SWAYAMPRABHA

By Gruha Navnirman Developers

RG-MH-01069 · RERA P52100001118 · Last updated on MahaRERA portal: 18 May 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 86 months past the filed date
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2019Possession promised86 months past this date
4 of 11Construction stages donefurthest along: Internal walls, 75%
0Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

SWAYAMPRABHA is a Residential / Group Housing project by Gruha Navnirman Developers in Pune, Maharashtra, registered with MahaRERA as P52100001118 on 26 Jul 2017. Possession was promised by 15 Aug 2019 and is now 86 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSWAYAMPRABHA
  • TypeResidential / Group Housing
  • Location
    • Rambaug Colony
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411030
  • Pincode411030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001118
  • ReraGenie IDRG-MH-01069

Builder

  • NameGruha Navnirman Developers
  • Entity typePartnership
  • PartnersAbhijit D Kenjale, DHIRAJ WANI, LALIT P AJGAONKAR, NILESH PATE
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

86 months past promisethis monthRegisteredJul 2017First promiseAug 2018Revised toAug 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jul 2017
  • Promised completion15 Aug 2019
  • Revised completionRevised to 15 Aug 2019 (originally 15 Aug 2018)
  • Buildings1 building record
  • Documents filed15 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SWAYAMPRBHANA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 May 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.

SWAYAMPRBHA: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes25%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Closed/Covered22
Open Space23

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,183 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SWAYAMPRABHA CO-OP HOUSING SOCIETYKothrudPune

Approvals and building plan

Permissible FSI2197.81
Proposed, not sanctioned2,198 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNARAYAN PETH

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectADESIGNSTUDIO ARCH SIDDHARTH HARISHCHANDRAKAR
EngineerG A Bhilare Consultants Private Limited GA BHILARE
PartnerRole in project
Gruha Navnirman Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000786Aug 2018 → Aug 2019

Reason as filed by the promoterWe hereby request for extension again due to following reasons. Part Completion was received from PMC on date 16/05/2018 Due to various compliance related issues at society end along with annual general body meetings etc there was delay in applying for extension. Lift work was started late from OTIS. Currently 1 lift is installed and 2nd in progress. Members had requested several changes in flats, thus causing delay.

EXT52100000251Aug 2018 → Aug 2019

Reason as filed by the promoterWe hereby request for extension of 4 months in order to finish the site which is more than 80% complete. Kindly find below few major reasons for delay: 1. The last commencement certificate for the building was received on 31/05/2017 (Already uploaded on MahaRERA). We had got permission to add 9th floor to the building previously sanctioned for 8 floors due to ever changing rules of Pune Municipal Corporation. To avail the benefit, we had to revise construction drawings to include additional floor water storage and also additional lift stop. This added at least 2 months of additional re-work/re

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jun 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jun 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: Swayamprbha Complition Part 1.pdf18 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Document.pdf28 Feb 2018
Declaration in FORM BFile: Swayamprabha Form B.pdf22 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Swayamprbha.pdf22 Jul 2017
Certificates of CA (Form 3)File: Form 3 Swayamprabha.pdf22 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect 's Certificate_Swyamprabha Soc _1-7-17.pdf14 Jul 2017
Details of encumbrancesFile: ENCUM_ Swyamprabha.pdf4 Jul 2017
Proforma of Allotment letterFile: Swayamprabha RERA MODEL AGREEMENT II.pdf4 Jul 2017
Copy of the legal title reportFile: Swayamprbha S and T.pdf12 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Swayamprbha Commencement Certificate-2017.pdf12 Jun 2017
Layout approvalFile: Swayamprbha layout.pdf2 Jun 2017
Building plan approvalFile: Swayamprbha layout.pdf2 Jun 2017
PAN CardFile: Pate GNN PAN.PDF2 Jun 2017
Copy of Layout Approval (in case of layout)File: Swayamprbha layout.pdf2 Jun 2017
Building Plan Approval (IOD)File: Swayamprbha layout.pdf2 Jun 2017

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
TRUPTITHORAT LANE CTS NO 109 FINAL PLOT NO 54 ERANDWANE PUNE11CompletedJan 2017Jan 2017
MATRUSMRITI APARTMENTSERANDWANE OPP SNDT COLLEGE PALANDE COURIER LANE KOTHRUD PUNE12CompletedDec 2016Late, Apr 2017
PERFECT APARTMENTSSURVEY NO 44 4 45 5 AND 46 7 CTS NO 323 AND 327 PLOT NO 14 AND 15 SHEELAVIHAR COLONY KOTHRUD26CompletedDec 2016Dec 2016
CENTURY COOPERATIVE HOUSING SOCIETY LTDSURVEY NO 45 9A CTS NO 323 SHEELAVIHAR COLONY KOTHRUD16CompletedAug 2016Aug 2016
VIJIGISHAS NO 93B 1B SHIVAJINAGAR BHAMBURDA PUNE20CompletedAug 2016Late, Oct 2016
ANUVEEPLOT NO 55 DHANUKAR COLONY14CompletedJul 2016Jul 2016
KALAKUNJ A BSR NO 26 DAHANUKAR COLONY KOTHRUD 3840CompletedJun 2016Late, Dec 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWAYAMPRABHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rambaug Colony13,700+ in Pune

2 kmSWAYAMPRABHACompleted 74Lapsed / revoked 53Other 132Dot size: filed unitsN

Filed coordinates, straight-line distance. 259 registered projects within 2 km.

Builder: Gruha Navnirman Developers

Gruha Navnirman Developers has 5 registrations on MahaRERA, including TRIMURTI and SWAYAMPRABHA. Its filings disclose 7 earlier MahaRERA projects: declares 4 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SWAYAMPRABHA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SWAYAMPRABHA is delayed beyond 15 Aug 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWAYAMPRABHA?

The registered promoter entity is Gruha Navnirman Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWAYAMPRABHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWAYAMPRABHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWAYAMPRABHA?

The professionals named in the filing: Architect: ADESIGNSTUDIO ARCH SIDDHARTH HARISHCHANDRAKAR; Engineer: G A Bhilare Consultants Private Limited GA BHILARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWAYAMPRABHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWAYAMPRABHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWAYAMPRABHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.