Home / Browse projects / Nashik, Maharashtra / SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL

Completed No litigation declared Others project

SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL

By SUN INFRASTRUCTURES PVT. LTD

RG-MH-01320 · RERA P51600002585 · Last updated on MahaRERA portal: 6 Jul 2022

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL is a Others project by SUN INFRASTRUCTURES PVT. LTD in Nashik, Maharashtra, registered with MahaRERA as P51600002585 on 2 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2022. The completion date has moved by 45 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL
  • TypeOthers
  • Location
    • NASHIK PUNE ROAD
    • NEAR BIRLA HOSPITAL
    • NASHIK ROAD
    • Deolali (CB)
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600002585
  • ReraGenie IDRG-MH-01320

Builder

  • NameSUN INFRASTRUCTURES PVT. LTD
  • Entity typeCompany
  • Managing DirectorsANANT KESHAV RAJEGAONKAR, ANIL BHAVARLAL JAIN
  • Other registrations23 more →
  • Completed3 of 24
  • No longer live17 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Aug 2017
  • Promised completion31 Dec 2022
  • Revised completionRevised to 31 Dec 2022 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUYOJIT ONE WORLD COMMERCIAL AND HOSPITALNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

SUYOJIT ONE WORLD COMMERCIAL AND HOSPITAL: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 6 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed127

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots127
Closed/Covered33
Open Space94

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,292 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7327.13
Proposed, not sanctioned7,327 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIRAJ CORNER, CANADA CORNER, NASHIK-422002

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANANT TECHNOCRATS PVT LTD
EngineerRELIABLE ENTERPRISES
PartnerRole in project
SUN INFRASTRUCTURES PVT. LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600011223Mar 2019 → Dec 2022

Reason as filed by the promoterDear Sir, We hereby apply for extension u/s 7(3) of the registered proejct bearing no. P5160002623.

EXT51600001630Mar 2019 → Dec 2020

Reason as filed by the promoterRef. Maharera Registration No. P51600002585, Project Name “ Suyojit One World Phase-¬II, Commercial And Hospital ” Dear Sir, In this connection, we have to state that we have submitted revised building plan of subject project to the Nashik Municipal Corporation, Nashik, long back, for approval. There is procedure of approval of revised plans before applying for occupation certificate. However the approval thereto has been pending at Nashik Municipal Corporation due to compulsory implementation of Auto DCR system (online processing & approval). However software of Auto DCR system is not compati

EXT51600006009Mar 2019 → Dec 2020

Reason as filed by the promoterWe have submitted revised building plan of subject project to the NMC, long back for approval. However the approval thereto has been pending at NMC due to compulsory implementation of Auto DCR System (online processing & Approval). Therefore auto DCR software was not accepting revised plans proposal. Hence all revised plans were stuck up in NMC. Due to this grant of revised plan approval is delayed and consequently completion certificate is also not yet issued by NMC in respect of said project. The revised building plans are approved on 24/10/2019 under its letter No. LND/BP/C3/143/2019. In th

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC001000000000107G N ADGAONKAR JEWELSM/S SUN INFRASTRUCTURES PVT LTD24/06/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: One Commercial Form 4.pdf6 Jul 2022
CERSAI detailsFile: CERSAI_Search_Report_200227184380_For_Asset_Based_Search_03_01_2022_11_00_50_029.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227184988_For_Asset_Based_Search_03_01_2022_11_02_40_752.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185278_For_Asset_Based_Search_03_01_2022_11_04_11_743.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185351_For_Asset_Based_Search_03_01_2022_11_05_00_491.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185409_For_Asset_Based_Search_03_01_2022_11_05_35_461.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185493_For_Asset_Based_Search_03_01_2022_11_06_23_598.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185573_For_Asset_Based_Search_03_01_2022_11_07_07_034.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185705_For_Asset_Based_Search_03_01_2022_11_08_05_906.pdf11 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200227185741_For_Asset_Based_Search_03_01_2022_11_08_29_531.pdf11 Jan 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD ONE WORLD.pdf11 Jan 2022
Form 2AFile: Quality Certificate Suyojit One World-Phase-II, Commercial.pdf8 Nov 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CATIFICATE.pdf19 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM- 5 SUYOJIT ONE WORLD PHASE II COMMERCIAL.pdf19 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SUN INFRA BY SUYOJIT ONE WORLD RERA CARIFICATE PHASE-II.pdf19 Oct 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration for Commercial Hospital.pdf20 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: One Word Commercial.pdf14 Aug 2021
Form 2AFile: One World Commercial.pdf5 Aug 2021
Form 2AFile: One World Commercial-compressed.pdf1 Jun 2021
Building plan approvalFile: PLAN ONE WORLD.pdf7 May 2021
Building Plan Approval (IOD)File: PLAN ONE WORLD.pdf7 May 2021
Form 2AFile: ONE WORLD COMMERCIAL.pdf3 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: One World Commercial.pdf27 Mar 2021
Form 2AFile: Suyoit One World commercial.pdf8 Dec 2020
Form 2AFile: SUYOJIT ONE WORD PHASE 2001.pdf26 Jun 2020
Form 2AFile: SUYOJIT WON WORD PHASE 2.pdf4 Feb 2020
Form 2AFile: SUYOJIT ONE WORD PHASE 2.pdf25 Oct 2019
Architect’s Certificate on Completion of Project (Form 4)File: form 4 Completion Certificate - Phase 2_compressed.pdf3 Sep 2019
Form 2AFile: ONE WORLD PHASE II.pdf19 Jul 2019
Form 2AFile: Suyojit One World Comme.pdf8 Apr 2019
Form 2AFile: FORM 2A One World - Comm.pdf17 Jan 2019
Certificates of CA (Form 5)File: CA Certificate - One World Commercial.pdf2 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineers Certificate (1).pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE FF.pdf27 Jul 2017
Layout approvalFile: suyojit one world phase-ii plan 1.pdf26 Jul 2017
Details of encumbrancesFile: No Encumrances certificate developer f.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: suyojit one world phase-ii plan 1.pdf26 Jul 2017
Declaration in FORM BFile: form B.pdf26 Jul 2017
Proforma of Allotment letterFile: undertaking.pdf26 Jul 2017
OtherFile: Development Agreement.pdf26 Jul 2017
Building plan approvalFile: suyojit one world phase-ii plan 1.pdf25 Jul 2017
Building plan approvalFile: suyojit one world phase ii plan2.pdf25 Jul 2017
Building plan approvalFile: suyojit one world phase-ii plan 3.pdf25 Jul 2017
Building plan approvalFile: suyojit one world phase ii plan 4.pdf25 Jul 2017
Building plan approvalFile: suyojit one world phase ii plan5.pdf25 Jul 2017
PAN CardFile: SUN PAN.pdf25 Jul 2017
Copy of the legal title reportFile: Title Report-Suyojit One World-20-7-2017 (1).pdf25 Jul 2017
Building Plan Approval (IOD)File: suyojit one world phase-ii plan 1.pdf25 Jul 2017
Building Plan Approval (IOD)File: suyojit one world phase ii plan2.pdf25 Jul 2017
Building Plan Approval (IOD)File: suyojit one world phase-ii plan 3.pdf25 Jul 2017
Building Plan Approval (IOD)File: suyojit one world phase ii plan 4.pdf25 Jul 2017
Building Plan Approval (IOD)File: suyojit one world phase ii plan5.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate-one world2.pdf25 Jul 2017
Certificates of CA (Form 3)File: Document1.pdf25 Jul 2017

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 45 months
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND H on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR BIRLA HOSPITAL, NASHIK ROAD4,100+ in Nashik

2 kmSUYOJIT ONE WORLD PHASE-Completed 36Lapsed / revoked 8Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: SUN INFRASTRUCTURES PVT. LTD

SUN INFRASTRUCTURES PVT. LTD has 24 registrations on MahaRERA, including SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR and SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

The registered promoter entity is SUN INFRASTRUCTURES PVT. LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

The professionals named in the filing: Architect: ANANT TECHNOCRATS PVT LTD; Engineer: RELIABLE ENTERPRISES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND HOSPITAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYOJIT ONE WORLD PHASE-II, COMMERCIAL AND H to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.