Home / Browse projects / Thane, Maharashtra / TANISHQ

Registered No litigation declared Others project

TANISHQ

By PHOENIX REALTY

RG-MH-94774 · RERA P51700048797 · Last updated on MahaRERA portal: 7 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken
  • Rs 8.50 crore secured on the land, in favour of MOTILAL OSWAL HOME FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 4 months from the original
4 of 11Construction stages donefurthest along: Podiums (if any), 95%
94 of 179Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

TANISHQ is a Others project by PHOENIX REALTY in Thane, Maharashtra, registered with MahaRERA as P51700048797 on 17 Jan 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months from the original filing. 85 of the 179 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameTANISHQ
  • TypeOthers
  • Location
    • KALYAN
    • Chikanghar
    • Thane
    • 421301
  • Pincode421301
  • RERA no.P51700048797
  • ReraGenie IDRG-MH-94774

Builder

  • NamePHOENIX REALTY
  • Entity typePartnership
  • PartnersSUNIL PANDURANG MHATRE, RAHUL BHARAT GAIKAR, ASLAM MOHD SHAIKH, GOPAL BACHUBHAI SENJALIA, HITENDRA JAMANDAS UNDHAD, ASHOK KUMAR GORDHANBHAI SAVALIYA, PARESH GAJANAN MHATRE
  • Other registrations1 more →

Key dates

this monthRegisteredJan 2023First promiseDec 2026Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Jan 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
  • Buildings1 building record
  • Documents filed101 files

Current status

47%85 of 179 units booked
59.8%Work done, per cost certificate

Figures as on 7 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TANISHQNA242374105179

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 95%.

TANISHQ: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)95%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 7 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes85%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed468

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots468
Closed/Covered468

Land and ownership8

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,644 sq m
Land owned byNot the promoter
Named landowners8
Encumbrance on the landDeclared present
Charge in favour ofMOTILAL OSWAL HOME FINANCE LIMITED
Secured amountRs 8.50 crore
CERSAI search filedYes
Declared on14 Aug 2026
LandownerVillageDistrict
PARESH GAJANAN MHATREKalyanThane
SUNIL PANDURANG MHATREKalyanThane
RAHUL BHARAT GAIKARKalyanThane
ANIL SUBHASH KOLIKalyanThane
PARAG SOHANLAL JAINKalyanThane
PARSN VILLA CO OPERATIVE HOUSING SOCIETYRambaugThane
GULAB CO -OPERATIVE HOUSING SOCIETY LIMITEDRambaugThane
MHALASA CO OP HOUSING SOCIETY LTDRambaugThane

Approvals and building plan

Sanctioning authorityKalyan Dombivali Municipal Corporation
Permissible FSI10803.35
Proposed, not sanctioned10,803 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.10-14,WHITE FIELD BUILDING GR.FLR,E-WING,FLOWER VALLEY COMPLEX KHADAKPADA, KALYAN WEST
Estimated costRs 78.70 cr
Cost incurredRs 47.08 cr
Work done59.83%
BuildingWingEstimatedIncurred
TANISHQNARs 70.83 crRs 43.47 cr
-NARs 7.87 crRs 3.61 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEMERGE ARCHITECTS AND ASSOCIATES
EngineerASSOCIATED STRUCTURAL ENGINEERS LLP
EngineerDarshan Jayantrao Zunjarrao
Chartered AccountantDEEPAK HIMARAM PUROHIT
Chartered AccountantC M LAD & ASSOCIATES
PartnerRole in project
PHOENIX REALTY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51700048797/WarDec 2026 → Apr 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: FORM 2A FY 24-25.pdf7 Sep 2026
Form 2A (FY 2025-2026)File: FORM 2A FY 25-26.pdf7 Sep 2026
Withdrawal Update Form 1File: Form 1.pdf7 Aug 2026
Withdrawal Update Form 1File: Form 1.pdf7 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf7 Aug 2026
Withdrawal Update Form 2File: Form 2.pdf7 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf7 Aug 2026
Withdrawal Update Form 3File: Form 3.pdf7 Aug 2026
Withdrawal Update Form 1File: FORM 1.pdf10 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf10 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf10 Jun 2026
Form 5 (FY 2024-2025)File: FORM 5 OF PHOENIX REALTY.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM 1.pdf27 Mar 2026
Withdrawal Update Form 2File: FORM 2.pdf27 Mar 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf27 Mar 2026
Withdrawal Update Form 1File: Tanishq_Rera_02-10-2025.pdf12 Jan 2026
Withdrawal Update Form 2File: form 2.pdf12 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf12 Jan 2026
Building plan approvalFile: Tanishq blue print-2nd_.pdf5 Jan 2026
Withdrawal Update Form 1File: Tanishq_Rera_02-10-2025.pdf4 Dec 2025
Withdrawal Update Form 2File: form 2.pdf4 Dec 2025
Withdrawal Update Form 3File: RERA FORM 3.pdf4 Dec 2025
Form 1File: FORM 1 .pdf31 Oct 2025
Form 2File: FORM 2 Sunil sir sign.pdf31 Oct 2025
Form 3File: FINAL FORM 3.pdf31 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf31 Oct 2025
Withdrawal Update Form 1File: architect certificate Q2.pdf31 Oct 2025
Withdrawal Update Form 1File: architect certificate Q2.pdf31 Oct 2025
Withdrawal Update Form 2File: FORM 2 Sunil sir sign.pdf31 Oct 2025
Withdrawal Update Form 2File: FORM 2 Sunil sir sign.pdf31 Oct 2025
Withdrawal Update Form 3File: CA CERTIFICATE SIGNED Q2 1169_11zon.pdf31 Oct 2025
Withdrawal Update Form 3File: FINAL FORM 3.pdf31 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM_3.pdf19 May 2025
Form 3File: FORM_3.pdf15 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf13 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 FINAL.pdf3 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_11zon.pdf3 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FINAL.pdf3 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf17 Feb 2025
Building plan approvalFile: PLAN LAYOUT_11zon.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECTS CERTIFICATE - TANISHQ - 30-09-2024.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: TANISHQ COMMENCEMENT CERTIFICATE DATED 02-08-2024.pdf8 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN LAYOUT_11zon.pdf8 Feb 2025
Declaration about Commencement CertificateFile: DECLARATION OF COMMENCEMENT CERTIFICATE.pdf8 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch 300624.pdf6 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 PR.pdf6 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE - TANISHQ PROJECT - 31-12-2023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - ARCHITECTS CERTIFICATE - TANISHQ - 31-03-2024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE - TANISHQ - 30-09-2023.pdf28 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DATED 31-12-2023.pdf28 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DATED 31-03-2024.pdf28 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 DATED 30-06-2024.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE - 30-06-2024.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE - 31-03-2024.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE - 30-12-2023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate q1.pdf15 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate Q2.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE FOR TANISHQ- q2.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE Q2.pdf15 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SIGNED q1 8590_11zon.pdf15 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SIGNED Q2 1169_11zon.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf23 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf16 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 UPDATION.pdf16 Aug 2023
Copy of the legal title reportFile: New Title Report.pdf6 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations tanishq-1.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations tanishq-2.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Ashok Kumar20230105-14121679.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Gopal20230105-13481736.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Hitendra20230105-13505378.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Mohmd shaikh20230105-13470686.pdf5 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Paresh20230105-13494319.pdf5 Jan 2023
Proforma of Agreement for saleFile: Tanishq AFS (1).pdf17 Nov 2022
Proforma of Allotment letterFile: Tanishq Allotment Letter (2).pdf17 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Certificate.pdf28 Oct 2022
Layout approvalFile: Blue Print 1-2_11zon.pdf25 Oct 2022

How this compares with Thane

47%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 4 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TANISHQ on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

Builder: PHOENIX REALTY

PHOENIX REALTY has 2 registrations on MahaRERA, including TANISHQ and PHOENIX SERENIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if TANISHQ is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TANISHQ?

The registered promoter entity is PHOENIX REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TANISHQ?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TANISHQ?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TANISHQ?

The professionals named in the filing: Architect: EMERGE ARCHITECTS AND ASSOCIATES; Engineer: ASSOCIATED STRUCTURAL ENGINEERS LLP; Engineer: Darshan Jayantrao Zunjarrao; Chartered Accountant: DEEPAK HIMARAM PUROHIT; Chartered Accountant: C M LAD & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TANISHQ?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TANISHQ. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TANISHQ to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.