ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SWARANAND

Registered No litigation declared Residential / Group Housing project

SWARANAND

By IMG DEVELOPERS

RG-MH-24458 · RERA P52100008149 · Last updated on MahaRERA portal: 24 Jan 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 95 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 95 months from the original
0 of 11Construction stages donefurthest along: Staircases, 90%
8 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

SWARANAND is a Residential / Group Housing project by IMG DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100008149 on 18 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 95 months from the original filing. 12 of the 20 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameSWARANAND
  • TypeResidential / Group Housing
  • Location
    • The Jewel of Magarpatta
    • Magarpatta Rear Approach
    • Hadapsar
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100008149
  • ReraGenie IDRG-MH-24458

Builder

  • NameIMG DEVELOPERS
  • Entity typePartnership
  • PartnerMAKARAND VASANT SHENDE

Key dates

this monthRegisteredAug 2017First promiseJan 2021Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 Aug 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Jan 2021)
  • Buildings1 building record
  • Documents filed56 files

Current status

60%12 of 20 units booked
5006.4%Work done, per cost certificate

Figures as on 24 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SWARANANDNA8520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

SWARANAND: 26% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 24 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered1
Open Space12

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,246 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Jun 2025
LandownerVillageDistrict
SHAMRAO HIRAJI TUPEHadapsarPune
Sanjeev J PhansalkarBhilarewadiPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1752.0
Proposed, not sanctioned1,104 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOREGAONPARK PUNE
Estimated costRs 5.66 cr
Cost incurredRs 283.23 cr
Work done5006.36%
BuildingWingEstimatedIncurred
SWARANANDNARs 5.60 crRs 283.20 cr
-NARs 5.72 lakhRs 3.43 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJEEV PHANSALKAR Sanjeev Phansalkar
EngineerANSHUMAN BHIDE
EngineerDinesh Anchan
Chartered AccountantDPNS AND CO
Chartered AccountantRSPH And Associates
Chartered AccountantAN SHETTY
PartnerRole in project
IMG DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012741Jan 2021 → Mar 2023

Reason as filed by the promoterWe have nearly completed the project and applied for the NOCs from the various departments. We need some extra time to acquire the road area as per the sanctioned plans. It will take another couple of months to complete this process and then we can apply for an occupancy certificate.

EXT52100009109Jan 2021 → Dec 2021

Reason as filed by the promoterMainly due to COVID19, We get Delayed to complete 1st phase of Project. Non development of adjoining 18M. wide DP Road. This affected to the Sales of already constructed Flats.

EA26082502440Jan 2021 → Dec 2028

Reason as filed by the promoterDue to delays caused bymaterial shortages, labor shortages, and insufficient funding, the project hasbeen delayed. However, with the funding now available, we kindly request an extension until 31/12/2028 to complete the project The flats are in the name of the partner, out of which he has sold 4 and 4 remain unsold. This partner has now been removed from the company. The 3 flats in the name of the company are also still unsold. Therefore, the 51% consent cannot be achieved. Further, part completion for this project has already been received, and an extension is required for completing the pend

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SWARANAND F1.pdf24 Jan 2026
Withdrawal Update Form 1File: SWARANAND F1.pdf24 Jan 2026
Withdrawal Update Form 1File: SWARANAND F1.pdf24 Jan 2026
Withdrawal Update Form 2File: SWARANAND F2.pdf24 Jan 2026
Withdrawal Update Form 2File: SWARANAND F2.pdf24 Jan 2026
Withdrawal Update Form 2File: SWARANAND F2.pdf24 Jan 2026
Withdrawal Update Form 3File: SWARANAND F3_compressed.pdf24 Jan 2026
Withdrawal Update Form 3File: SWARANAND F3_compressed.pdf24 Jan 2026
Withdrawal Update Form 3File: SWARANAND F3_compressed.pdf24 Jan 2026
Form 2A (FY 2022-2023)File: 0 (28).pdf26 Aug 2025
Form 5 (FY 2022-2023)File: 0 (29).pdf26 Aug 2025
Form 1File: 1-Architect Certificate March 22.pdf26 Jun 2025
Form 2File: 1-Engineer Certificate-March-22.pdf26 Jun 2025
Form 3File: 1-CA Certificate-March 22 final.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 1-Disclosure March 22.pdf26 Jun 2025
Form 1File: 2-Architect Certificate June 22.pdf26 Jun 2025
Form 2File: 2 Engineer Certificate- June 22.pdf26 Jun 2025
Form 3File: 2-CA Certificate-June 22 final.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 2-Disclosure June 22.pdf26 Jun 2025
Form 1File: 3-Architect Certificate Sept 22.pdf26 Jun 2025
Form 2File: 3 Engineer Certificate- Sept 22.pdf26 Jun 2025
Form 3File: 3-CA Certificate-Sept 22 final.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 3-Disclosure-Sept 22.pdf26 Jun 2025
Form 1File: 4-Architect Certificate Dec 22.pdf26 Jun 2025
Form 2File: 4Engineer Certificate- Dec 22.pdf26 Jun 2025
Form 3File: 4-CA Certificate-Dec 22 final.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 4-Disclosure Dec 22.pdf26 Jun 2025
Form 1File: 5-Architect Certificate March 23.pdf26 Jun 2025
Form 2File: 5 Engineer Certificate- March 23.pdf26 Jun 2025
Form 3File: 5-CA Certificate-March 23 final.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: 5-Disclosure -March 23.pdf26 Jun 2025
Declaration about Commencement CertificateFile: 05 DECLARATION OF CC IN FORMAT-D -LETTER HEAD.pdf9 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 03-CA FORM-5-2020-2021.pdf9 Nov 2022
Disclosure of sold/ booked inventoryFile: 04 DISCLOSURE OF SOLD FLATS.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 03-CA FORM-5-2017-2018.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 03-CA FORM-5-2018-2019.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 03-CA FORM-5-2019-2020.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 03-CA FORM-5-2020-2021.pdf9 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 03-CA FORM-5-2021-2022.pdf9 Nov 2022
Proforma of Agreement for saleFile: FLAT PURCHASE AGREEMENT FOR RERA FORMATS.pdf9 Nov 2022
Building plan approvalFile: Revised plan R-1.PDF31 Jul 2017
Building plan approvalFile: Revised plan R-2.pdf31 Jul 2017
Layout approvalFile: Revised plan R-1.PDF31 Jul 2017
PAN CardFile: IMG DEVELOPERS PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: SERACH REPORT-P1-7.pdf31 Jul 2017
Copy of the legal title reportFile: SERACH REPORT-P-8-12.pdf31 Jul 2017
Details of encumbrancesFile: SERACH REPORT-P1-7.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Revised plan R-1.PDF31 Jul 2017
Building Plan Approval (IOD)File: Revised plan R-1.PDF31 Jul 2017
Building Plan Approval (IOD)File: Revised plan R-2.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: new commencement certficate.pdf31 Jul 2017
Declaration in FORM BFile: Form B-SUBMITTED 20170731.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: new commencement certficate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA_ENGINEER certificate_FORM2.pdf31 Jul 2017
Certificates of CA (Form 3)File: CERTIFICATE OF CA-FORM 3.pdf31 Jul 2017
Proforma of Allotment letterFile: IMG- SWARANAND-allotment letter.pdf31 Jul 2017

How this compares with Pune

60%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 95 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SWARANAND on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Magarpatta Rear Approach13,700+ in Pune

2 kmSWARANANDCompleted 45Lapsed / revoked 20Other 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 131 registered projects within 2 km.

Builder: IMG DEVELOPERS

IMG DEVELOPERS has 1 registration on MahaRERA, including SWARANAND. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SWARANAND is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWARANAND?

The registered promoter entity is IMG DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWARANAND?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWARANAND?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWARANAND?

The professionals named in the filing: Architect: SANJEEV PHANSALKAR Sanjeev Phansalkar; Engineer: ANSHUMAN BHIDE; Engineer: Dinesh Anchan; Chartered Accountant: DPNS AND CO; Chartered Accountant: RSPH And Associates; Chartered Accountant: AN SHETTY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWARANAND?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWARANAND. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWARANAND to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.