Home / Browse projects / Mumbai Suburban, Maharashtra / SUN SUMIT JEEVAN MANGAL
SUN SUMIT JEEVAN MANGAL
RG-MH-45817 · RERA P51800046062 · Last updated on MahaRERA portal: 26 Jun 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUN SUMIT JEEVAN MANGAL is a Residential / Group Housing project by SUN SUMIT VENTURE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046062 on 15 Jun 2022. The registration is recorded completed; possession was promised by 29 Jun 2026. The completion date has moved by 12 months from the original filing. 11 of the 20 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameSUN SUMIT JEEVAN MANGAL
- TypeResidential / Group Housing
- Location
- LINK ROAD
- CHIKUWADI BORIVALI WEST
- Borivali
- Mumbai Suburban
- 400092
- Pincode400092
- RERA no.P51800046062
- ReraGenie IDRG-MH-45817
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jun 2022
- Promised completion29 Jun 2026
- Revised completionRevised to 29 Jun 2026 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed81 files
Current status
Figures as on 26 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sun Sumit Jeevan Mangal Phase 1 | NA | 11 | 11 | 8 | 4 | 12 |
| SUN SUMIT JEEVAN MANGAL PHASE 2 | NA | 3 | 0 | 8 | 0 | 8 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 26 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
Sun Sumit Jeevan Mangal Phase 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SUN SUMIT JEEVAN MANGAL PHASE 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 26 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed42
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Sun Sumit Jeevan Mangal Phase 1 | 30 | 30 |
| SUN SUMIT JEEVAN MANGAL PHASE 2 | 12 | 12 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Jeevan Mangal Co Housing Society | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Sun Sumit Jeevan Mangal Phase 1 | NA | Rs 4.34 cr | Rs 4.34 cr |
| - | NA | Rs 3.56 cr | Rs 3.56 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NILESH MAKWANA |
| Architect | Swapnil Ambre |
| Engineer | HIREN TANNA |
| Engineer | Clint Santos |
| Chartered Accountant | PRIYANKA DHRUVA |
| Chartered Accountant | R S Gokani & Co |
| Chartered Accountant | Mulraj D Gala & Co. |
| Chartered Accountant | Mukesh M Choksi |
| Partner | Role in project |
|---|---|
| SUN SUMIT VENTURE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The Construction work of the building was on hold due to major Road digging for infrastructure work and RCC road Construction on the Link Road twice for the period approx. 12 months during this period, it was not possible to deliver the material on site, as the site was not accessible to heavy vehicle to unlaod- material. 2 Further period of 12-15 months is required to complete balance work of site
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Aug 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Aug 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Final March 26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: Form 3_opt.pdf | 26 Jun 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A (2).pdf | 26 Jun 2026 |
| Occupational CertificateFile: OC.pdf | 26 Jun 2026 |
| Occupational CertificateFile: OC plan 1_opt Set1.pdf | 26 Jun 2026 |
| Occupational CertificateFile: OC plan - Copy_opt Set 2.pdf | 26 Jun 2026 |
| Occupational CertificateFile: OC plan - Copy (2)_opt Set 3.pdf | 26 Jun 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Final.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 rev ised.pdf | 25 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 Dec 25 Final.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Sep 2026_opt.pdf | 25 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Dec 25 final_opt.pdf | 25 Jun 2026 |
| Form 5 (FY 2024-2025)File: Form 5 2025 1.pdf | 25 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form 5 2026 1.pdf | 25 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 June 25.pdf | 19 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 June 25.pdf | 19 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 June 2025.pdf | 19 Sep 2025 |
| Form 5 (FY 2022-2023)File: Form 5 march 23.pdf | 13 Sep 2025 |
| Form 5 (FY 2023-2024)File: Form 5 march 24.pdf | 13 Sep 2025 |
| Layout approvalFile: Amended Plan.pdf | 1 Aug 2025 |
| Commencement certificateFile: CC.pdf | 1 Aug 2025 |
| Form 1File: FORM 1 March 25.pdf | 1 Aug 2025 |
| Form 2File: Form 2 March 25.pdf | 1 Aug 2025 |
| Form 3File: Form 3 March 2025.pdf | 1 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Flat Sold unsold.pdf | 1 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: Self Declaration.pdf | 1 Aug 2025 |
| Form 2A (FY 2022-2023)File: Form 2A march 23.pdf | 1 Aug 2025 |
| Form 2A (FY 2023-2024)File: Form 2A march 24.pdf | 1 Aug 2025 |
| Form 2A (FY 2024-2025)File: Form 2A march 25.pdf | 1 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUN SUMIT JEEVAN MANGAL PHASE 1.pdf | 30 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUN SUMIT JEEVAN MANGAL PHASE 2.pdf | 30 Oct 2023 |
| Proforma of Agreement for saleFile: JEEVAN MANGAL_DRAFT AGREEMENT.pdf | 18 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Jeevan Mangal.pdf | 1 Jun 2022 |
| Layout approvalFile: 1.pdf | 28 May 2022 |
| Layout approvalFile: 2.pdf | 28 May 2022 |
| Layout approvalFile: 3.pdf | 28 May 2022 |
| Layout approvalFile: 4.pdf | 28 May 2022 |
| Layout approvalFile: 5.pdf | 28 May 2022 |
| Layout approvalFile: 6.pdf | 28 May 2022 |
| Layout approvalFile: 7.pdf | 28 May 2022 |
| Layout approvalFile: 8.pdf | 28 May 2022 |
| Layout approvalFile: 9.pdf | 28 May 2022 |
| Building plan approvalFile: 1.pdf | 28 May 2022 |
| Building plan approvalFile: 2.pdf | 28 May 2022 |
| Building plan approvalFile: 3.pdf | 28 May 2022 |
| Building plan approvalFile: 4.pdf | 28 May 2022 |
| Building plan approvalFile: 5.pdf | 28 May 2022 |
| Building plan approvalFile: 6.pdf | 28 May 2022 |
| Building plan approvalFile: 7.pdf | 28 May 2022 |
| Building plan approvalFile: 8.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 2.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 3.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 4.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 5.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 6.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 7.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 8.pdf | 28 May 2022 |
| Copy of Layout Approval (in case of layout)File: 9.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 28 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 28 May 2022 |
| Copy of the legal title reportFile: Format A of Title Report Circular No 282022.pdf | 20 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg sun sumit jeevan mangal resize.pdf | 20 Apr 2022 |
| Details of encumbrancesFile: Undertaking cum No Claim Certificate.pdf | 18 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CCsigned.pdf | 18 Apr 2022 |
| Declaration about Commencement CertificateFile: form D Jeevan Mangal.pdf | 18 Apr 2022 |
| Declaration in FORM BFile: Form B 150422 JEEVAN MANGAL.pdf | 18 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch phase 1 sun sumit jeevan mangal resize.pdf | 18 Apr 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch phase 2 sun sumit jeevan mangal resize.pdf | 18 Apr 2022 |
| CERSAI detailsFile: CERSAI Search Report Jeevan Mangal.pdf | 18 Apr 2022 |
| Proforma of Allotment letterFile: Allotment Letter Jeevan Mangal 150422.pdf | 18 Apr 2022 |
| Proforma of Allotment letterFile: Jeevan Mangal RERA Agrrement sale.pdf | 18 Apr 2022 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Sun Sumit YashodhanP51800079912 | Andheri West, Mumbai Suburban | 38 | Mar 2025 | Certificate Signed | Dec 2027 | Not due yet |
| SUN SUMIT NAOMI ARKP51800080402 | Santacruz East, Mumbai Suburban | 20 | Jun 2025 | Ongoing | Oct 2027 | Not due yet |
| Sun Sumit DeepshalP51800046252 | Borivali, Mumbai Suburban | 80 | Jun 2022 | Ongoing | Dec 2026 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
Keep SUN SUMIT JEEVAN MANGAL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHIKUWADI BORIVALI WEST6,700+ in Mumbai Suburban
Hiranandani Bluecrest
SHODEN DEVELOPERS PRIVATE LIMITED
KANAKIA PRIVAASA TOWER 1 & 2
KANAKIA TRANSPARENT DEVELOPERS PRIVATE LIM
BHOOMI AIRAVAT
Bhoomi Shashwat Estate Private limited
Shraddha Paradise
Shraddha Prime Projects Limited
UNIQUE REGALIA
UNIQUE SHANTI DEVELOPERS LLP
NICCO VANASHRI AND NICCO HEIGHTS
NEW INDIA CONSTRUCTION COMPANY
See every Mumbai Suburban project, with the district possession charts
Builder: SUN SUMIT VENTURE
SUN SUMIT VENTURE has 4 registrations on MahaRERA, including SUN SUMIT JEEVAN MANGAL and Sun Sumit Deepshal. Its filings disclose 7 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SUN SUMIT JEEVAN MANGAL is delayed beyond 29 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUN SUMIT JEEVAN MANGAL?
The registered promoter entity is SUN SUMIT VENTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUN SUMIT JEEVAN MANGAL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SUN SUMIT JEEVAN MANGAL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUN SUMIT JEEVAN MANGAL?
The professionals named in the filing: Architect: NILESH MAKWANA; Architect: Swapnil Ambre; Engineer: HIREN TANNA; Engineer: Clint Santos; Chartered Accountant: PRIYANKA DHRUVA; Chartered Accountant: R S Gokani & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUN SUMIT JEEVAN MANGAL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback