Home / Browse projects / Mumbai Suburban, Maharashtra / SUMER LIFE
SUMER LIFE
RG-MH-04525 · RERA P51800024414 · Last updated on MahaRERA portal: 4 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 22 complaints at MahaRERA
- Completion date moved by 36 months
- 1 extension taken
- Rs 45.00 crore secured on the land, in favour of Edelweiss ARC
- The charge is held by Edelweiss ARC, a distressed-debt buyer or stressed-asset fund rather than an originating lender
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUMER LIFE is a Others project by SUMER CORPORATION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800024414 on 12 Feb 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 22 complaints are on record with the regulator.
At a glance
Project
- NameSUMER LIFE
- TypeOthers
- Location
- Chandivali
- Kurla
- Mumbai Suburban
- 400072
- Pincode400072
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800024414
- ReraGenie IDRG-MH-04525
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on12 Feb 2020
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2024)
- Buildings3 building records
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING -A | NA | 24 | 0 | 0 | 0 | 0 |
| WING -B | NA | 24 | 0 | 0 | 0 | 0 |
| WING - C | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 4 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 40%.
WING -A53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 16% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 6% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
WING -B53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 16% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 6% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
WING - C53%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 16% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 6% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Progress on shared amenities15
As on 4 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed336
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING -A | 118 | 0 | 118 |
| WING -B | 99 | 0 | 99 |
| WING - C | 118 | 1 | 119 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ashwin Parmar |
| Architect | S S Associates |
| Engineer | SK Consultants & Engineers |
| Engineer | JW Consultants LLP |
| Chartered Accountant | M/s. & Associates |
| Chartered Accountant | CA & Associates |
| Chartered Accountant | CA Rupesh Gupta |
| Partner | Role in project |
|---|---|
| SUMER CORPORATION | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800024414.As per HEARING DATED 10th July 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is uploaded in Other Tab for your reference
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 975/2010 | Bombay High Court | Pending |
Complaints filed with MahaRERA22
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500090 | Nandlal Maikulal Maurya | SUMER CORPORATION | 09/01/2025 |
| CC12500210 | Altamas Gulam Rasool Shaikh | SUMER CORPORATION | 21/01/2025 |
| CC12500389 | Mujeeb Khan Pathan | SUMER CORPORATION | 05/02/2025 |
| CC12500444 | Mujeeb Khan Pathan | SUMER CORPORATION | 10/02/2025 |
| CC12500446 | Mujeeb Khan Pathan | SUMER CORPORATION | 10/02/2025 |
| CC12500768 | Nenaram Jagaram Chaudhary | Mr Rahuul Ramesh Shah | 06/03/2025 |
| CC12500767 | Mr Jeevaram Jagaram Chaudhary | Mr Rahuul Ramesh Shah | 06/03/2025 |
| CC12500792 | Mujeeb Khan Pathan | SUMER CORPORATION | 08/03/2025 |
| CC12500793 | Mujeeb Khan Pathan | SUMER CORPORATION | 08/03/2025 |
| CC12500794 | Mujeeb Khan Pathan | SUMER CORPORATION | 08/03/2025 |
| CC12501145 | Mohammad Zuber Ahmed Siddiqui | SUMER CORPORATION | 05/04/2025 |
| CC12501195 | Abdur Rahman Siddiqui | SUMER CORPORATION | 09/04/2025 |
| CC12501235 | Mujeeb Khan Pathan | SUMER CORPORATION | 14/04/2025 |
| CC12501237 | Mujeeb Khan Pathan | SUMER CORPORATION | 14/04/2025 |
| CC12501238 | Mujeeb Khan Pathan | SUMER CORPORATION | 14/04/2025 |
| CC12501240 | Mujeeb Khan Pathan | SUMER CORPORATION | 14/04/2025 |
| CC12501267 | Mujeeb Khan Pathan | SUMER CORPORATION | 16/04/2025 |
| CC12501268 | Mujeeb Khan Pathan | SUMER CORPORATION | 16/04/2025 |
| CC12501269 | Mujeeb Khan Pathan | SUMER CORPORATION | 16/04/2025 |
| CC12501270 | Mujeeb Khan Pathan | SUMER CORPORATION | 16/04/2025 |
| CC12501430 | Mujeeb Khan Pathan | SUMER CORPORATION | 28/04/2025 |
| CC12501432 | Mujeeb Khan Pathan | SUMER CORPORATION | 28/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Feb 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_Sumer Life_ Dec 2024.pdf | 4 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_Sumer Life_ March 2025.pdf | 4 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Sumer Life_ Dec 2024.pdf | 4 Jul 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Sumer Life_ March 2025.pdf | 4 Jul 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 _Sumer Life_ March 2025.pdf | 4 Jul 2025 |
| Declaration in FORM BFile: FORM B_ SUMER LIFE.pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SL from 1 December 24.pdf | 4 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SL_ Form 3_ September 2024_compressed.pdf | 14 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SL_ Form 2_ September 2024.pdf | 14 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: 29_compressed.pdf | 14 Nov 2024 |
| Declaration in FORM BFile: Form B.pdf | 11 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SL - Form 1 Sept 2024.pdf | 11 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 30 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sumer Life_ Circular 29 _June 2024.pdf | 21 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Sumer Life _Encumbrance Finance Letter.pdf | 18 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Sumer Life _Encumbrance Litigation Letter.pdf | 18 Oct 2024 |
| Declaration in FORM BFile: Form B.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2023.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 2024.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ SL- June 2023.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ SL- June 2024.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ SL- March 2024.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ SL- December 2023.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ SL- September 2023.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SL- 30-06-2024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SL- 30-03-2024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SL- 30-09-2023.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SL- 30-06-2023.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SL- 30-12-2023.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A _ 2019-2020.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_ 2019-2020.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_ 2020-2021.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A _ 2020-2021.pdf | 18 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 18 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Sumer Life _Encumbrance Litigation Letter.pdf | 18 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Sumer Life _Encumbrance Finance Letter.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_ 2021-2022.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A _ 2021-2022.pdf | 18 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A _ 2022-2023.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2023-24.pdf | 18 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A _ 2023-2024.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Sumer Life as on December 2022.pdf | 17 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Sumer Life as on 31-03-2023.pdf | 17 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Sumer Life as on December 2022.pdf | 17 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Sumer Life as on 31-03-2023.pdf | 17 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sumer Life - Form 2 September 2022.pdf | 11 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life march 2022.pdf | 11 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life June 22.pdf | 11 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate 365.pdf | 11 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SUMER LIFE.pdf | 6 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Sumer Life 2021-2022.pdf | 1 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sumer Life Form 2- 31 March 2022_compressed.pdf | 27 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sumer Life Form 2- 30 June 2022_compressed.pdf | 27 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SUMER LIFE Dec 2021.pdf | 9 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SUMER LIFE march 2022.pdf | 9 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life June 2021.pdf | 9 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life September 2021.pdf | 9 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Life Dec 2021.pdf | 9 May 2022 |
| CERSAI detailsFile: Sumer Life.pdf | 9 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life June 2021.pdf | 9 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life Sept 2021.pdf | 9 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Life Dec 2021.pdf | 9 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Sumer Life FY 2019-20.pdf | 27 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Sumer Life FY 2020-21.pdf | 27 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumer Life_compressed.pdf | 25 Aug 2021 |
| Declaration about Commencement CertificateFile: Sumer Life.pdf | 22 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Form 3 March 2020 .pdf | 19 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Form 3 June 2020.pdf | 19 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Form 3 Dec 2020.pdf | 19 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Form 3 Sept 2020.pdf | 19 Jul 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sumer Life Form 3 March 2021_compressed.pdf | 19 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Sumer Life Retail (1).pdf | 20 May 2021 |
| Disclosure of sold/ booked inventoryFile: Sumer Life Residential (2)_compressed (2).pdf | 20 May 2021 |
| Building plan approvalFile: Binder1 (1)-1-4_organized.pdf | 24 Dec 2020 |
| Building plan approvalFile: Binder1 (1)-10-13_organized.pdf | 24 Dec 2020 |
| Building plan approvalFile: Binder1 (1)-5-9_organized_compressed_1-3.pdf | 24 Dec 2020 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Sumer Life | CTS NO 11A pt11 191to402 11D pt 16 16 1to92 19 19 1to28 20pt 25pt 25 1to32 50pt Chandivali | 327 | Completed | Jun 2024 | Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 104 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SUMER LIFE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chandivali6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 136 registered projects within 2 km.
AMARYLLIS TOWERS AND PLAZA
NAHAR BUILDERS LTD.
JANGID MEADOWS
JANGID HOME PVT LTD
NAHAR'S CHANDI VALLEY - PHASE I
NAHAR BUILDERS LIMITED
KABRA RESIDENCY PARK
AHINSA BUILDTECH PVT LTD
IBIS at L and T Realty Elixir Reserve
Larsen & Toubro Ltd. (Realty Division)
BARBET at L and T Realty Elixir Reserve
Larsen & Toubro Ltd. (Realty Division)
See every Mumbai Suburban project, with the district possession charts
Builder: SUMER CORPORATION
SUMER CORPORATION has 2 registrations on MahaRERA, including SUMER LIFE and SUMER LIFE CASA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SUMER LIFE is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUMER LIFE?
The registered promoter entity is SUMER CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUMER LIFE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SUMER LIFE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SUMER LIFE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUMER LIFE?
The professionals named in the filing: Architect: Ashwin Parmar; Architect: S S Associates; Engineer: SK Consultants & Engineers; Engineer: JW Consultants LLP; Chartered Accountant: M/s. & Associates; Chartered Accountant: CA & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUMER LIFE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback