Home / Browse projects / Nashik, Maharashtra / SYMPHONY PARK
SYMPHONY PARK
RG-MH-50335 · RERA P51600050743 · Last updated on MahaRERA portal: 7 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SYMPHONY PARK is a Residential / Group Housing project by NARAYAN ZIPARU WANI in Nashik, Maharashtra, registered with MahaRERA as P51600050743 on 28 Apr 2023. Possession is promised by 31 Dec 2027. 69 of the 102 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameSYMPHONY PARK
- TypeResidential / Group Housing
- Location
- DHARMAJI COLONY
- DHRUV NAGAR
- SATPUR GANGAPUR SHIWAR
- Nashik (M Corp.)
- Nashik
- 422007
- Pincode422007
- RERA no.P51600050743
- ReraGenie IDRG-MH-50335
Builder
- NameNARAYAN ZIPARU WANI
- Entity typeIndividual
- GSTIN27AACPW6172D1ZK
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on28 Apr 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed108 files
Current status
Figures as on 7 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SYMPHONY PARK | NA | 8 | 8 | 84 | 18 | 102 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
SYMPHONY PARK: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 7 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed210
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SYMPHONY PARK | NA | Rs 10.50 cr | Rs 8.85 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIL N YEOLA |
| Engineer | ANIL N YEOLA |
| Engineer | SUSHANT CHAVAN |
| Chartered Accountant | CA VIKAS PAGAR |
| Chartered Accountant | sahebrao d pawar |
| Chartered Accountant | AJINKYA VYAVAHARE |
| Partner | Role in project |
|---|---|
| NARAYAN ZIPARU WANI | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Apr 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Dec 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Jan 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: NZW FORM-1 APR26.pdf | 7 May 2026 |
| Withdrawal Update Form 2File: nzw form2 march26.pdf | 7 May 2026 |
| Withdrawal Update Form 3File: nzw form3 mar26_11zon.pdf | 7 May 2026 |
| Withdrawal Update Form 1File: Form 1 Dec25.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Dec25.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Dec25_compressed.pdf | 4 Feb 2026 |
| Form 1File: Form 1 Dec24.pdf | 31 Jan 2026 |
| Form 2File: Form 2 Dec24.pdf | 31 Jan 2026 |
| Form 3File: Form 3 Dec24_compressed.pdf | 31 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: disc of sold n unsold.pdf | 31 Jan 2026 |
| Form 1File: Form 1 March25.pdf | 31 Jan 2026 |
| Form 2File: Form 2 March25.pdf | 31 Jan 2026 |
| Form 3File: Form 3 March25_compressed.pdf | 31 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: disc of soldnunsild.pdf | 31 Jan 2026 |
| Form 1File: Form 1 June25.pdf | 31 Jan 2026 |
| Form 2File: Form 2 June25.pdf | 31 Jan 2026 |
| Form 3File: Form 3 Jun25_compressed.pdf | 31 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: disc of soldnunsold.pdf | 31 Jan 2026 |
| Form 1File: Form 1 Sep25.pdf | 31 Jan 2026 |
| Form 2File: Form 2 Sep25.pdf | 31 Jan 2026 |
| Form 3File: Form 3 Sep25_compressed.pdf | 31 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: disc of sold n unsold.pdf | 31 Jan 2026 |
| Form 1File: Form 1 Dec25.pdf | 31 Jan 2026 |
| Form 2File: Form 2 Dec25.pdf | 31 Jan 2026 |
| Form 3File: Form 3 Dec25_compressed.pdf | 31 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: disc of soldnunsold.pdf | 31 Jan 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: symphony park form 1.pdf | 21 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: symphony park form 3_11zon.pdf | 21 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: symphony park form 2.pdf | 21 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: annual report.pdf | 17 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1sep23.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1dec23.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1mar24.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1jun24.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1jun23.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3sep23_11zon.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3jun24_11zon.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3mar24_11zon.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3dec23_11zon.pdf | 16 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3jun23_11zon.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2dec23.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 .pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2jun24.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2mar24.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2sep23.pdf | 16 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2jun23.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory sep 23.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory june 23.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory December 23.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory march 24.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory june 24.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: inventory .pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form2a.pdf | 16 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: inventory june 23.pdf | 16 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: inventory june 23.pdf | 16 Oct 2024 |
| Form 1File: form1jun23.pdf | 3 Oct 2024 |
| Form 2File: form2jun23.pdf | 3 Oct 2024 |
| Form 3File: form3jun23.pdf | 3 Oct 2024 |
| Disclosure of Sold and Booked InventoryFile: inventory june 23.pdf | 3 Oct 2024 |
| Form 3File: form3jun24.pdf | 3 Oct 2024 |
| Disclosure of Sold and Booked InventoryFile: inventory june 24.pdf | 3 Oct 2024 |
| Form 1File: form1jun24.pdf | 3 Oct 2024 |
| Form 2File: form2jun24.pdf | 3 Oct 2024 |
| Form 1File: form1mar24.pdf | 3 Oct 2024 |
| Form 2File: form2mar24.pdf | 3 Oct 2024 |
| Form 3File: form3mar24_11zon.pdf | 3 Oct 2024 |
| Disclosure of Sold and Booked InventoryFile: inventory march 24.pdf | 3 Oct 2024 |
| Form 1File: form1sep23.pdf | 3 Oct 2024 |
| Form 2File: form2sep23.pdf | 3 Oct 2024 |
| Form 3File: form3sep23.pdf | 3 Oct 2024 |
| Disclosure of Sold and Booked InventoryFile: inventory sep 23.pdf | 3 Oct 2024 |
| Form 1File: form1dec23.pdf | 3 Oct 2024 |
| Form 2File: form2dec23.pdf | 3 Oct 2024 |
| Form 3File: form3dec23.pdf | 3 Oct 2024 |
| Disclosure of Sold and Booked InventoryFile: inventory December 23.pdf | 3 Oct 2024 |
| Form 1File: form1jun23.pdf | 25 Sep 2024 |
| Form 2File: form2jun23.pdf | 24 Sep 2024 |
| Form 3File: form3jun23.pdf | 24 Sep 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 6 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SYMPHONY PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SATPUR GANGAPUR SHIWAR4,100+ in Nashik
SHREE GANESH SRUSHTI
JYK NIRMITI INFRA LLP
BOLKAR MAJESTIC
GANESH TUKARAM BOLKAR
PALM TOWN
VAKRATUNDA PROPERTIES
Swaraj 1 and 2 BHK Homes
Kothawale Patil Builders And Developers Pv
HAPPY LIFE AT APNA GHAR PHASE V
M/S Shweta Infrastructure & Housing (I) Pv
Balaji Heights
Geeta Developers
See every Nashik project, with the district possession charts
Builder: NARAYAN ZIPARU WANI
NARAYAN ZIPARU WANI has 2 registrations on MahaRERA, including WOODLAND APARTMENT and SYMPHONY PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SYMPHONY PARK is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SYMPHONY PARK?
The registered promoter entity is NARAYAN ZIPARU WANI, an individual as per the filing. Its GSTIN 27AACPW6172D1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SYMPHONY PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SYMPHONY PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SYMPHONY PARK?
The professionals named in the filing: Architect: ANIL N YEOLA; Engineer: ANIL N YEOLA; Engineer: SUSHANT CHAVAN; Chartered Accountant: CA VIKAS PAGAR; Chartered Accountant: sahebrao d pawar; Chartered Accountant: AJINKYA VYAVAHARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SYMPHONY PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback