG-MH-83870 · RERA P51900047260 · Last updated on MahaRERA portal: 23 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
8 of 11Construction stages donefurthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

Techno Kalpana is a Residential / Group Housing project by MEHTA ENTERPRISES in Mumbai City, Maharashtra, registered with MahaRERA as P51900047260 on 15 Oct 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameTechno Kalpana
  • TypeResidential / Group Housing
  • Location
    • V A Ozha Marg
    • Matunga
    • Mumbai City
    • 400019
  • Pincode400019
  • RERA no.P51900047260
  • ReraGenie IDRG-MH-83870

Builder

  • NameMEHTA ENTERPRISES
  • Entity typePartnership
  • PartnersKUNTAL NIKHIL MEHTA, DHWANI JAYDEEP MEHTA, SONAL CHETAN MEHTA, PRAMILA JASHWANT MEHTA, ANUPRITA RAJESH LOYA, KIRTI MEHTA HUF HUF
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredOct 2022First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Oct 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Techno KalpanaNA210000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

Techno Kalpana: 81% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed30

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots30
Closed/Covered30

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area589 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Shubha Kalpana Co-op. Housing Society LtdMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1904.59
Proposed, not sanctioned1,547 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPremises No 59 AND 61, Sonawala Building, 57 Mumbai Samachar Marg, Opp Bombay Stock Exc, Fort, Mumba

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB N SHAH & ASSOCIATES
EngineerManish Jha
Chartered AccountantM. S. Mandlecha & Co Chartered Accountants
Chartered AccountantJagritS Bhalja
PartnerRole in project
MEHTA ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900027842Dec 2024 → Dec 2025

Reason as filed by the promoter(a) We have received full Occupation Certificate for our project on 29th May, 2025. We do not need to extend the timeline of the project anymore. We can now show the project as completed under MahaRERA. We have also enclosed herewith From 2, 2A, 3, 4 and 5, Disclosure of Inventory along with Full Occupation Certificate for your reference (b) During excavation and foundation work, we encountered unexpected hard rocrk at very early stage which required significant additional time for pile foundation & hence further work was delayed. These unforeseen site conditions have extended the construction

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Apr 2025

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: Format-B Application for Extension of Project.pdf23 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Occupation Certificate up to 19th Floor_03032025.pdf19 Apr 2025
Other - TechnicalFile: CPM Chart.pdf19 Apr 2025
Declaration in FORM BFile: 3_Form B - Extension.pdf12 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_31122024_Kalpana.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Dec 2024_Kalpana.pdf12 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_31122024_Techno Kalpana.pdf12 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Dec 24.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_30092024_Kalpana.pdf13 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Sep 2024_Kalpana.pdf13 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Sep 24.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_30062024_Techno Kalpana.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_30092024_Techno Kalpana.pdf9 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 For Annual Report of CA FY 2023-24_ME.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_30062024_Kalpana.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Jun 2024_Kalpana.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Jun 24.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_FY 2023-24_Kalpana.pdf25 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_31032024_Kalpana.pdf13 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Mar 2024_Kalpana.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_31032024_Techno Kalpana.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Mar 24.pdf24 Apr 2024
Building plan approvalFile: Amemded Drawing 26Dec2023.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Amemded Drawing 26Dec2023.pdf13 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Further_13022024.pdf13 Feb 2024
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate_13022024.pdf13 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Dec 2023_Kalpana.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_31122023_Techno Kalpana.pdf30 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_31122023_Kalpana.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Dec 23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_30092023_Kalpana.pdf30 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Sep 2023_Kalpana.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_30092023_Techno Kalpana.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Sep 23.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 For Annual Report of CA FY 2022-23_ME.pdf29 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_30062023_Kalpana.pdf29 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Further_20072023.pdf20 Jul 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate_20072023.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1- KALPANA-Jun 23.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Jun 2023_Kalpana.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_FY 2022-23_Kalpana.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_30062023_Techno Kalpana.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA form 1- KALPANA-Mar 23.pdf13 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Techno Kalpana_31032023.pdf13 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_31032023_Techno Kalpana.pdf13 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_31032023_Kalpana.pdf13 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account2.pdf13 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_Further_Second_22022023.pdf27 Feb 2023
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate_22022023.pdf27 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Certificate of Society Registrartion.pdf24 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Techno Kalpana_31122022.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (Cost)_31122022_Kalpana.pdf20 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA form 1- KALPANA-Dec 22.pdf6 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate_Techno Kalpana_31122022.pdf6 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Booking Inventory_31122022_Techno Kalpana.pdf6 Jan 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf23 Nov 2022
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf23 Nov 2022
CERSAI detailsFile: CERSAI_Search_Report_200252995579_For_Debtor_Based_Search_23_11_2022_15_58_22_730.pdf23 Nov 2022
Proforma of Agreement for saleFile: Proforma of Agreement of Sale - Kalpana.pdf23 Nov 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model copy of agreement.pdf23 Nov 2022
Other - TechnicalFile: Form B - declaration.pdf11 Oct 2022
Proforma of Allotment letterFile: Proforma of Agreement of Sale - Kalpana.pdf6 Oct 2022
Other - LegalFile: Deviation Report with respect to Model Allotment Letter.pdf23 Sep 2022
Proforma of Allotment letterFile: Proforma of Allotment Letter - Kalpana.pdf19 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate (cost)_Application final.pdf14 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model copy of agreement.pdf26 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Separate Bank Account.pdf10 Aug 2022
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Model Allotment Letter.pdf10 Aug 2022
Layout approvalFile: Details of encumbrances concerned to Layout.pdf3 Aug 2022
Building plan approvalFile: Building Plan Approval.pdf3 Aug 2022
PAN CardFile: PAN CARD_ME.pdf3 Aug 2022
Copy of the legal title reportFile: Title Report.pdf3 Aug 2022
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf3 Aug 2022
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf3 Aug 2022
Copy of Layout Approval (in case of layout)File: Details of encumbrances concerned to Layout.pdf3 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf3 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: 2336298_FirstCC_signed.pdf3 Aug 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf3 Aug 2022
Declaration in FORM BFile: Form B - declaration.pdf3 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 KALPANA.pdf3 Aug 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MODY KUNJCTS No.500C-10 Plot No.8A2 K A Subramaniam Road Matunga East Mumbai 4000191CompletedMar 2019Late, Dec 2019

How this compares with Mumbai City

33%of Mumbai City projects moved their completion datethis one moved by 12 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Techno Kalpana on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Matunga780+ in Mumbai City

Builder: MEHTA ENTERPRISES

MEHTA ENTERPRISES has 2 registrations on MahaRERA, including MODY KUNJ and Techno Kalpana. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Techno Kalpana shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Techno Kalpana is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Techno Kalpana?

The registered promoter entity is MEHTA ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Techno Kalpana?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Techno Kalpana?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Techno Kalpana?

The professionals named in the filing: Architect: B N SHAH & ASSOCIATES; Engineer: Manish Jha; Chartered Accountant: M. S. Mandlecha & Co Chartered Accountants; Chartered Accountant: JagritS Bhalja. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Techno Kalpana?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Techno Kalpana. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Techno Kalpana to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.