Home / Browse projects / Ratnagiri, Maharashtra / Swami Swarupanand Elite
Swami Swarupanand Elite
RG-MH-02988 · RERA P52800020193 · Last updated on MahaRERA portal: 27 Sep 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 41 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Swami Swarupanand Elite is a Others project by Pravin Narayan Lad in Ratnagiri, Maharashtra, registered with MahaRERA as P52800020193 on 29 Mar 2019. Possession was promised by 29 May 2023 and is now 41 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSwami Swarupanand Elite
- TypeOthers
- Location
- Ratnagiri Pawas Road
- Near Hotel Nisarg
- Kasop
- Ratnagiri
- 415612
- Pincode415612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800020193
- ReraGenie IDRG-MH-02988
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Mar 2019
- Promised completion29 May 2023
- Revised completionRevised to 29 May 2023 (originally 30 May 2022)
- Buildings1 building record
- Documents filed22 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Swami Swarupanand Elite | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Swami Swarupanand Elite: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shabbir Hamza Borkar |
| Engineer | Manoj S Joshi |
| Partner | Role in project |
|---|---|
| Pravin Narayan Lad | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAPPROXOMATE 70% WORK IS COMPETED AND REMAINING WORK IS IN PROGRESS
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Sep 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Mar 2022
Documents filed22
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: plan.pdf | 27 Sep 2022 |
| Copy of Layout Approval (in case of layout)File: plan.pdf | 27 Sep 2022 |
| Declaration about Commencement CertificateFile: DECLARATION.pdf | 27 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2a 19-20.pdf | 27 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 27 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19-20.pdf | 27 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21.pdf | 27 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK FORMAT.pdf | 27 Sep 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SSE Occupancy Certificate.pdf | 17 Mar 2022 |
| Building plan approvalFile: Permission.pdf | 26 Mar 2019 |
| Layout approvalFile: layout.pdf | 26 Mar 2019 |
| PAN CardFile: Pan Card.pdf | 26 Mar 2019 |
| Copy of the legal title reportFile: Search.pdf | 26 Mar 2019 |
| Details of encumbrancesFile: Encumbrance.pdf | 26 Mar 2019 |
| Copy of Layout Approval (in case of layout)File: layout.pdf | 26 Mar 2019 |
| Building Plan Approval (IOD)File: Permission.pdf | 26 Mar 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Permission.pdf | 26 Mar 2019 |
| Declaration in FORM BFile: form B.pdf | 26 Mar 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 26 Mar 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form2.pdf | 26 Mar 2019 |
| Certificates of CA (Form 3)File: form 3.pdf | 26 Mar 2019 |
| Proforma of Allotment letterFile: Agreement to sale.pdf | 26 Mar 2019 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Janaki ComplexP52800017248 | Fish Market, Ratnagiri | Jul 2018 | Completed | Dec 2019 | Late, Aug 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 22 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Swami Swarupanand Elite on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Hotel Nisarg1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 56 registered projects within 2 km.
Navkar Enclave
Evergreen Associates
Kalpavriksha Heritage
Kalpavriksha Builders & Developers
LAXMI KEHSAV NAGAR PHASE II
DEEPAK YASHWANT SALVI
THE WIND
Arihant Vastu Nirman Pvt. Ltd
THE WOODLAND
Siddhivinayak Realty
AKAR VANAJU ESTATE
AKAR INFRASTRUCTURE
See every Ratnagiri project, with the district possession charts
Builder: Pravin Narayan Lad
Pravin Narayan Lad has 5 registrations on MahaRERA, including Janaki Complex and Swami Swarupanand Elite. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What does it mean that Swami Swarupanand Elite shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Swami Swarupanand Elite is delayed beyond 29 May 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Swami Swarupanand Elite?
The registered promoter entity is Pravin Narayan Lad, an individual as per the filing. Its GSTIN 27AAXPL4681K1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Swami Swarupanand Elite?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Swami Swarupanand Elite?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Swami Swarupanand Elite?
The professionals named in the filing: Architect: Shabbir Hamza Borkar; Engineer: Manoj S Joshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Swami Swarupanand Elite?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback