Home / Browse projects / Pune, Maharashtra / SWASTIK MILAN

Registered No litigation declared Residential / Group Housing project

SWASTIK MILAN

By SWASTIKCONSTRUCTION

RG-MH-22339 · RERA P52100031496 · Last updated on MahaRERA portal: 19 Nov 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 37 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 37 months from the original
4 of 11Construction stages donefurthest along: External plumbing and external plaster, 80%
12 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SWASTIK MILAN is a Residential / Group Housing project by SWASTIKCONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100031496 on 25 Oct 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 37 months from the original filing. 4 of the 16 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSWASTIK MILAN
  • TypeResidential / Group Housing
  • Location
    • MHALUNGE
    • PUNE
    • Balewadi
    • Haveli
    • 411045
  • Pincode411045
  • RERA no.P52100031496
  • ReraGenie IDRG-MH-22339

Builder

  • NameSWASTIKCONSTRUCTION
  • Entity typePartnership
  • PartnersVISHWANATH PADALE, YAMUNABAI PADALE, SUNIL DEOKAR, MURLIDHAR PADALE, rangubai padale, USHA PADALE, NINAD PADALE, bhamabai baban padale
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2021First promiseSep 2023Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Oct 2021
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 12 Sep 2023)
  • Buildings1 building record
  • Documents filed37 files

Current status

25%4 of 16 units booked
100.0%Work done, per cost certificate

Figures as on 19 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SWASTIK MILANNA6416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 80%.

SWASTIK MILAN: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 19 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area561 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
VISHWANATH PADALEMahalungePune
SUNIL DEOKARMahalungePune
BABAN PADALEMahalungePune
NINAD PADALEMahalungePune
MURLIDHAR PADALEMahalungePune
SWASTIK CONSTRUCTIONMahalungePune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI692.52
Proposed, not sanctioned693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANER MAHAUNGE ROAD PUNE 411028
Estimated costRs 5.31 cr
Cost incurredRs 5.31 cr
Work done100.0%
BuildingWingEstimatedIncurred
-NARs 2.94 crRs 2.94 cr
SWASTIK MILANNARs 2.37 crRs 2.37 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSOURABH SHINDE AND ASSOCIATE
ArchitectNEOSYS DESIGN STUDIO PVT LTD
EngineerULHAS RAUT
Chartered AccountantSANKET SHAH
Chartered AccountantSANJAY DODIYA
PartnerRole in project
SWASTIKCONSTRUCTION-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018195Sep 2023 → Feb 2025

Reason as filed by the promoterDUE TO DELAY OF COMPLETION CCERTIFICATE

EA29102518194Sep 2023 → Oct 2026

Reason as filed by the promoterDELAY IN COMPLETION CERTIFICATE

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 (ARCHITECT CERTIFICATE).pdf19 Nov 2025
Form 2File: ENGINEER CERTIFICATE (FORM 2).pdf19 Nov 2025
Form 3File: FORM 3 (3).pdf19 Nov 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf19 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 (29).pdf19 Nov 2025
Withdrawal Update Form 1File: Architect's Certificate.pdf28 Oct 2025
Withdrawal Update Form 2File: ENGINEER CERTIFICATE (FORM 2).pdf28 Oct 2025
Withdrawal Update Form 3File: FORM 3 (1).pdf28 Oct 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: milan swastik viren sir date FORM 2.pdf10 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: milan swastik viren sir form 2A ajjjjj.pdf10 May 2024
Disclosure of sold/ booked inventoryFile: parat oswal sir.pdf10 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: parat oswal sir 3.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: parat oswal sir 2.pdf25 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: parat oswal sir 3.pdf25 Apr 2024
Declaration in FORM BFile: FORM B.pdf1 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf1 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate.pdf1 Mar 2024
Disclosure of sold/ booked inventoryFile: Swastik Milan.pdf1 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate.pdf1 Mar 2024
Declaration about Commencement CertificateFile: DCC-compressed.pdf21 Oct 2021
Copy of the legal title reportFile: SEARCH REPORT NEW-converted.pdf18 Oct 2021
Proforma of Allotment letterFile: SWASTIK MILAN AGREEMENT AND SALE.pdf15 Oct 2021
Building plan approvalFile: HPSC0361-compressed.pdf9 Oct 2021
Layout approvalFile: HPSC0361-compressed.pdf9 Oct 2021
Copy of Layout Approval (in case of layout)File: HPSC0361-compressed.pdf9 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: HPSC0361-compressed.pdf9 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: SodaPDF-compressed-VIKASANKARARNAMA 9529 - 2021-compressed (1) (1)_reduce (1) (1)_compress9 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: MILAN CC_compressed.pdf3 Oct 2021
Proforma of Allotment letterFile: NEW ALLOTTEMENT.pdf3 Oct 2021
Disclosure of sold/ booked inventoryFile: rera Sold inventory NEW.pdf16 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate-Form 3_compressed.pdf16 Sep 2021
Layout approvalFile: Vishwanath-Swastik JV_sALE pLAN.pdf12 Sep 2021
Details of encumbrancesFile: Allottment milan.pdf12 Sep 2021
Copy of Layout Approval (in case of layout)File: Vishwanath-Swastik JV_sALE pLAN.pdf12 Sep 2021
Declaration in FORM BFile: Rera Form B.pdf12 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR CERTIFICATE.pdf12 Sep 2021

How this compares with Pune

25%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 37 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWASTIK MILAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

Builder: SWASTIKCONSTRUCTION

SWASTIKCONSTRUCTION has 4 registrations on MahaRERA, including SWASTIK MUHURTAM and SWASTIK MANORATH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SWASTIK MILAN is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWASTIK MILAN?

The registered promoter entity is SWASTIKCONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWASTIK MILAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWASTIK MILAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWASTIK MILAN?

The professionals named in the filing: Architect: SOURABH SHINDE AND ASSOCIATE; Architect: NEOSYS DESIGN STUDIO PVT LTD; Engineer: ULHAS RAUT; Chartered Accountant: SANKET SHAH; Chartered Accountant: SANJAY DODIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWASTIK MILAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWASTIK MILAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWASTIK MILAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.