Home / Browse projects / Pune, Maharashtra / SUYASH TOWER
SUYASH TOWER
RG-MH-72907 · RERA P52100045939 · Last updated on MahaRERA portal: 28 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 32 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUYASH TOWER is a Residential / Group Housing project by SUYASH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100045939 on 15 Jun 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 32 months from the original filing. 2 of the 11 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameSUYASH TOWER
- TypeResidential / Group Housing
- Location
- KASBA PETH
- Pune (M Corp.)
- Pune City
- Pune
- 411011
- Pincode411011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100045939
- ReraGenie IDRG-MH-72907
Builder
- NameSUYASH ASSOCIATES
- Entity typePartnership
- PartnersHARIKISAN SHANKAR CHAVAN, TASLEEM HANIF SHAIKH, NAZIR GULABNABI PATHAN, SHAHID SADIK PATEL, KARIM REHMAN SAYYED
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jun 2022
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2025)
- Buildings1 building record
- Documents filed27 files
Current status
Figures as on 28 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUYASH TOWER | NA | 5 | 5 | 11 | 0 | 11 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
SUYASH TOWER: 33% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
Progress on shared amenities15
As on 28 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership14
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| PARAG VILASH GHADGE | Pune (M Corp.) | Pune |
| MADHAVISHEKHAR GORI | Pune (M Corp.) | Pune |
| MANDAKINI RAJARAM GHADGE | Pune (M Corp.) | Pune |
| MILIND RAJARAM GHADGE | Pune (M Corp.) | Pune |
| RUPALI RAJARAM GHADGE | Pune (M Corp.) | Pune |
| BHARATI JAYANT WAYAL | Pune (M Corp.) | Pune |
| SATISH DATTATRAYA GHADGE | Pune (M Corp.) | Pune |
| ANJANA SUBHASH GHADGE | Pune (M Corp.) | Pune |
| AMOL SUBHASH GHADE | Pune (M Corp.) | Pune |
| USHA ASHOK GHADGE | Pune (M Corp.) | Pune |
| YATIN Alias ANIL ASHOK GHADGE | Pune (M Corp.) | Pune |
| RASHMI SANTOSH SARAL (GARAD0 | Pune (M Corp.) | Pune |
| ROHINI ABHIJEET NIMBALKAR | Pune (M Corp.) | Pune |
| SUYASH ASSOCIATES | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SUYASH TOWER | NA | Rs 5.85 cr | Rs 5.85 cr |
| - | NA | Rs 10.00 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARVEEN M ANSARI |
| Architect | Rahil Shaikh |
| Engineer | S V & ASSOCIATES |
| Engineer | Zaki Shaikh |
| Chartered Accountant | D S D & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SUYASH ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Oct 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed27
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: DOC019 (1).PDF | 28 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate Form 1.pdf | 28 Oct 2025 |
| Withdrawal Update Form 2File: Structural Engineer Certificate Q2.pdf | 28 Oct 2025 |
| Withdrawal Update Form 3File: CA Certificate ForM 3 - Q2.pdf | 28 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate Form 1.pdf | 19 Oct 2025 |
| Withdrawal Update Form 2File: Structural Engineer Certificate Q2.pdf | 19 Oct 2025 |
| Withdrawal Update Form 3File: CA Certificate ForM 3 - Q2.pdf | 19 Oct 2025 |
| Building plan approvalFile: BUILDING PLAN.pdf | 13 Oct 2025 |
| Form 1File: Architect Certificate Q4 04-07-2025.pdf | 23 Aug 2025 |
| Form 2File: Structural Engineer Certificate Q2.pdf | 23 Aug 2025 |
| Form 3File: CA Certificate ForM 3 - Q2.pdf | 23 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular 29.pdf | 23 Aug 2025 |
| Layout approvalFile: Sanction plan 21-5-2021_compressed.pdf | 3 Jun 2022 |
| Building plan approvalFile: Sanction plan 21-5-2021_compressed.pdf | 3 Jun 2022 |
| PAN CardFile: suyash pan.pdf | 3 Jun 2022 |
| Copy of the legal title reportFile: search and title suyash.pdf | 3 Jun 2022 |
| Details of encumbrancesFile: encumbrances suyash.pdf | 3 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: Sanction plan 21-5-2021_compressed.pdf | 3 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanction plan 21-5-2021_compressed.pdf | 3 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 21-5-2021.pdf | 3 Jun 2022 |
| Declaration about Commencement CertificateFile: declaration of commencement suyash.pdf | 3 Jun 2022 |
| Declaration in FORM BFile: suyash form B.pdf | 3 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arcitect form a suyash_compressed.pdf | 3 Jun 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer form b_compressed.pdf | 3 Jun 2022 |
| CERSAI detailsFile: undertaking.pdf | 3 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form c suyash associates.pdf | 3 Jun 2022 |
| Proforma of Allotment letterFile: FORMAT OF AGREEMENT.pdf | 3 Jun 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 27 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SUYASH TOWER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KASBA PETH13,700+ in Pune
Filed coordinates, straight-line distance. 86 registered projects within 2 km.
Wyng
Manasara Realty LLP
SARA KASTURI BUILDING C
JAGRUTSARA STRUCTURES LLP
ANTRIKSH TOWERS
AUM CITYSCAPES LLP
EVOLET TIARA
M/S EVOLET DEVELOPERS
B. T. SQUARE
AJAY JAYAWANT BHOSLE
GIRNAR
SHREE DATTA REALTORS
Builder: SUYASH ASSOCIATES
SUYASH ASSOCIATES has 1 registration on MahaRERA, including SUYASH TOWER. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SUYASH TOWER is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUYASH TOWER?
The registered promoter entity is SUYASH ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUYASH TOWER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SUYASH TOWER?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUYASH TOWER?
The professionals named in the filing: Architect: PARVEEN M ANSARI; Architect: Rahil Shaikh; Engineer: S V & ASSOCIATES; Engineer: Zaki Shaikh; Chartered Accountant: D S D & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUYASH TOWER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback