Home / Browse projects / Mumbai Suburban, Maharashtra / SUNFLOWER

Completed No litigation declared Residential / Group Housing project

SUNFLOWER

By Shree Krishna Developers

RG-MH-26980 · RERA P51800006422 · Last updated on MahaRERA portal: 31 Jul 2020

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 42 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
5Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SUNFLOWER is a Residential / Group Housing project by Shree Krishna Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006422 on 14 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 42 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameSUNFLOWER
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006422
  • ReraGenie IDRG-MH-26980

Builder

  • NameShree Krishna Developers
  • Entity typePartnership
  • PartnersLEENA SANJAY BANSAL, PRERNA SATISH GARG, SHAMJI SHIVJI FARIA
  • Other registrations11 more →
  • Completed7 of 12
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SUNFLOWERNA160000
SHRAMIK NAGARNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Jul 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

SUNFLOWER91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SHRAMIK NAGAR91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 Jul 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered5
Open Space12
BuildingClosed/CoveredOpen SpaceTotal
SUNFLOWER41216
SHRAMIK NAGAR101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,789 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4556.97
Proposed, not sanctioned4,557 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 2 ON GROUND FLOOR M K PLAZA NEAR ANAND NAGAR OWALE GODHBUNDER ROAD THANE W MAHARASHTRA 40060

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSS ASSOCIATES
EngineerNEXUS PROJECT SOLUTIONS PVT LTD
PartnerRole in project
Shree Krishna Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008645Dec 2018 → Dec 2021

Reason as filed by the promoterWE HEREBY SAY THAT THIS IS A SRA PROJECT. THE SLUM TENANTS ARE REHABILITATED IN THE NEW BUILDING. AS PER THE APPROVALS THE SALE BUILDING IS OF ABOUT 14 FLOORS, TILL 12TH FLOOR OF THE SAID BUILDING PART O.C HAS BEEN OBTAINED ON 19.01.2019, HOWEVER 13TH AND 14TH FLOOR IS COMPLETED AS PER THE FORM -4 DATED 06.02.2020 ISSUED BY THE ARCHITECT S.S.ASSOCIATES THE SAID STRUCTURE IS FIT FOR OCCUPANCY . THE ALLOTTEES HAVE TAKEN THE POSSESSION OF THEIR RESPECTIVE FLATS AND FURTHER EVEN THE CO-OPERTIVE SOCIETY HAS BEEN FORMED BY THE ALLOTTEES IN 2019. I SAY THAT AS PER THE CONDITIONS OF THE IOA/ CC, THE P

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000120944Ashok J KaramchandaniShree Krishna Developers17/09/2019
CC006000000192860ASHOK J KARAMCHANDANIShree Krishna Developers06/03/2020
CC006000000196163Ashok Jamiatsingh KaramchandaniShree Krishna Developers25/02/2021
CC006000000192501SUNFLOWER CHSLShree Krishna Developers07/02/2020
CC006000000195636Ashok KaramchandaniShree Krishna Developers16/01/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Feb 2020

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: STATUS OF CONVEYANCE-.pdf31 Jul 2020
Architect’s Certificate on Completion of Project (Form 4)File: 11_0001-10.pdf7 Feb 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf5 Feb 2020
Architect’s Certificate on Completion of Project (Form 4)File: SANJAY BANSAL FORM 4 .pdf5 Feb 2020
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERTIFICATE.pdf5 Feb 2020
Building plan approvalFile: IOD.pdf29 Jul 2017
Layout approvalFile: 21_0002.pdf29 Jul 2017
Layout approvalFile: 21_0002.pdf29 Jul 2017
Layout approvalFile: 21_0003.pdf29 Jul 2017
Layout approvalFile: 41.pdf29 Jul 2017
Layout approvalFile: 20170726150246341.pdf29 Jul 2017
Layout approvalFile: 21_0004.pdf29 Jul 2017
Layout approvalFile: 41_0004.pdf29 Jul 2017
Layout approvalFile: 41_0002.pdf29 Jul 2017
Layout approvalFile: 41_0003.pdf29 Jul 2017
Layout approvalFile: 41_0001.pdf29 Jul 2017
Layout approvalFile: 31_0006.pdf29 Jul 2017
Layout approvalFile: 31_0005.pdf29 Jul 2017
Layout approvalFile: 31_0001.pdf29 Jul 2017
Layout approvalFile: 31_0002.pdf29 Jul 2017
Layout approvalFile: 31_0003.pdf29 Jul 2017
Layout approvalFile: 31_0004.pdf29 Jul 2017
Layout approvalFile: 41_0005-compressed.pdf29 Jul 2017
PAN CardFile: PAN CARD.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf29 Jul 2017
Details of encumbrancesFile: DECLARATION.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 21_0002.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 21_0002.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 21_0003.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 21_0004.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 20170726150246341.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41_0001.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41_0002.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41_0003.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41_0004.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 41_0005-compressed.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0001.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0002.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0003.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0004.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0005.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: 31_0006.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf29 Jul 2017
Declaration in FORM BFile: DECLARATION.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR CERT - final.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERT.pdf29 Jul 2017
Certificates of CA (Form 3)File: ca.pdf29 Jul 2017
Proforma of Allotment letterFile: allotment draft.pdf29 Jul 2017
Proforma of Allotment letterFile: SHREE_KRISHNA_DEVELOPERS_FINAL_AGREEMENT-.pdf29 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUNFLOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmSUNFLOWERCompleted 92Lapsed / revoked 82Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 292 registered projects within 2 km.

Builder: Shree Krishna Developers

SHREE KRISHNA DEVELOPERS has 12 registrations on MahaRERA, including SHREE KRISHNA HEIGHTS and SUNFLOWER. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SUNFLOWER is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUNFLOWER?

The registered promoter entity is Shree Krishna Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUNFLOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUNFLOWER?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUNFLOWER?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUNFLOWER?

The professionals named in the filing: Architect: SS ASSOCIATES; Engineer: NEXUS PROJECT SOLUTIONS PVT LTD. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUNFLOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUNFLOWER. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUNFLOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.