Home / Browse projects / Mumbai Suburban, Maharashtra / SUYASH
SUYASH
RG-MH-73785 · RERA P51800034301 · Last updated on MahaRERA portal: 14 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 18 months past the filed date
- Completion date moved by 19 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUYASH is a Residential / Group Housing project by DVASUYASH CONSTRUCTION LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034301 on 30 Mar 2022. Possession was promised by 11 Apr 2025 and is now 18 months past that date. The completion date has moved by 19 months from the original filing.
At a glance
Project
- NameSUYASH
- TypeResidential / Group Housing
- Location
- P.M. ROAD
- VILE PARLE
- Greater Mumbai (M Corp.) (Part) (802794)
- Mumbai
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800034301
- ReraGenie IDRG-MH-73785
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on30 Mar 2022
- Promised completion11 Apr 2025
- Revised completionRevised to 11 Apr 2025 (originally 30 Sep 2023)
- Buildings1 building record
- Documents filed87 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUYASH | NA | 10 | 6 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
SUYASH: 88% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MRS. ANJALI RAJENDRA BHAGTTJEE | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
| MRS. SHILPA PRAKASH CHAUBAL | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
| MRS. MINAL KETAN DIGHE | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
| MRS. JYOTSNA ANAND BHATE | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOMESH RAO |
| Engineer | FRAMES |
| Engineer | NIKHIL SARVAIYA SARVAIYA |
| Chartered Accountant | VINATA VIDYA & CO |
| Partner | Role in project |
|---|---|
| DVASUYASH CONSTRUCTION LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of SUYASH’- As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30/09/2023 as the project completion date, we will not be able to complete the project on given date due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices
Reason as filed by the promoterPOST FACTO
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Mar 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Jan 2025
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1_SUYASH_JUNE 2024 (1).pdf | 14 Jul 2026 |
| Form 2File: FORM 2_SUYASH_JUNE 2024 (1).pdf | 14 Jul 2026 |
| Form 3File: FORM 3_SUYASH_JUNE 2024 (1).pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-SUYASH_JUNE 2024 (1).pdf | 14 Jul 2026 |
| Form 1File: FORM 1_SUYASH_JUNE 2025 (1).pdf | 14 Jul 2026 |
| Form 2File: FORM 2_SUYASH_JUNE 2025 (1).pdf | 14 Jul 2026 |
| Form 3File: FORM 3_SUYASH_JUNE 2025.pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-SUYASH_JUNE 2025 (1).pdf | 14 Jul 2026 |
| Form 1File: FORM 1_SUYASH_MARCH 2025 (1).pdf | 14 Jul 2026 |
| Form 2File: FORM 2_SUYASH_MARCH 2025 (1).pdf | 14 Jul 2026 |
| Form 3File: FORM 3_SUYASH_MARCH 2025 (1).pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-SUYASH_MARCH 2025 (1).pdf | 14 Jul 2026 |
| Form 1File: FORM 1_SUYASH_DEC 2024 (1).pdf | 14 Jul 2026 |
| Form 2File: FORM 2_SUYASH_DEC 2024 (1).pdf | 14 Jul 2026 |
| Form 3File: FORM 3_SUYASH_DEC 2024 (1).pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-SUYASH_DEC 2024 (1).pdf | 14 Jul 2026 |
| Form 1File: FORM 1_SUYASH_SEPT 2024 (1).pdf | 14 Jul 2026 |
| Form 2File: FORM 2_SUYASH_SEPT 2024 (1).pdf | 14 Jul 2026 |
| Form 3File: FORM 3_SUYASH_SEPT 2024 (1).pdf | 14 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD-SUYASH_SEPT 2024 (1).pdf | 14 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A (1).pdf | 14 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A (1) (1).pdf | 14 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A (1) (1).pdf | 14 Jul 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 SUYASH (1).pdf | 14 Jul 2026 |
| Form 5 (FY 2025-2026)File: FORM 5 SUYASH (1) (1).pdf | 14 Jul 2026 |
| Declaration in FORM BFile: P51800034301_FileName_2.pdf | 22 May 2025 |
| Copy of the legal title reportFile: 28 Legal title Report - REVISED.pdf | 6 Mar 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 199798116NoteSheet_24351_signed_250121_174136.pdf | 27 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 4 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 4 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-SUYASH_DEC 23.pdf | 16 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-SUYASH_DEC 23_compressed.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-SUYASH_DEC 23.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-SUYASH_DEC 23_compressed.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-SUYASH_SEP 23.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-SUYASH_SEP 23.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-SUYASH_22-23.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-SUYASH_SEP 23.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-SUYASH_SEP 23_compressed.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-SUYASH_22-23_compressed.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-SUYASH_JUN 23.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-SUYASH_JUN 23.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD-SUYASH_JUN 23.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-SUYASH_JUN 23_compressed.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: GetUserDocumentFileContent (1).pdf | 2 Jul 2023 |
| Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf | 20 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1.pdf | 19 Jun 2023 |
| Details of encumbrancesFile: rera intimation_1.pdf | 12 Jun 2023 |
| Proforma of Agreement for saleFile: Draft Agreement.pdf | 12 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf | 5 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf | 5 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: SUYASH.pdf | 5 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 4 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 4 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed (1).pdf | 4 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 28 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 28 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 28 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 28 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf | 22 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 22 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 22 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 4 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_compressed.pdf | 4 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 4 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_compressed.pdf | 4 Oct 2022 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf | 21 Mar 2022 |
| Layout approvalFile: PLAN.pdf | 19 Mar 2022 |
| Building plan approvalFile: PLAN.pdf | 19 Mar 2022 |
| PAN CardFile: DVASUYASH PAN -compressed.pdf | 19 Mar 2022 |
| Copy of the legal title reportFile: LEGAL TITLE SEARCH REPORT_compressed.pdf | 19 Mar 2022 |
| Details of encumbrancesFile: NO ENCUMBRANCES.pdf | 19 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: PLAN.pdf | 19 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf | 19 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 19 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SUYASH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILE PARLE6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 362 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: DVASUYASH CONSTRUCTION LLP
DVASUYASH CONSTRUCTION LLP has 3 registrations on MahaRERA, including SUYASH and SUYASH EMINENCE. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that SUYASH shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SUYASH is delayed beyond 11 Apr 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUYASH?
The registered promoter entity is DVASUYASH CONSTRUCTION LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUYASH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SUYASH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUYASH?
The professionals named in the filing: Architect: YOMESH RAO; Engineer: FRAMES; Engineer: NIKHIL SARVAIYA SARVAIYA; Chartered Accountant: VINATA VIDYA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUYASH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.