Home / Browse projects / Nagpur, Maharashtra / TAMEEM CASTLE

De-registered No litigation declared Others project

TAMEEM CASTLE

By TAMEEM CONSTRUCTION & LAND DEVELOPERS

RG-MH-02700 · RERA P50500026533 · Last updated on MahaRERA portal: 23 Oct 2023

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 49 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Sep 2022Possession promised49 months past this date
5 of 11Construction stages donefurthest along: Staircases, 60%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

TAMEEM CASTLE is a Others project by TAMEEM CONSTRUCTION & LAND DEVELOPERS in Nagpur, Maharashtra, registered with MahaRERA as P50500026533 on 30 Sep 2020. Possession was promised by 30 Sep 2022 and is now 49 months past that date. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameTAMEEM CASTLE
  • TypeOthers
  • Location
    • W-20/1 SHEET NO -04 BLOCK NO -23
    • ISLMAILPURA CROSS ROAD KAMPTEE
    • Kamptee (CB)
    • Kamptee
    • Nagpur
    • 441001
  • Pincode441001
  • RERA no.P50500026533
  • ReraGenie IDRG-MH-02700

Builder

  • NameTAMEEM CONSTRUCTION & LAND DEVELOPERS
  • Entity typePartnership
  • PartnerMOHAMMAD ABDUL FAROOQUE

Key dates

49 months past promisethis monthRegisteredSep 2020First promiseMar 2021Revised toSep 2022

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on30 Sep 2020
  • Promised completion30 Sep 2022
  • Revised completionRevised to 30 Sep 2022 (originally 31 Mar 2021)
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TAMEEM CASTLENA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 60%.

TAMEEM CASTLE: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area246 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI369.0
Proposed, not sanctioned355 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKAMPTEE

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHEKHAR POTDAR
ArchitectAr Prasad Shendre
EngineerSHEKHAR POTDAR
EngineerZiauddin
Chartered AccountantT S RAWAL
PartnerRole in project
TAMEEM CONSTRUCTION & LAND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500009313Mar 2021 → Mar 2022

Reason as filed by the promoterDear Sir, I/We the Promoters of the Project name Tameem Castle registered under project registration no P50500026533 do hereby declare that we had mentioned the revised proposed date of completion of project is 31st March 2021. We would like to bring to your notice that our project is 50% completed. We have a total of 19 shops/apartments and all the shops/apartments are unsold which needs to be sold but without the Extension Number we are unable to sell those apartments/shops. Hence we are making this application for Project Extension. We request you to give extension for our project for One Y

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Sep 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Sep 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Tameem Form 2A Certificate APR 21.pdf23 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Tameem Form 2A Certificate APR 22.pdf23 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Tameem Form 2A Certificate APR 23.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Tameem Cons FY 20-21 FORM 5-CA CERTIFICATE FOR AUDIT.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Tameem Cons FY 21-22 FORM 5-CA CERTIFICATE FOR AUDIT.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tameem Cons FY 22-23 FORM 5-CA CERTIFICATE FOR AUDIT.pdf23 Oct 2023
Declaration about Commencement CertificateFile: Tameem Form D MAR23.pdf22 Oct 2023
Declaration about Commencement CertificateFile: Tameem FoRm D JUN23.pdf22 Oct 2023
Declaration about Commencement CertificateFile: Tameem FormD SEP23.pdf22 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tameem Archn Certificed MAR23.pdf22 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tameem Arch Certificate JUN23.pdf22 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Tameem Arch XCertificate SEP23.pdf22 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tameem Eng Certificate MAR23.pdf22 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tameem Eng Certificate JUN23.pdf22 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Tameem Eng Certificate SEP23.pdf22 Oct 2023
Disclosure of sold/ booked inventoryFile: Tameem Sold Book MAR23.pdf22 Oct 2023
Disclosure of sold/ booked inventoryFile: Tameem Sold Book JUN23.pdf22 Oct 2023
Disclosure of sold/ booked inventoryFile: Tameem Sold Book SEP23.pdf22 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tameem CA Certificate MAR23.pdf22 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tameem CA Certificate JUN23.pdf22 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Tameem CA Certificate SEP23.pdf22 Oct 2023
Other - LegalFile: ANNEXURE A Tameen Construction.pdf22 Oct 2023
Other - LegalFile: ANNEXURE B Tameem Construction.pdf22 Oct 2023
Other - TechnicalFile: Authority Letter.pdf22 Oct 2023
Other - TechnicalFile: Resolution of de-registration.pdf22 Oct 2023
Layout approvalFile: MAP_0001.pdf28 Sep 2020
Layout approvalFile: MAP_0001.pdf28 Sep 2020
Building plan approvalFile: MAP_0001.pdf28 Sep 2020
Layout approvalFile: MAP_0001.pdf28 Sep 2020
Copy of Layout Approval (in case of layout)File: MAP_0001.pdf28 Sep 2020
Copy of Layout Approval (in case of layout)File: MAP_0001.pdf28 Sep 2020
Copy of Layout Approval (in case of layout)File: MAP_0001.pdf28 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: MAP_0001.pdf28 Sep 2020
Copy of the legal title reportFile: TITLE REPORT.pdf21 Sep 2020
PAN CardFile: PAN CARD.pdf18 Sep 2020
Details of encumbrancesFile: NO ENCUMBRANCE.pdf18 Sep 2020
Declaration in FORM BFile: FORM B.pdf18 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE .pdf18 Sep 2020
Proforma of Allotment letterFile: SELF DECLARATION.pdf18 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: BUILDING PERIMAT.pdf16 Sep 2020

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 18 months
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TAMEEM CASTLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ISLMAILPURA CROSS ROAD KAMPTEE2,800+ in Nagpur

Builder: TAMEEM CONSTRUCTION & LAND DEVELOPERS

TAMEEM CONSTRUCTION & LAND DEVELOPERS has 1 registration on MahaRERA, including TAMEEM CASTLE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that TAMEEM CASTLE shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TAMEEM CASTLE is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TAMEEM CASTLE?

The registered promoter entity is TAMEEM CONSTRUCTION & LAND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TAMEEM CASTLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TAMEEM CASTLE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TAMEEM CASTLE?

The professionals named in the filing: Architect: SHEKHAR POTDAR; Architect: Ar Prasad Shendre; Engineer: SHEKHAR POTDAR; Engineer: Ziauddin; Chartered Accountant: T S RAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TAMEEM CASTLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TAMEEM CASTLE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TAMEEM CASTLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.